4 : Business Case Flashcards

1
Q

What sections should be included in a Business Case?

A

The main sections that Prince2 suggest should be included in a business case are:

  1. Executive summary (key points, benefits, ROI)
  2. Reasons (problem or opportunity statement and alignment to business strategy)
  3. Business options (analysis and reasoned reccomendation for the base options or do nothing, do mininum, do something)
  4. Expected benefits (what business benefits are possible, and how they’ll be accrued)
  5. Expected dis-benefits (what negative outcomes are possible)
  6. Timescale (actual project duration until benefits are realised)
  7. Cost (summary of project costs from the project plan including maintaining the products)
  8. Investment apprasial (aggregrate benefits and dis-benefts and costs incl. maintenance costs)
  9. Major risks (summary of major risks associated with the projects)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Business Justification?

A

Business Justification means that a valid business reason must exist, so that the project makes sense from a investment point of view.

If there is no business justification, i.e., no business case, then the project should not be done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of the business case theme?

A

All projects must be driven and underpinned by a viable business case.

The purpose of the Business Case Theme is to provide a structure to judge if the business case is desirable, viable and achievable and worth the continued investment that is made during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In which document may a summary of the business case first appear?

A

The project mandate document usually contains business case information. If there is no Business Case information in the project mandate then outline Business Case document may be the first document to contain information on the Business Case. This outline Business Case is usually derived from the project mandate and is created in the Starting up a Project process. The outline Business Case becomes part of the Project Brief and is expanded in to a full Business Case document in the Initiation Stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What management product must be complete before the business case can be completed?

A

The Business Case document cannot be completed until the project plan is ready as the following information comes from the project plan: costs, timescale and product information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which question does the Business Case answer about the project?

A

The Business Case answers “why”. Why are we doing this project? What are the reasons?

The business case might also include some “How” informaiton, but this is included in the project plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who identifies and documents the project benefits?

A

The Senior User has this responsibility to identify benefits and they can get help from other person to gather information on the current status of products or services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where are the project’s expected benefits documented in?

A

This is the Benefits Review Plan.

It is also used after the project is complete to track the benefits that are realized after the project. For most projects, the benefits will be reached after the project is closed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Corporate or Programme Management responsible for with regard to the Business Case? (3 things)

A
  1. They may write the first Business Case summary, which is part of the project mandate document.
  2. They are responsible for the Business Review Plan once the project has ended.
  3. They hold the Senior User Accountable for realizing and reporting on the Benefits.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who is responsible for the following in the Business Case theme?
• Responsible for the Business Case during the duration of the project.
• Responsible for the Benefits Review Plan during the project if not managed by the corporate or program management.
• Oversee the development of a viable Business Case ensure that the project is aligned with corporate strategies and secure funding for the project.

A

This is the Executive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who specifies and then ensures project benefits are realised?

A

The Senior User specifies the expected benefits, and then ensures they are realised (via measurements)

The senior user is also responsible for ensuring the products produced by the project deliver the desired outcomes, in other words they can be used as expected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Project management responsible for in the business case? (4 things)

A

The Project Manager:

  1. Assists the Executive in preparing the Business Case.
  2. Do an impact analysis on each new or review risks during the project.
  3. Assess and update the Business Case at the end of each Management Stage.
  4. And assess and report on project performance at project closure.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Senior supplier responsible for in the business case?

A

The Senior Supplier:

  • Confirming that the products required by the project can be delivered within the expected costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is project assurance responsible for in the business case? (4 things)

A

Project Assurance are responsible for:

  1. Can assist in the development of the Business Case.
  2. Verify and monitor the Business Case against external events and project progress.
  3. Ensure that the project fits with overall programme or corporate strategy.
  4. Verify and monitor the Benefits Review Plan for alignment to corporate or programme management.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an Output?

A

The outputs of a project are the products that the users will use. These are also known as specialist products and the project is setup to create these products.
A good question to uncover the output is: “What is the product that will be delivered by the project?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an Outcome?

A

From a PRINCE2 project point of view we say that an outcome is the result of the change, derived from using the project’s outputs. Let me give you a good question to uncover the outcome and an example.

