Chapter 5: Creating the Project Schedule Flashcards

Core Topics: Activity Definition, Sequencing, Estimation, Scheduling Techniques (CPM, PERT), Kanban, and Scrum

1
Q

What is the Schedule Management Plan?

A

The schedule management plan defines how the project schedule will be developed, monitored, and controlled throughout the project lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Define Activities process?

A

Define Activities is the process of identifying and documenting the specific actions required to produce the project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a milestone in project scheduling?

A

A milestone is a significant point or event in the project that marks the completion of major deliverables or phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Work Breakdown Structure (WBS) used for in scheduling?

A

The WBS is used to break the project work into smaller, more manageable components, which are then used to define activities and build the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Sequence Activities process?

A

Sequence Activities involves identifying and documenting the relationships among project activities, creating the logical flow of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are predecessors and successors in activity sequencing?

A

A predecessor is an activity that must be completed before another can start, while a successor is an activity that follows a predecessor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is float (or slack) in project scheduling?

A

Float is the amount of time an activity can be delayed without delaying the project completion date or the start of subsequent activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four types of dependencies in scheduling?

A

Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), Start-to-Finish (SF).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the critical path?

A

The critical path is the longest sequence of activities in a project that must be completed on time for the entire project to be completed on schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Critical Path Method (CPM)?

A

CPM is a scheduling technique that determines the longest path through the project, identifying the shortest possible project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Program Evaluation and Review Technique (PERT)?

A

PERT is a statistical tool used to analyze and represent the tasks involved in completing a project, calculating expected durations using optimistic, pessimistic, and most likely estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for PERT?

A

(Optimistic + 4 × Most Likely + Pessimistic) / 6.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a Gantt Chart?

A

A Gantt chart is a visual representation of the project schedule, showing tasks, durations, dependencies, and progress over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is resource leveling?

A

Resource leveling is a technique used to adjust the project schedule to account for resource constraints, ensuring that resources are not over-allocated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is resource smoothing?

A

Resource smoothing adjusts the schedule within predefined limits (without changing the critical path) to balance resource allocation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Kanban boards used for in Agile project management?

A

Kanban boards visually manage workflow by tracking tasks as they move through stages such as “To Do,” “In Progress,” and “Done.”

16
Q

What is the Scrum Board?

A

A Scrum Board is a tool used in Scrum to track the progress of work during a sprint, showing user stories, tasks, and progress toward completion.

17
Q

What is a burndown chart in Agile?

A

A burndown chart shows the remaining work in a sprint or project over time, helping to track progress and predict completion.

18
Q

What is Schedule Compression?

A

Schedule compression involves techniques like crashing and fast-tracking to shorten the project duration without reducing the project scope.

19
Q

What is the difference between crashing and fast-tracking?

A

Crashing involves adding resources to critical path activities, while fast-tracking involves performing activities in parallel that were originally scheduled sequentially.

20
Q

What is the Develop Schedule process?

A

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and constraints to create the project schedule.

21
Q

What are lag and lead in scheduling?

A

Lag is the delay between activities, while lead allows activities to overlap, starting the successor activity before the predecessor finishes.

22
Q

What is Schedule Baseline?

A

The schedule baseline is the approved version of the project schedule, which is used as a basis for comparison throughout the project.

23
Q

What is rolling wave planning?

A

Rolling wave planning is an iterative approach where near-term activities are planned in detail, while future work is planned at a higher level until it becomes clearer.

24
Q

What is the Critical Chain Method (CCM)?

A

CCM is a scheduling technique that focuses on resource constraints, using buffers to protect critical chain tasks and prevent delays.