Case Study - SPA Flashcards

1
Q

When taking over the project what was needed first leadership or management

A

Leadership to take control of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

By what methods did you use to analysise the problems you inherited on the project in order to decide which to tackle first?

A

I made a list of the important items, assessed their status, considered the impact for each item, and decided on priority in line with the tender programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What method did you use to assess the capacities of each of your staff?

A

Discussion on their previous experience for individual items as well as Q&A on how they would approach them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

At the staff assessment stage what was your management style?

A

I used an autocratic style to make quick decisions based on my discussions and assessments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Do you consider meeting with the individual members leadership or management?

A

I consider this management as I was essentially controlling the staff and their roles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was your contingency plan in one or more of your sub-contractors and not wanted to work?

A

Initially to go back to those that tendered for the works and determine if any suitable contractors would be willing to take on the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What was JCT’s advice about COVID at the time and did it vary over the life of the project

A

That ceasing works could be a breach of contract and that the primary consideration should be the H&S of the workforce and general public. All parties should discuss and agree on how the project should be dealt with within the parameters of the contract. Also to follow the CLC’s SOP. Initially could be considered as a relevant event but not for projects tendered after Covid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Did you consider the need to apply for an extension in time if so on what contractual basis would such a claim be made?

A

EoT would have to be considered if the virus caused a shortage of labour or materials, or delay caused by compliance with the SOP. It would be on the basis of being a Relevant Event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How often did you review your construction plan?

A

Approximately every 1-2 weeks or after any significant event such as a delay in procurement or material delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Although you met frequently with your commercial manger to review the budget what was the day to day control

A

The commercial manager was based on site in the same office so frequent discussions were had on a daily basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was your actual involvement with the financial control?

A

The CM was responsible for obtaining tender costs but meetings were had to agree that a contractor was suitable from a performance and cost point of view

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What “flag” did you have in place to give you warning of high expenditure items

A

The CM was to advise me if anything was likely to be excessively over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You refer to government guidance can you name 2 of the pieces of legislation when dealing with covid?

A

Not specifically. There was guidance on procurement policy and on responsible contractual behaviour in the performance and enforcement of contracts impacted by the Covid-19 emergency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You refer to the UK Government, Public Health England, and the Construction Leadership Council’s Site Operating Procedures- can you describe to me 2 of the measures in that document but not mentioned in your case study.

A
  1. Social distancing measures such as reducing the number of workers involved in each task or traveling to site together.
  2. Stopping non-essential visitors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you manage the design team?

A

By giving them target dates and frequent virtual meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What style of management did you adopt?

A

It was mostly democratic to agree achievable dates

17
Q

You give examples of how you managed the COVID crises on site but what measures did you take with the design team.

A

Instructed them not to visit site unless necessary, hold virtual meetings and follow general COVID advice to avoid infection

18
Q

How did you ensure that these were followed?

A

By frequent communication and providing photos of any site issues

19
Q

Can you describe to me some of the changes to your working practices that came about because of the COVID pandemic?

A

Virtual meetings, provision of photos to review site issues.

20
Q

Who acted as the Principal designer?

A

It was a private BCO company who also acted as the Principal designer

21
Q

Was your company the Principal contractor on the project, if so how did you manage the responsibilities?

A

Yes - Implementing a Construction Phase Plan, liaising with the client and principal designer, company H&S procedures and visits by Safety Advisor

22
Q

Can you give me an example of where you have used different style of management and why you felt it necessary

A

Due to delivery delays, there was a need to change the specification of light fittings to meet the programme dates. I had to take an autocratic approach to make this decision against the wishes of the architect.

23
Q

What makes a good leader?

A

Integrity, taking responsibility, inclusion

24
Q

What was the contract type for the project?

A

JCT Design & Build 2016

25
Q

What was the value of the project?

A

Tender sum was £13.6m rising to £15.2m with variations

26
Q

What was the programme duration?

A

47 weeks

27
Q

What design stage was tender?

A

Stage 3 to stage 6

Stage 1 - preparation and brief
Stage 2 - Concept design in line with project brief
Stage 3 - Developed design including architectural, services, structural
Stage 4 - technical design including spec
Stage 5 - construction drawings
Stage 6 - handover and close out - as-builts

28
Q

What were the main issues to be resolved?

A
  • Basic programme
  • site logistics (TFL, taxi rank, street access)
  • PW Agreements
  • Crane lift
  • COVID
29
Q

What contractural action could be taken if unable to work on the project due to covid?

A

The contract allowed entitlement to time but not costs for any covid related delays. Any issues could be addressed under force majeure

30
Q

What were the risk to the employer if work continued?

A

Sudden suspension of works, delays

31
Q

What was the cost reporting protocol?

A

Construction cost report monthly and valuations against forecast works and variations

32
Q

What items were included in the cost report to client?

A

Ongoing costs and forecast FA, including CAIs