The Contract Documents:
Where is this detailed in the AIA docs?
- Where are the contract document enumerated in the AIA docs?
- What contract docs are not included in the list of enumerated docs?
- What documents are NOT part of the contract docs
- What is included in Contract Docs?
The Contract Documents:
A101 & A201
- A101
- Modifications (after contract signed)
- Advertisement, instruction, or invitation to bid
- included in the Contract Docs
1. contract
2. Conditions of contract
3. Drawings
4. Specs
5. Addenda
6. Modifications
Date of Commencement:
AIA location? (hint-4 places)
- name the 3 options for commencement date?
- Why does this matter?
Date of Commencement:
A101, B101…also B201 initial info, A201
- Three options for commencement date:
1. date of contract sign (default)
2. Notice to proceed date
3. Other
-Why does this matter?
date of commencement is the start of the “contract time”
Contract sum:
AIA location?
Contract sum:
A101
Payment:
AIA location:
a. time period covered by each pay app?
b. can contractor make advance payments for items not already stored on site?
Payment:
A101 (also B101 but that not what we care about here)
a. Calander month, ending on last day
b. no, not without owner approval
Dispute Resolution in A101
What does it say about it here?
- it says see A201
Termination in A101
What does it say about it here?
- it says see A201
Enumerated contract docs:
AIA location?
Enumerated contract docs:
A101
Main diff between A101 and a201
Sections of A101? 9
A201?
For info only don’t memorize
A101.
1.list of doc/ contracts included
- Payment and retention.. Simple
- Dates.. Start and substantial
- See A201 for disbutes, termination, misc, and dtl info
A201
1. Team
- Details on payments, changes, disbutes, termination
- Insurance and bonds
- See A101 for cost and dates
……
….
1. The contract documents
- The work of this contract
- Date of comensment and substantial completion
- Contract sum
- Payments
- Dispute Resolution
- Termination
- Misc
- Enumeration of contract docs
.
A201
- General povisions
- Owner, Arch, contractors, subs
- Construction by owner
- Changes
- Time
- Payments and completion
- Insurance and protections
- Corrections and uncovering
- Termination
- Claims and disbutes