The Foundation Exam 1 Flashcards
1. All 75 questions should be attempted. 2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial. 3. All answers are to be marked on the answer sheet provided. 4. Please use a pencil and NOT ink to mark your answers on the answer sheet provided. There is only one correct answer per question. 5. You have 1 hour for this paper. 6. You must get 35 or more correct to pass.
1 Which is one of the six aspects of project performance that needs to be managed?
a) Accuracy
b) Reliability
c) Scope
d) Ease of use
1 Syllabus Topic:OV0101 - Overview and Principles
Correct Answer:C
Objective:LL1 - Recall the six aspects of project performance to be managed.
a) Incorrect. May be an acceptance criterion, but this is NOT one of the six aspects of
project performance that need to be managed. The six aspects are cost, timescale,
scope, quality, risk and benefits. Ref 1.5.2
b) Incorrect. May be an acceptance criterion, but this is NOT one of the six aspects of
project performance that need to be managed. The six aspects are cost, timescale,
scope, quality, risk and benefits. Ref 1.5.2
c) Correct. One of the six aspects, together with costs, timescales, quality, risk and
benefits. Ref 1.5.2
d) Incorrect. May be an acceptance criterion, but this is NOT one of the six aspects of
project performance that need to be managed. The six aspects are cost, timescale,
scope, quality, risk and benefits. Ref 1.5.2
2 What theme ensures the project is desirable, viable and achievable?
a) Organization
b) Progress
c) Business Case
d) Risk
2 Syllabus Topic:BC0201 - Business Case Theme
Correct Answer:C
Objective:LL2 - Understand the purpose of the Business Case theme.
a) Incorrect. The Organization theme defines and establishes the project’s structure of
accountability and responsibilities. Ref 5.1
b) Incorrect. The Progress theme establishes mechanisms to monitor and compare actual
achievements against those planned and provides a forecast for the project’s continued
viability. Ref 10.1
c) Correct. The Business Case theme drives decision-making throughout the project and is
used to assess if the project remains viable and benefits can be realized. Ref 4.1
d) Incorrect. The Ris
3 What process is triggered by the Project Manager’s request to initiate a project?
a) Starting up a Project
b) Initiating a Project
c) Directing a Project
d) Managing a Stage Boundary
3 Syllabus Topic:DP0203 - Directing a Project Process
Correct Answer:C
Objective:LL2 - Understand the context of the Directing a Project process.
a) Incorrect. The Starting up a Project process prepares for the authorization of the
initiation stage. The request to initiate the project is an action carried out during the
Starting up a Project process. Ref 12.1
b) Incorrect. The Initiating a Project process prepares documentation to be submitted to the
Project Board for project authorization, but the actual authorization comes from the
Directing a Project process. Ref 14.3
c) Correct. Only the Project Board can authorize project initiation, and its activities are
covered in the Directing a Project process. Ref 13.3
d) Incorrect. The Managing a Stage Boundary process prepares material to request
authorization of a stage from the Project Board. Ref 17.1
4 The purpose of which theme is to establish mechanisms to monitor and compare actual
achievements against those planned?
a) Business Case
b) Change
c) Progress
d) Quality
4 Syllabus Topic:PG0202 - Progress Theme
Correct Answer:C
Objective:LL2 - Understand the purpose of the Progress theme.
a) Incorrect. The purpose of the Business Case theme is to establish mechanisms to judge
whether the project is desirable, viable and achievable as a means to support decision
making in its investment. Ref 4.1
b) Incorrect. The purpose of the Change theme is to identify, assess and control any
potential and approved changes to the baseline. Ref 9.1
c) Correct. The purpose of the Progress theme is to establish mechanisms to monitor and
compare actual achievements against those planned; provide a forecast for the project
objectives and the project’s continued viability, and control any unacceptable deviations.
