Valuation Level Three Flashcards
Tell me about how you have used a sensitivity analysis to produce a reasoned analysis of risk.
Tell me about a development appraisal you have used to advise on the acquisition/disposal of a development site.
Tell me about an example of when you have provided reasoned advice on an appropriate source of development finance.
And what measurement basis do you calculate your bill costs?
GIA basis
How do you work out your contingency rate?
Typically this range is between five and 10% dependent on risk.
Where does the information provided by BCIS come from?
This is an RICS service. Updates are obtained monthly from recent contract prices/tenders agreed.
What are three levels of debt?
Senior debt
Secondary funding
Mezzanine funding
What is a profit erosion period?
The length of time it takes for the development profit to be eroded by holding charges following completion.
What is included in the preconstruction period?
This could be:
Site assembly
Obtaining vacant possession
Planning
Agreeing architectural designs
Soil investigations
What is included in the construction period?
Decontamination
Demolition
The main build