Commercial management Flashcards
What RICS publication covers commercial management?
The ‘Black Book’ is a collection of technical practice documents which covers all processes throughout the construction project life cycle. The documents are essential development tools for junior professionals working through their APC and useful guides to best practice for more experienced professionals.
What is covered in the Black Book?
- cash flow forecasting
- change control and management
- commercial management of construction
- conflict avoidance and dispute resolution
- construction security and performance
- cost reporting
- defining completion on construction projects
- e-tendering
- employers agent - D&B
- final account procedures
- fluctuations
- interim valuations and payment
- monitoring surveyor
- life cycle costing
- management of risk
- retention
- subcontracting
- tendering strategies
- termination of contract
- value management
- valuing change
What does the guidance note on Cash Flow Forecasting (1st edition) include?
- explains what cash flow forecasting is, how to produce one, and how to use as a measure of progress
Minimum level of service includes:
* taking brief from employer for requirements of a cash flow forecast
* produce cash flow forecast at feasibility stage so employer has understanding of obligations
* update cash flow forecast throughout stages of construction
* monitor payments against cash flow forecast
What are the two types of cash flow forecast?
There are two main types of cash flow forecast:
* The cash flow forecast of a company (i.e. a contractor or consultant) – otherwise known as organisational cash flow.
* The cash flow forecast of a particular construction contract or project – otherwise known as project cash flow.
Why is knowledge of cash flow forecasts important?
In simple terms the purpose of a cash flow forecast is to ensure that the employer has an accurate assessment of what needs to be paid to the contractor and at what periods, therefore the employer’s bank or funder needs to be aware of draw-downs to manage the movement of funds to meet the contractual timescales of payment.
Various parties within a construction contract use cash flow forecasts for different reasons and it is therefore not uncommon to present cash flow forecasts in different ways to fit the requirement.
What is a monitoring surveyor?
Banks will often employ bank monitoring specialists (often quantity surveyors) to ensure that the contractor’s drawdown requests are in line with the original cash flow forecast and to provide an explanation if it differs. The employer can be liable for penalties, interest charges and arrangement fees for securing an accelerated fund, from their funder if the drawdown is markedly less or in excess of the drawdown schedule.
What is the most common use of a cash flow forecast?
The most common use of a cash flow forecast for a quantity surveyor is to monitor the progress of the works on site against the agreed programme. It is equally important that this done between the main contractor and their subcontractors. This becomes more accurate than using an S-curve as it is based on an agreed sequence of events rather than a formula. It is also therefore very useful in assessing whether a contractor is on programme or not. If the interim valuations are ahead of cash flow then this can signify that the works are ahead of programme. If the interim valuations are behind cash flow then this can signify that the works
are behind programme.
How does a forecast affect cashflow?
All parties know their liability and when to expect payment. Delays in payments, disputes with clients or renegotiation of overdraft terms can have disastrous consequences to the future of businesses and affect the contract progress.
What stakeholders may be involved in a cash flow forecast?
- funders
- shareholders
- client
- contractors
- subcontractors
- suppliers
- consultants
How does an organisational (company) cash flow forecast help?
Cash flow forecasts are often used within a company to manage resources. Resources may include staff, training, equipment, premises, etc. Companies must be sure that they can meet the liabilities in terms of wages, insurances and other overheads before employing additional staff. An organisational cash flow forecast can help to inform these decision making processes.
What are the types of valuation?
- stage payments - pre-agreed payments at set times regardless of progress
- milestone payments - pre-agreed payments at milestones
- payment against an activity schedule - At pre-agreed timescales progress against an activity schedule is monitored and pre agreed payments are made for activities which have been completed
- valuation of works to date - At pre-agreed periods the value of work on site is assessed
What legislation refers to construction payments?
‘The Construction Act’, The Housing Grants, Construction and Regeneration Act (HGCRA) 1996 fundamentally attempted to improve payment practices in the construction industry by improving cash flow and helping to resolve disputes quicker.
* right to interim or periodic payments
* contract has a mechanism to determine what payments are due and when
* payer must provide payee early notification
* Providing that the payee may suspend performance where a sum due is not paid in full by the final date for payment
* Providing a statutory right to refer disputes to adjudication.
What is the S-curve?