Ref 10.1
d) Incorrect. The purpose of the Quality theme is to define and implement the means by
which the project will create and verify products that are fit for purpose. Ref 6.1
5 Which is an objective of the Closing a Project process?
a) Check that all the project’s products have been accepted by the users
b) Prepare for the final stage of the project
c) Capture the customer’s quality expectations
d) Ensure that all benefits have been achieved
5 Syllabus Topic:CP0202 - Closing a Project Process
Correct Answer:A
Objective:LL2 - Understand the objectives of the Closing a Project process.
a) Correct. To verify user acceptance of a project’s products. Ref 18.2
b) Incorrect. The Closing a Project process occurs during the final stage, which is
prepared during the Managing a Stage Boundary process, as for any other stage, except
for the initiation stage. Ref 18.3
c) Incorrect. The customer’s quality expectations are defined and agreed early in the
Starting up a Project process. The expectations are captured in discussions with the
customer (business and user stakeholders) and then refined for inclusion in the Project
Product Description. Ref 12.4.4
d) Incorrect. NOT all benefits may have been achieved before the project closes. Some will
be measured post-project as part of a benefits review. Ref 18.4.3
6 Identify the missing words in the following sentence.
A purpose of the Managing a Stage Boundary process is to provide the Project Board with
sufficient information so that it can approve the [ ? ] for the next stage.
a) Work Packages
b) Exception Report
c) Stage Plan
d) Project Brief
6 Syllabus Topic:SB0201 - Managing a Stage Boundary Process
Correct Answer:C
Objective:LL2 - Understand the purpose of the Managing a Stage Boundary process.
a) Incorrect. Work Packages are authorized by the Project Manager during the Controlling
a Stage process. Ref 15.4.1
b) Incorrect. An Exception Report may trigger the Managing a Stage Boundary process if
an Exception Plan is required. Ref 15.4.7
c) Correct. A purpose of the Managing a Stage Boundary process is to provide sufficient
information to the Project Board, so that it can review the success of the current stage
and approve the next Stage Plan. Ref 17.1
d) Incorrect. The Project Brief is approved by the Project Board following the Starting up a
Project process, and before the Initiating a Project process. Ref 13.4.1
7 Which theme provides information on what is required, how it will be achieved and by whom?
a) Organization
b) Plans
c) Business Case
d) Quality
7 Syllabus Topic:PL0201 - Plans Theme
Correct Answer:B
Objective:LL2 - Understand the purpose of the Plans theme.
a) Incorrect. The purpose of the Organization theme is to define and establish the project’s
structure of accountabilities and responsibilities. Ref. 5.1
b) Correct. Planning provides all personnel in a project with information on what is required,
how it will be achieved and by whom, using what specialist equipment and resources,
when events will happen and whether targets are achievable. Ref 7.1
c) Incorrect. The Business Case is used to document the justification for undertaking the
project. Ref. 4.1
d) Incorrect. The purpose of the Quality theme is to define and implement the means by
which the project will create and verify products that are fit-for-purpose. Ref. 6.1
8 Which is recommended as a possible risk response type for an opportunity?
a) Reduce
b) Transfer
c) Reject
d) Fallback
8 Syllabus Topic:RK0102 - Risk Theme
Correct Answer:C
Objective:LL1 - Recall the risk response types and whether they are used to respond to a
threat or an opportunity.
a) Incorrect. Reduce is a proactive action taken to reduce the probability or the impact of a
threat occurring, by performing some form of control. Ref Table 8.2
b) Incorrect. Transfer is where a third party takes on responsibility for some of the financial
impact of a threat. Ref Table 8.2
c) Correct. Reject is where a conscious and deliberate decision is taken NOT to exploit or
enhance an opportunity, having discerned that this is more economical than to attempt
an opportunity response action. Ref Table 8.2
d) Incorrect. Putting in place a fallback plan for the actions that will be taken to reduce the
impact of a threat should it occur. This is a reactive form of reduce response which has
no impact on likelihood. Ref Table 8.2
9 Basing projects on a ‘management by exception’ principle provides which benefit?
a) Promotes consistency of project work and staff mobility
b) Provides a common language
c) Clarity of what a project will deliver, why, when and by whom
d) Efficient and cost-effective use of management time
9 Syllabus Topic:OV0202 - Overview and Principles
Correct Answer:D
Objective:LL2 - Understand the seven principles.
