2 : Principles Flashcards
It is more important that you understand each of the seven principles and recognize them when taking the exam.
What does the following statement mean: “PRINCE2 is principle based”?
This means that each PRINCE2 project should include the 7 principles and even if just one of the principles is missing, it can still be a project but it cannot be considered a PRINCE2 Project.
What are the Prince2 Principles?
The 7 principles are:
- Continue business justification – business case must exist throughout the project.
- Learn from experience – learn from lessons.
- Defined roles and responsibilities – everyone knows what is expected from them.
- Manage by stages – break projects into stages – easier to manage.
- Manage by exception – Allows the level below to get on with their work and inform above level if work will go out of tolerance.
- Focus on products – be clear and specific from the beginning of the project of what the project will deliver – so all stakeholders know what to expect from the project.
- Tailor to suit the project environment – don’t overload your projects with unnecessary administration.
Which principle deals with the business reasons behind the project?
This principle is Continued Business Justification.
What does Continued Business Justification mean?
Continued business justification is a project principle.
- Justifies the reason for starting the project
- Reason is documented (in the business case)
- Justification is reviewed throughout the project
- Justification could be a business plan in the early stages
- The documented justification ensures the project continues to deliver outputs
The business justification drives the decision making process.
Even in cases where the justification is legislated (and required) the busines case ensures Value for Money.
Where is the Business Justification for a project documented?
In the Business Case document, this document is created in the Initiation Stage and it becomes part of the Project Initiation Documentation.
What is a Premature Close?
When the Project Board instructs the Project Manager to close this project because the business justification is no longer valid.
What does the principle Continued Business Justification prevent at the start of a project?
This principle prevents projects that have few real benefits for the company from starting.
When does the Project Manager check for Business Justification in the project?
The business justification is checked throughout the lifetime of the project. This is done first at the start of the project to make sure the project is worth doing and then at the end of every stage. The end of every stage is a good time as the Project Manager provides the End Stage Report, overview of Risk and information that affects the business case to the Project Board.
What is the name of the principle that deals with Lessons Learned?
Learn from Experience. So learn from previous projects and other information that is available.
What is Learn from Experience?
Learn from experience is a project principle.
Even though projects are unique, lessons can be learnt from participants prior experiences, or from similar projects. This learning should happen throughout the project.
Lessons are recorded in the lessons log.
What is a lesson? “do this…” or “don’t do this”.
Who should learn from experience?
PRINCE2 says that all stakeholders should take the initiative to seek lessons learned. This will help to decrease the unknowns and provide more information on risks. So it is not just up to the Project Manager but all the stakeholders.
Who has the responsibility to seek lessons learned?
PRINCE2 states that seeking lessons learned is a responsibility for everybody involved in the project.
How can you learn from experience if there were no similar projects within their organization?
They should then look for outside help, e.g.: consulting, reports, trade information, visit other companies that may have done similar projects, etc…
What are the three phases of lessons learnt (and what happens in each?)
Lesson Learned covers the complete lifecycle of the Project. There are 3 phases for lessons:
- Starting Up a Project, Looking outside for useful Lessons Learned and the Project Manager adds them to the Lessons Log
- During the Project: identify new lessons learned to the Lesson Log
- At Project Close: you can pass on lessons to the next project in the Lesson Report
What is the name of the principle that deals with Roles & Responsibilities?
The principle name is “Defined Roles & Responsibilities”.
What are Defined roles and responsibilities?
Defined roles and responsibilities is a project principle.
It answers the question “What is expected from me” or “What is expected from everybody in the project”. Everyone connected to the project should know their role and this should be decided at the start of the project.
Who are stakeholders?
Those who have an interest in the project, are affected by it, or can affect the project.
Who are the three primary stakeholders?
- Business Sponsors
- Users
- Suppliers
These stakeholders should be represented in the Project Board.
Who are Business Sponsors (and what do they do)?
The Business Sponsors are a project stakeholder. They:
- Endorse the objectives
- Ensure the project provides return on investment.
Who are Users (and what do they do)?
Users are those who will use the products once created, so they receive the benefits or they represent the people who will use the products.
Throughout the project, their main concern is “Can the product be delivered as expected and will it usable?”
Who are suppliers (and what do they do)?
Suppliers provide the resources and expertise to the project and produce the products. Their main concern throughout the project is “Can it be done as expected?”