3.3.4 Critical Path Analysis Flashcards

1
Q

What is critical path analysis?

A

The process of planning the sequence of activities in a project in order to identify the most efficient strategy for competition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the aim of critical path analysis?

A

The aim is to complete the project in the shortest time possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the rules for constructing a critical path analysis?

A

1) work from left to right (add)
2) Focus on EST first
3) Take the highest value-adding the time taken
4) get to the end
5) Duplicate the number
6) Go back working right to left (minus)
7) Take the lowest value minusing time
8) Back to 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the critical path?

A

A path that shows tasks that must be prioritised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does it mean if a task is on the critical path?

A

the task must be prioritised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does it mean if a task is not on the critical path?

A

there is more flexibility around the task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you indicate the critical path on a diagram?

A

using two parallel lines on the task line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do network diagrams/critical path analysis show?

A

1) The order of tasks
2) length of each stage
3) earliest date at which other stages start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the EST?

A

Earliest start time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the LFT?

A

Latest finish time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the structure of a node in a critical path analysis?

A

The left half of the circle is the node containing the unique activity.
The top right section shows the EST
The bottom right section shows the LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What do you do moving from left to right?

A

Add the duration to the EST (in the top right)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you do moving from right to left?

A

Take the lowest value minusing the largest duration = LFTs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is float time?

A

Flexibility you have to complete tasks not on the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you work out total float?

A

LFT - duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the positives of using critical path analysis?

A

+ smooth operations, shorterns project length, good for problem-solving
- not useful for complex operations?, activity lines aren’t proportional

17
Q

What does float tell us?

A

Actual float tells us the degree of flexibility (hours/days..) to complete a particular task whilst still completing the project within the time frame.

18
Q

What are the uses of a critical path analysis?

A
  • to estimate and minimise project time
  • support project costing and evaluation
  • plan and organise resources
  • prioritise tasks
  • help provide direction (improved motivation)
19
Q

What are the positives of using critical path analysis?

A

+ helps reduce risk and costs, + ensures accuracy during planning,
+ decision-making tool,
+ can shorten project length, spot where activities have some slack (float),
+ helps with coordination

20
Q

What are the negatives of using critical path analysis?

A
  • reliability based off of accurate estimates and assumptions, CPA doesn’t guarantee success, too many activities may complicate the diagram, dependent on non-fixed variables e.g. weather/resources of capital