a) Incorrect. Consistency of project work is a benefit derived from the use of PRINCE2
project documentation and processes. It facilitates staff mobility between projects and
reduces the impact of personnel changes/handovers. Ref 1.7
b) Incorrect. PRINCE2 is widely recognized and understood, and therefore provides a
common vocabulary for project participants. A common vocabulary is NOT a benefit
provided by the management by exception principle. Ref 1.7 / 2.5
c) Incorrect. A PRINCE2 project’s product focus provides the benefit of clarifying (for all
parties) what a project will deliver, why, when, by whom and for whom. Ref 1.7
d) Correct. PRINCE2 is based on a ‘management by exception’ framework, providing for
efficient and economic use of management time (whether at corporate, programme,
Project Board or project management level). It reduces their time burden without
removing their control by ensuring decisions are made at the right level in the
organization. Ref 1.7 / 2.5
10 Identify the missing words in the following sentence.
The purpose of the [ ? ] process is to establish solid foundations for the project, enabling the
organization to understand the work that needs to be done to deliver the project’s products.
a) Initiating a Project
b) Starting up a Project
c) Directing a Project
d) Managing a Stage Boundary
10 Syllabus Topic:IP0201 - Initiating a Project Process
Correct Answer:A
Objective:LL2 - Understand the purpose of the Initiating a Project process.
a) Correct. The purpose of the Initiating a Project process is to establish solid foundations
for the project, enabling the organization to understand the work that needs to be done
to deliver the project’s products before committing to a significant spend. Ref 14.1
b) Incorrect. The purpose of the Starting up a Project process is to ensure that the
prerequisites for initiating a project are in place by answering the question: do we have a
viable and worthwhile project? Ref 12.1
c) Incorrect. The purpose of the Directing a Project process is to enable the Project Board
to be accountable for the project’s success by making key decisions and exercising
overall control while delegating day-to-day management of the project to the Project
Manager. Ref 13.1
d) Incorrect. The purpose of the Managing a Stage Boundary process is to enable the
Project Board to be provided with sufficient information by the Project Manager so that it
can review the success of the current stage, approve the next Stage Plan, review the
updated Project Plan, and confirm continued business justification and acceptability of
the risks. Ref 17.1
11 Which is a purpose of the Managing Product Delivery process?
a) Controls the link between the Project Manager and the Team Manager(s)
b) Tracks the progress of a stage with the help of Checkpoint Reports
c) Provides a link between the work of the Project Manager and the Project Board
d) Maintains a focus on the delivery of benefits throughout the stage
11 Syllabus Topic:MP0201 - Managing Product Delivery Process
Correct Answer:A
Objective:LL2 - Understand the purpose of the Managing Product Delivery process.
a) Correct. The Managing Product Delivery process places formal requirements on
accepting, executing and delivering project work. Ref 16.1
b) Incorrect. This is the role of the Project Manager in the Controlling a Stage process.
Ref 15.4.4
c) Incorrect. This is an objective of the Controlling a Stage process. Ref 15.1
d) Incorrect. This is the role of the Project Manager in the Controlling a Stage process. Ref
15.2
12 Which role is responsible for authorizing and monitoring work to be completed and for taking
corrective action within a stage?
a) Project Manager
b) Project Support
c) Project Assurance
d) Team Manager
12 Syllabus Topic:CS0203 - Controlling a Stage Process
Correct Answer:A
Objective:LL2 - Understand the context of the Controlling a Stage process.
a) Correct. The Project Manager is responsible for controlling the day-to-day activities of
the stage. Ref 15.3
b) Incorrect. Project Support provides administrative support to the Project Manager, but is
NOT responsible for authorizing the work. Ref 5.3.2.8
c) Incorrect. Project Assurance reviews the activities of the stage, but is NOT responsible
for authorizing the work. Ref 5.3.2.3
d) Incorrect. The Team Manager agrees work with the Project Manager to be delivered as
part of a Work Package. Ref 5.3.2.7
13 Which fact is true of Project Assurance but not quality assurance?
a) Responsible for monitoring the conduct of the project
b) Independent of the Project Manager
c) Appointed as part of the project management team
d) Responsible for reviewing the project for compliance with corporate standards
13 Syllabus Topic:QU0202 - Quality Theme
Correct Answer:C
Objective:LL2 - Understand the difference between quality assurance and Project Assurance.
