Ting du må øve på Flashcards

1
Q

Hvordan regne ny CPI?

A

Gjenstående arbeid / Gjenstående budsjett

Gjenstående arbeid = BAC - BCWP
Gjenstående budsjett = BAC - ACWP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

ETAC =

A

tid / SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ECAC =

A

Acwp + ( ( BAC - BCWP) / CPI) )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CPI =

A

BCWP / ACWP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SPI =

A

BCWP / BCWS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Hvor finner du BAC?

A

I tabellen under akkumulerte kostnader og hvilken uke det gjelder ( står som regel i oppgaveteksten)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Hvordan regner man kostnad for crashing av aktiviteter?

A

Crash kostnad - Normal kostnad / Normal tid - crash tid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

BCWP =

A

% av fullført aktivitet * kostnad for hele aktiviteten

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

BCWS =

A

Finner tall i tabell i akkumulert kostnad (oppgis i oppgave hvilken uke/dag der er)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly