17 : Managing a Stage Boundary Flashcards

The objective of these questions is to get you to think from a PRINCE2 point of view, learn about PRINCE2 at the same time and hold on to this knowledge. And most important don’t worry if you are not using the exam same terms as I do in the answers; it is more important that you understand the answers

1
Q

Who review the current stage?

A

The Project Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who approves the next stage?

A

The Project Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who reviews the updated project plan and confirm business justification?

A

The Project Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the project board do in the SB process?

A

The Project Manager provide information to the project board so that they can review the current stage, approve next stage, review the updated project plan and confirm business justification.

If needed, they also review and approve any exception plans (if requested)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When does the Managing a Stage Boundary process begin?

A

The Managing a Stage Boundary process will begin towards the end of the Controlling a Stage process which is the same as saying “towards the end of the current stage”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is the Managing a Stage Boundary normally used after the last stage in a project?

A

No. It is not used after the last stage. The Closing a Project process is used instead. The End Project Report is produced instead of the End Stage Report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who creates the Next Stage Plan?

A

The Project Manager creates the Next Stage Plan (with input)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who is involved in creating the Next Stage Plan?

A

As this a planning document, the Project Manager involves people with specific knowledge about the products, like the Team Managers and Subject Matter experts (which is a nice way of say people with knowledge about the products), to create a robust plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What level of detail is the stage plan?

A

The stage plan will be detailed enough to be used on a day-to-day basis by the Project Manager to manage a stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What document does the Project Board use throughout the project to measure progress of the project?

A

The Project Board uses the Project Plan throughout the Project to measure progress and to get an accurate picture of how well the project is going, what products have been produced and the best estimate plan for the rest of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is the Business Case document updated in the Managing a Stage Boundary process?

A

The Project Board checks the Business Case in the Activity “Approve a Stage or Exception Plan” which happens after each stage to see if the project is still viable. Therefore the Project Board should be given an updated Business Case at the same time as the Next Stage Plan, End Stage Report and Project Plan. After each stage there are bound to be changes to time and cost and other tolerances information, so this information should be added to the Business Case and then to check if the project is still worth doing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who may the Project Manager seek advice from/consult with when updating the Business Case?

A

The Project Manager will consult with the Executive when updating the Business Case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which document does the Project Board use to see how well the stage has performed in the relation to the Stage Plan?

A

The Project Board uses the End Stage Report. The Project Manager creates it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What triggers the creation of an Exception Plan?

A

An Exception Plan is requested by the ¨Project Board, usually after reading the Exception Report which gives an overview of the exception and recommends a way forward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does the Project Manager do next if the Exception Plan is approved by the Project Board?

A

The Project Manager goes back and completes the current stage using the Controlling a Stage process. The Exception Plan replaces the current Stage Plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of the Managing a stage boundry process?

A

The managing a stage boundry process enables the project manager to provvide the project board with sufficient information to be able to:

  • Review the sucess of the current management stage
  • Approve the next stage plan
  • Review the updated project plan
  • Confirm the continued business justification and acceptability of risks
17
Q

What are the 6 objectives of the SB process when project is running normally?

A
  1. Assure the project board that all products in the current stage plan have been completed as defined
  2. Prepare the stage plan for the next stage
  3. Review and if necessary update the PID, in particular
    • Business case
    • Project plan
    • Project approach
    • Project management team structure and role descriptions
  4. Provide the iinformation needed for the project board to assess the continuing viability of the project
  5. Record any lessons or information that can help later stages or other projects
  6. Request authroisation to start the next management stage
18
Q

What are the 4 objectives of the SB process when project is in exception?

A
  1. Review and if necessary update the PID, in particular
    • Customer’s quality expectations
    • Project approaches
    • Controls
    • Role descriptions
  2. Provide the iinformation needed for the project board to assess the continuing viability of the project
  3. Prepare an exception plan
  4. Seek approval to replace the project or stage plan with the exception plan
19
Q

What are the 5 activities in the SB process?

A
  1. Plan the next management stage
  2. Update the project plan
  3. Update the business case
  4. Report management stage end
  5. Produce an exception plan
20
Q

What is created in the Managing a stage boundry process?

A
  • End stage report
  • Next stage plan
  • Exception plan (if needed)
21
Q

How does the MB process link to the Directing a project process?

A

The request to approve the next stage plan or exception plan links to the authorise stage or exception plan activity in the DP process.