a) Incorrect. Both Project Assurance and quality assurance are responsible for monitoring
the project’s conduct. Project Assurance reports to the project’s stakeholders. Quality
assurance reports to the wider community. Ref 6.2.6
b) Incorrect. They are both independent of the Project Manager. Ref 6.2.6
c) Correct. Quality assurance is a function within the organization. Project Assurance is a
temporary role within the project management team. Ref 6.2.6
d) Incorrect. Both Project Assurance and quality assurance are responsible for assuring
that applicable standards are being used. Ref 6.2.6
14 Which is NOT a characteristic of a project?
a) Has a higher degree of risk than business as usual
b) Involves people with different skills introducing a change that will impact others outside of the
team
c) Has a lifespan that usually covers the delivery of the desired outcomes and the realization of
all the expected benefits
d) A temporary management structure created for the implementation of business products
14 Syllabus Topic:OV0203 - Overview and Principles
Correct Answer:C
Objective:LL2 - Understand the characteristics of a project.
a) Incorrect. Projects introduce threats and opportunities over and above those we typically
encounter in the course of stable business operations. Projects are more risky. Ref 1.3
b) Incorrect. The project environment involves a temporary team of people with different
skills working together to introduce change within the business environment. Ref 1.3
c) Correct. These are characteristics of a programme. Whilst projects do deliver outcomes
and benefits, many will NOT be realized until after the project has closed. Ref 19.4
d) Incorrect. Projects are temporary in nature. Once the change has been implemented the
need for the project is removed. Ref 1.3
15 Which product forms the ‘contract’ between the Project Manager and the Project Board for the
project?
a) Project Plan
b) Project Product Description
c) Project Initiation Documentation
d) Project Brief
15 Syllabus Topic:IP0204 - Initiating a Project Process
Correct Answer:C
Objective:LL2 - Understand the purpose of the Project Initiation Documentation.
a) Incorrect. A Project Plan states how and when the objectives will be achieved but is NOT
an agreement on what is to be delivered. That is defined in the Project Initiation
Documentation. Ref A.16
b) Incorrect. The Project Product Description is used in the Closing a Project process to
verify that the project has delivered what was expected, but is NOT a contract between
the Project Manager and the Project Board. Ref A.21
c) Correct. The Project Initiation Documentation forms the basis for the management and
overall success of the project and as such is the ‘contract’ between the Project Manager
and the Project Board. Ref A.20
d) Incorrect. Information in the Project Brief is NOT confirmed or detailed enough to form a
firm agreement and, after use in creating the Project Initiation Documentation, it is NOT
maintained. Ref A.19
16 Which is an objective of the Managing a Stage Boundary process?
a) Enable the Project Board to commit resources and expenditure required for the initiation stage
b) Review and, if necessary, update the Project Initiation Documentation
c) Provides a break between those managing the project from those creating products
d) Ensure a periodic review is held to approve the products created within the completed stage
16 Syllabus Topic:SB0202 - Managing a Stage Boundary Process
Correct Answer:B
Objective:LL2 - Understand the objectives of the Managing a Stage Boundary process.
a) Incorrect. Commencement of the initiation stage is approved by the Project Board during
the Directing a Project process, at the end of start up. This is NOT a stage boundary.
Ref 13.4.1
b) Correct. Review and, if necessary, update the Project Initiation Documentation (in
particular the Business Case, Project Plan, project approach, strategies, project
management team structure and role descriptions). Ref 17.2
c) Incorrect. It is the Managing Product Delivery process that provides the break between
the Project Manager and the teams delivering the products. Ref 16.1
d) Incorrect. Products are assessed and approved as and when they are completed during
the Managing Product Delivery process. These quality checks are NOT left until the end
of the stage. Ref 16.4.2
17 How should a Team Manager escalate a suggestion for an improvement to a product?
a) Include details in a Checkpoint Report
b) Include details in a Highlight Report
c) Raise an issue
d) Raise an Exception Report
17 Syllabus Topic:CH0204 - Change Theme
Correct Answer:C
Objective:LL2 - Understand the recommended steps in the issue and change control
procedure.
a) Incorrect. This is a request for change. Although a Team Manager may refer to it in a
Checkpoint Report it is NOT the vehicle to deal with a change. Ref 9.3.3
b) Incorrect. The Team Manager does NOT produce Highlight Reports. Ref 10.3.3.4
c) Correct. A Team Manager will raise it as an issue, but it is the Project Manager who
determines whether this should be dealt with as a formal Issue Report. Ref 9.3.3
d) Incorrect. The Team Manager does NOT raise Exception Reports. Ref 10.3.4
18 Which is a purpose of the Closing a Project process?
a) Define the procedure for handing over products
b) Provide a fixed point at which acceptance for the project product is confirmed
c) Define formal requirements for the acceptance, execution and delivery of project work
d) Confirm all project benefits have been achieved
18 Syllabus Topic:CP0201 - Closing a Project Process
Correct Answer:B
Objective:LL2 - Understand the purpose of the Closing a Project process.
a) Incorrect. This is done in the Initiating a Project process as part of defining the
Configuration Management Strategy. Ref 14.4.2
b) Correct. This is a purpose of the Closing a Project process. Ref 18.1
c) Incorrect. This is a purpose of the Managing Product Delivery process. Ref 16.1
d) Incorrect. NOT all project benefits will have been achieved at project closure. Ref 18.4.4
19 Which is an objective of the Starting up a Project process?
a) Confirm there are no known restrictions that would prevent the project from being delivered
b) Ensure all Team Managers understand their responsibilities
c) Get approval for the Project Plan from corporate or programme management
d) Prepare the Project Initiation Documentation for authority to initiate the project
19 Syllabus Topic:SU0202 - Starting up a Project Process
Correct Answer:A
Objective:LL2 - Understand the objectives of the Starting up a Project process.
a) Correct. An objective of the Starting up a Project process is to ensure time is NOT
wasted on initiating any projects that are based on unsound constraints etc. Ref 12.2
b) Incorrect. The project management team is designed during the Starting up a Project
process, but the actual Team Managers may NOT be appointed until the Managing a
Stage Boundary process. Ref 12.4.3
c) Incorrect. The Project Plan is created in the Initiating a Project process and approved by
the Project Board in the Directing a Project process. Ref 14.4.6 / 13.4.2
d) Incorrect. The Project Initiation Documentation is prepared in the Initiating a Project
process. Ref 14.3
20 Which process is used to provide an interface with corporate or programme management?
a) Managing Product Delivery
b) Directing a Project
c) Controlling a Stage
d) Managing a Stage Boundary
20 Syllabus Topic:DP0202 - Directing a Project Process
Correct Answer:B
Objective:LL2 - Understand the objectives of the Directing a Project process.
a) Incorrect. This process is used by Team Manager(s) to communicate with the Project
Manager within the Controlling a Stage process. Ref 16.1
b) Correct. This process ensures that corporate or programme management has an
interface to the project. It is a key role for the Project Board to engage with corporate or
programme management and to act as a communication channel. Ref 13.2 / 13.3
c) Incorrect. The Project Manager should report to and receive information from the Project
Board within this process. Ref 15.1
d) Incorrect. Products from this process will be provided to the Project Board in the
Directing a Project process for it to communicate with corporate/programme
management. Ref 17.1
21 Which is NOT a purpose of an End Project Report?
a) Compare project achievements against what was originally agreed
b) Record information that will help future projects
c) Prompt the Project Board to authorize the next stage
d) Pass on details of any ongoing risks for those who will maintain and operate the finished
product
21 Syllabus Topic:PG0207.2 - Progress Theme
Correct Answer:C
Objective:LL2 - Understand the purpose of an End Project Report.
a) Incorrect. The End Project Report includes a comparison of project performance against
the original Project Initiation Documentation. Ref A.8.1
b) Incorrect. An End Project Report includes the Lessons Report which will help future
projects by their learning from these lessons. Ref A.8.1
c) Correct. The Project Board would use the End Stage Report in tandem with the next
Stage Plan to decide what action to take with the project: for example, authorize the
next stage, amend the project scope, or stop the project. Ref A.9.1
d) Incorrect. The End Project Report includes any follow-on action recommendations, which
will contain any risks for the attention of those who will maintain and operate the finished
product. Ref A.8.1
22 Identify the missing word(s) in the following sentence.
If a baselined product requires modification, the [ ? ] procedure should be applied in order to
manage the modification.
