Chapter 11: Monitoring and Controlling Project Work Flashcards
Core Topics: Project Monitoring, Change Control, Earned Value Management (EVM), and Corrective Actions.
What is the purpose of the Monitoring and Controlling Process Group?
The Monitoring and Controlling Process Group tracks, reviews, and regulates project performance and progress to ensure that project objectives are met.
What is the role of the Change Control Board (CCB)?
The CCB is a formally constituted group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, ensuring that only beneficial changes are implemented.
What is the Perform Integrated Change Control process?
Perform Integrated Change Control is the process of reviewing all change requests, approving or rejecting them, and managing their implementation throughout the project.
What is the Monitor and Control Project Work process?
Monitor and Control Project Work involves tracking, reviewing, and reporting project progress to meet the performance objectives defined in the project management plan.
What are the key components of a change request?
A change request includes the proposed change, the reason for the change, the impact on the project scope, schedule, cost, and quality, and any recommendations.
What is Earned Value Management (EVM)?
EVM is a project performance measurement technique that integrates scope, cost, and schedule to assess project progress and performance against the plan.
What is Planned Value (PV) in EVM?
Planned Value (PV) is the authorized budget assigned to scheduled work that should have been completed by a specific time.
What is Earned Value (EV) in EVM?
Earned Value (EV) is the value of work actually performed expressed in terms of the approved budget for that work.
What is Actual Cost (AC) in EVM?
Actual Cost (AC) is the total cost incurred for the work performed on a project at a specific point in time.
What is Schedule Variance (SV)?
Schedule Variance (SV) is the difference between the work planned and the work performed, calculated as SV = EV – PV.
What is Cost Variance (CV)?
Cost Variance (CV) is the difference between the budgeted cost of work performed and the actual cost, calculated as CV = EV – AC.
What is the Schedule Performance Index (SPI)?
The SPI is a measure of schedule efficiency, calculated as SPI = EV / PV. An SPI greater than 1 indicates ahead of schedule, while less than 1 indicates behind schedule.
What is the Cost Performance Index (CPI)?
The CPI is a measure of cost efficiency, calculated as CPI = EV / AC. A CPI greater than 1 indicates under budget, while less than 1 indicates over budget.
What is Estimate at Completion (EAC)?
EAC is the expected total cost of completing the project, based on current performance, and can be calculated using various formulas depending on the scenario.
What is Variance at Completion (VAC)?
VAC is the difference between the original budget and the expected total project cost, calculated as VAC = BAC – EAC.