The S-curve stands for ‘standard’ curve but it also takes the shape of the letter ‘S’ when shown on a graph. This represents the lower level of periodic expenditure at the beginning of a contact (due to site set up and relatively inexpensive enabling works) and the lower level of expenditure at the end of a contact (due to the vast majority of materials being on site, reduced number of trades on site and reduction of contractor’s staff overhead). These S-curves are ascertained by formula, which uses data from previously similar construction projects.
What is a good way to produce a cash flow forecast?
Wherever possible the cash flow forecast should be written in conjunction with the main contractor who will often be able to provide more detailed and specific information. It should be noted that there is generally a difference in the approach to producing a cash flow forecast between an employer and a contractor.
Type of questions prior to producing a cash flow forecast?
- Is it for the employer or contractor?
- Should it be produced for the whole development or just the construction contract?
- Should it show values at valuation date, certificate date, invoice date or payment date?
- Should gross or net values be used?
- Should it show cumulative payments, monthly payments or both?
An employer must decide whether the cash flow forecast is to show the valuation date, certificate date, invoice date or actual payment date. Whatever is decided must be clearly noted in the cash flow forecast; otherwise a problem could arise if the employer assumed that the valuation date was shown when it was actually showing the payment date.
When would you require separate cash flow forecasts?
There may be separate enabling works and main works contracts and these may even overlap in some scenarios. If any of the separate contacts are of substantial value then it is worth producing separate cash flows and merging the data to produce an overall development cash flow.
What is important with cash flow forecasts?
Ensuring it reflects subcontractors stages i.e. 1st fix will be cheaper than 2nd fix of expensive fittings, similarly, testing and commissioning will be lower.
Holidays such as easter and Christmas will need to be reflected
How is retention included in forecast?
An accurate cash flow forecast will have to take account of retention, especially when showing the net payment at the end of each month. It will also mean that there will be a long period between practical completion and the final certificate where the cash flow is static, with a final jump at the end, which signals the return of the final part of retention
What is a rectification period?
Sometimes known as a defects liability period, a fixed term for the contractor to complete defects prior to final payment certificate.
What is a payment period?
The payment period is the time lag between the payment certificate being issued and the payment being made. The standard time lag is normally 14 days in a standard form of contract but can substantially differ if client amendments have been made to the contract.
How are variations covered in CF forecast?
Variations should be included along with likely costs and additional time if needed
How are risks forecast?
The New Rules of Measurement for Estimating and Cost Planning calls for risks to be split between four categories:
* Design development risks
* Construction risks
* Employer change risks, and
* Employer other risks.
How are materials on site included in CF forecast?
The quantity surveyor should not allow payment to be made for materials which are brought onto site well in advance just to boost the contractor’s cash flow. A cash flow forecast should be carried out on the assumption that materials will be brought onto site as and when required unless otherwise stated.
How are materials off-site covered in CF forecast?
Pre-assembled items may be considered as complete and payment may be due earlier. This will need to be agreed.
What is the minimum level of service for change control?
A chartered quantity surveyor is expected to be able to fulfil the following duties as part of the core competency Contract practice, notwithstanding the terms of any appointment or contractual obligation:
* demonstrate knowledge and understanding of the various forms of contract used in the construction industry and the change control procedures they contain, along with the digital portals available for some contracts that can be used to control change on projects
* apply that knowledge at a project-specific level while being aware of the implications and obligations of the parties involved in the change control procedure and
* provide reasoned advice on the effect of the change control procedure, be able to prepare and present reports to employers to determine the correct change control procedure to use and advise on the correct documentation and procedure at the various stages of a construction contract.
How are changes actioned?
- procedures included in contract (who and how)
- identify the reason and and impact on costs and time
What are the types of changes?
Changes can be divided into two principal categories as follows:
* changes from within the contractor’s own organisation that do not involve the employer (design change or change of spec)
* changes specifically requested by the employer.
Examples of change
- request by employer or contractor
- value engineering
- unforeseen ground conditions or change to specified items
- scope gaps
What is a risk register and who is responsible for risks?
A risk register helps manage risks and includes the probability, controls. Can be apportioned to the contractor in D&B contract
When can changes be applied?
pre-contract at end of design concept or during tender process
post-contract - changes to scope or instruction of PS
When can changes be applied?
pre-contract at end of design concept or during tender process
post-contract - changes to scope or instruction of PS