a) risk management
b) exception
c) issue and change control
d) quality control
22 Syllabus Topic:CH0201 - Change Theme
Correct Answer:C
Objective:LL2 - Understand the purpose of the Change theme.
a) Incorrect. This procedure assesses and controls uncertainty, NOT change. Ref 8.3.5
b) Incorrect. This procedure monitors and evaluates achievements, NOT change. Ref 10.3.4
c) Correct. This is the procedure that identifies and controls changes to baselined
products. It is part of the Change theme. Ref 9.1
d) Incorrect. This procedure defines and produces products that are fit-for purpose. Ref
6. 3.2
23 Which is a purpose of a Project Brief?
a) Describe an agreed position from which the project can be started
b) Describe the information needs of the project’s stakeholders
c) Describe the configuration management procedure that will be used by the project
d) Describe the reporting requirements of the Project Board
23 Syllabus Topic:SU0204.1 - Starting up a Project Process
Correct Answer:A
Objective: LL2 - Understand the purpose of the Project Brief.
a) Correct. One of the purposes of the Project Brief is to ensure the project has a welldefined
start point. Ref A.19.1
b) Incorrect. This is a purpose of the Communication Management Strategy. Ref A.4.1
c) Incorrect. This is a purpose of the Configuration Management Strategy. Ref A.6.1
d) Incorrect. This is part of setting up the project controls, performed in the Initiating a
Project process, NOT the Project Brief. Ref A.20.1 / 14.4.5
24 Which is one of the four integrated elements within PRINCE2?
a) Quality
b) Role descriptions
c) Processes
d) Product Descriptions
24 Syllabus Topic:OV0103 - Overview and Principles
Correct Answer:C
Objective:LL1 - Recall the four integrated elements.
a) Incorrect. Quality is an aspect of project performance that needs to be managed. The
integrated elements are the seven principles, seven themes, seven processes and
tailoring. Ref 1.5.3
b) Incorrect. Role descriptions help to agree and communicate project management team
roles and responsibilities. The integrated elements are the seven principles, seven
themes, seven processes and tailoring. Ref 1.5.3
c) Correct. Principles, themes, processes and tailoring are the four integrated elements.
Ref 1.5.3
d) Incorrect. Product Descriptions support the focus on products but the four integrated
elements are the seven principles, seven themes, seven processes and tailoring.
Ref 1.5.3
25 Which of the following statements apply to a Stage Plan?
- Is produced with the knowledge of earlier stages
- Provides the basis for control by the Project Board
- Is produced close to the time when the planned events will take place
- Provides the basis for day-to-day control by the Project Manager
a) 1, 2, 3
b) 1, 2, 4
c) 1, 3, 4
d) 2, 3, 4
25 Syllabus Topic:PL0202 - Plans Theme
Correct Answer:C
Objective:LL2 - Understand the levels of plan, their purpose and the interrelationship between
them.
a) Incorrect. (4) A Stage Plan is created at the level of detail needed to enable the day-today
control by the Project Manager. Ref 7.2.5
b) Incorrect. (3) A Stage Plan is created towards the end of the preceding stage. Ref 7.2.5
c) Correct. (2) The Stage Plan provides the basis for the Project Manager’s control. The
Project Board monitors against the Project Plan. Ref 7.2.4
d) Incorrect. (1) A Stage Plan is produced towards the end of the preceding stage and can
therefore be written with the knowledge of previous stages. Ref 7.2.5
26 Identify the missing words in the following sentence.
Because the Project Board receives regular [ ? ], there is no need for regular progress
meetings.
a) End Stage Reports
b) Checkpoint Reports
c) Exception Reports
d) Highlight Reports
26 Syllabus Topic:PG0208.2 - Progress Theme
Correct Answer:D
Objective:LL2 - Understand the purpose a Highlight Report.
a) Incorrect. End Stage Reports are NOT regular and may be too far apart for good
reporting. Ref A.9.1
b) Incorrect. These are from the Team Manager to the Project Manager. Ref A.3.1
c) Incorrect. These are NOT regular progress reports. Ref A.10.1
d) Correct. These are sent on a regular basis by the Project Manager to the Project Board.
