Risk Management Flashcards
What are the stages of risk management?
Identify
Analyse
Respond
Monitor
What are the various risk response strategies?
Retain
Reduce
Transfer
Avoid
Share
What are the NRM risk categories?
Employer Change Risk
Employer Other Risk
Design Development Risk
Construction Risk
What is the key to good risk management?
Ownership of risks.
Identifying as many risks as possible, quantifying them as much as possible.
Ensuring that the party most able to take on the risk does so.
Monitoring & recording
What happens to risk allowances if the risk does not occur?
If it’s a central contingency pot, this should be reduced proportionally as the project progresses. If there are allowances contained within various works packages then I would release them into the central contignency pot
There are 2 methods of reporting general risk allowances
1) General risk allowance maintenance method
2) General risk allowance progressive release method
1) Costs incurred for which no other provision was made in the budget should be set against the general risk allowance. The balance of remaining risk allowance is maintained through the project
2) Costs incurred for which no other provision was made in the budget should be set against the general risk allowance. The balance of remaining risk allowance is progressively reduced on an agreed basis, either pro-rata to completion date or pro-rata % completion of cost
Can you give me some examples of risk in a construction project?
External risks: econoic, legal, political (BREXIT)
Financial risks: exchange rate, funding, inflation, solvency
Site risks: restricted site, occupied site, planning difficulties
Client risks: lack of experience, mulit-headed client, likelihood of post-contract changes, failture to take bond,
Design risks: inapproproate consultant team, poor brief, incomplete design, co-ordination
Contrcator selection: inadequate selection process
Construction: weather, buildability, H&S, availability of resources
Ground conditions, limitations in liability, sequencing, design, economics
What is central limit theory?
It is a method of risk allowance qunatification based on the average of previous projects
It is a risk analysis tool which calculates a contingency pot allowance with 90% degree of certainty
What is the difference between qualitative and quantitative risk management?
Quantitative quantifies risks numerically 1-5
Qualitative categorises them in descriptive terms such as low to very high
What is an issue?
It is something that is occurring now. i.e. a risk that has already materialised.
An event which has either occurred or certainly accorded and will impact the forecast final cost and / or programme
What common risks affect construction projects?
Pricing fluctuations post tender
Client unable to secure funding
Ground obstructions
Contamination
How are risk registers used?
Used to Identify, Analyse, Respond to and Monitor risks
How does procurement route affect risk?
Procurement route affect the apportionment of risk.
E.G D&B v MC
Some routes reduce risk to the client however this risk will be included in the contractor’s tender price.
What is a risk
A risk is an uncertainty which have have a positive or negative effect on a project
Risk is an uncertainty which has a positive or negative effect on a project
To quantify risks so we know what an appropriate risk pot would be
Also to idenfiy which risks pose the greatest threat to the scheme
Identify risk management strategies and risk champions in order to transfer / control / reduce / eliminate these
What is the least risky procurement strategy? How do you mitigate the risks within it?
Not one of the procurement strategies is universally least risky, as it depends on the parameter s of each scheme. For example a D&B procurement route might be the least risky for say a warehouse with limited design needs, but the most risky for a project where vast engineering is needed (perhaps a laboratory or nuclear facility)
D&B as cost and time is fixed. Quality / design could be the risk. Mitigate it by making sure the ER documents are thorough, design to stage 3, novate design team, little changes from Ers.