A good question to ask to uncover Outcomes: “What can the users do better with this product?”
Example of a CRM application: Some answers could be:

  • Sales orders are processed quickly and accurately
  • Clients can assess data online and track orders
  • Easier for administration staff to track orders
  • Easier to get reports from the system

Notice how all the answers are very vague, no mention of anything tangible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are Benefits?

A

PRINCE2 says that Benefits are the measurable improvement, resulting from an outcome that is perceived as an advantage by one of the stakeholders. So see Benefits as the measurable advantages of using the product.

Here is an example: The measurable advantages of using a CRM system might be:

  • 40% reduction in cost in handling client data
  • 15% increase in sales as users can order online
  • Overall revenue increased by 12% annually

Remember, it is these benefits that are written into the Business Case and the Senior User is expected to prove that these benefits were realized.

18
Q

When is the business case reviewed?

A

The business case is reviewed at all key decision points for the project including:

  1. End state assessment, and
  2. Exception assessment
19
Q

When are benefits reviewed?

A

When they start to accrue (usually at the end of the project - but they can accrue during the project).

20
Q

What is desirable?

A

That the cost, benefit, and risk analysis is valid.

Benefits outweight the cost and risk.

21
Q

What is Viable?

A

That the project can deliver it’s products.

22
Q

What is Achievable?

A

Whether using the products is likely to result in the envisaged outcomes and resulting benefits.

23
Q

What are Dis-benefits?

A

Negative Side effects and consequences of business changes.

24
Q

What ensures the project is aligned to business (incl. corporate and customer) objectives?

A

The Executive

25
Q

What is the mininum requirements for the business case theme? (4 things)

A

To be a Prince2 project, a project must at mininum:

  1. Create and maintain a business justification (usually a business case)
  2. Review and update the justification in response to decision & events that affect the project’s Desirability, Viability, and Achievability
  3. Define the management actions to ensure the outcomes are achieved and the benefits realised
  4. Define and document the roles and responsibilities for the business case and benefits management
26
Q

What does develop mean? (in terms of developing a business case)

A

Getting the right information

27
Q

What does Maintain mean? (i.e. when “maintaining” a business case)

A

Updating the business case with the latest information about costs and benefits

28
Q

What does Confirm mean? (i.e. when “confirming” a business case)

A

Assessing whether the intended benefits have / will be realised

29
Q

What documents are associated with the business case theme?

A
  1. Business case document
  2. Benefits Management Approach document
30
Q

In which process is a business case developed?

A

In the Starting up a project (SU) process

31
Q

In which process is a business case refined?

A

In the Initiating a project (IP) process

32
Q

In which process is the business case approved?

A

In the Directing a project (DP) process

33
Q

In which process are the issues and risks in the business case assessed?

A

In the Controlling a stage (CS) process

34
Q

In which process is the business case reviewed and updated?

A

In the managing a stage boundry (SB) process, and the Closing a project (CP) process

35
Q

What is the business case?

A

The business case documents the business justification for the project

36
Q

What is the Benefits management approach?

A

Defines the actions and benefits reviews that are required to ensure that the outcomes and benefits are achieved.

37
Q

In which process is the Benefits management approach prepared?

A

In the Initiating a project (IP) process

38
Q

What happens to the benefits management approach after the project?

A

It is executed by the business after the project has finished.

It is maintained by corporate or programme management.

39
Q

What is used as the basis for the business case?

A

The outline of the business case in the project mandate document is used as the basis for the business case during the Starting Up A Project process.

40
Q

What is the Executive responsible for in relation to the business case?

A

Ensuring the project’s objectives, costs, and objectives are aligned to the business or programme strategy.

41
Q

What happens to the information in the business case once the business case has been approved?

A

It is used as the basis for the business justification in the PID (project Initiation Document) along with the project plan, and the risk register.

The PID is developed in the Initiating a Project process (IP).

42
Q

When does the Project Manager review the business case? (4 times)

A
  1. As part of an impact assessment
  2. At stage end
  3. During final stage
  4. During benefits review.