Ref A.11.1
27 Which is a benefit of using the product-based planning technique?
a) All the required products of the project will be delivered to time and to cost
b) Clearly shows how long a project will take
c) It removes the need for activity-based planning
d) Reduces the risk of incorrectly scoping the project
27 Syllabus Topic:PL0203 - Plans Theme
Correct Answer:D
Objective:LL2 - Understand the product-based planning technique.
a) Incorrect. The scope will be clear, but the time and effort taken to deliver them is NOT
affected. Ref 7.3.3
b) Incorrect. Product-based Planning does NOT involve any estimates, and cannot therefore
identify how long a project will take. Ref 7.3.3
c) Incorrect. Whilst the technique focuses on identifying the products required of the
project, the activities required to create or change each of the planned products may
need to be identified to give a fuller picture of the plan’s workload. Ref 7.3.3
d) Correct. Clearly and consistently identifying and documenting the plan’s products and
interdependencies between them reduces the risk of important scope aspects being
neglected or overlooked. Ref 7.3.3
28 Which of the following describe the purpose of the Risk theme?
- Identify risks that may have an impact on the project delivering its objectives
- Assess and evaluate the impact of the risks on the project delivering its objectives
- Manage risks at the corporate or programme level of the organization
- Implement risk management activities to improve the chances of the project delivering
its objectives
a) 1, 2, 3
b) 1, 2, 4
c) 1, 3, 4
d) 2, 3, 4
28 Syllabus Topic:RK0201 - Risk Theme
Correct Answer:B
Objective:LL2 - Understand the purpose of the Risk theme.
a) Incorrect. (4) The Risk Management Strategy defines activities that should be
implemented to control risks on the project. Ref 8.1
b) Correct. (3) The purpose of the Risk theme is to manage project risks, NOT at the
corporate or programme level. Ref 8.1
c) Incorrect. (2) The purpose of the Assess step is to assess the impact of risks on the
project objectives. Ref 8.1
d) Incorrect. (1) The purpose of the Identify risks step is to identify risks to the project. Ref
8.1
29 Which project management team role can trigger the premature closure of a project?
a) Project Manager
b) Project Board
c) Project Support
d) Project Assurance
29 Syllabus Topic:CP0203 - Closing a Project Process
Correct Answer:B
Objective:LL2 - Understand the context of the Closing a Project process.
a) Incorrect. The Project Manager does NOT have the required level of authority. They will
implement premature closure on the request of the Project Board. Ref 18.4.2
b) Correct. The Project Board triggers premature closure from the Directing a Project
process. Ref 18.4.2 / 13.4.4
c) Incorrect. Project Support may supply management information to support a premature
project closure, but the closure can only be triggered from within the project
management team by the decision-making authority of the Project Board. Ref 18.4.2
d) Incorrect. The Project Board may appoint Project Assurance to undertake some of the
reviewing and assessing actions during the Closing a Project process, but Project
Assurance does NOT have the required level of authority to trigger premature closure.
Ref 18.4.2 / 13.4.5
30 Which is a purpose of the Organization theme?
a) Set the tolerance on the cost of resources
b) Provide project management training to those working within the project
c) Define the structure of accountability and responsibilities on the project
d) Implement the controls required to permit management by exception
30 Syllabus Topic:OR0201 - Organization Theme
Correct Answer:C
Objective:LL2 - Understand the purpose of the Organization theme.
a) Incorrect. This is covered by the Progress theme. Ref 10.1
b) Incorrect. At the start of the project, team members may need training. The Project
Manager should ensure that training needs are built into the appropriate plans. Ref
5.3.3.2
c) Correct. The purpose of the Organization theme is to define and establish the project’s
structure of accountability and responsibilities (the who?). Ref 5.1
d) Incorrect. Management by exception requires the setting of stages, targets against the 6
objectives and tolerance for each. This is all covered within the Progress theme. Ref 10.1