10 : Progress Flashcards
What is the purpose of the Progress theme? (3 things)
To establish mechanisms to monitor and compare actual achievements against those planned in order to provide a forecast for the project objectives, including its continued viability, and control any unacceptable deviations.
Or split into 3 parts it is:
- To establish how to monitor and compare actual achievements against those planned
- To provide a forecast for the project objectives and the project’s continued viability
- To be able to control any unacceptable deviations
What happens in the progress theme? (7 things)
- Progress is monitored
- Compare achievement with plan
- Review plans and options against future situations
- Detect problems
- Identify risks
- Initiate corrective action
- Authorise further work
What Prince2 Princples are represented in the Progress Theme?
Three of the seven principles are represented in the Progress Theme.
These are:
- Manage by stages: The Project Board use stages as control points
- Continued business justification: The business case is continually checked that the project is still worth doing.
- Managed by Exception: If tolerances are exceeded, then the issue is referred up to the next management level for approval.
What is progress and/or control about?
Control or progress is all about decision-making and is central to project management, ensuring that the project remains viable against its approved Business Case.
What is an exception?
An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. The keyword here is forecast.
What can tolerances be set against what?
Tolerances can be set against the project aspects of:
- Time,
- Cost,
- Quality,
- Scope,
- Benefits, and
- Risk.
Why use Tolerances?
If tolerances didn’t exist, for every small issue that occurs, the Project Manager would escalate to the Project Board and they would end up working on the project 8 hours a day and therefore would be doing a lot of the work for the Project Manager.
The Project Board are (usually) busy people and we don’t want to take up much of their time.
Setting tolerances allows the Project Manager to handle smaller issues and only bother the Project Board for bigger issues that are outside this tolerance.
What are the 4 ways to control a project?
PRINCE2 provides control through four main ways:
- Delegating Authority from one level to the next
- Dividing the project into management stages (and authorizing one stage at a time)
- Time driven and event-driven progress reports
- Raising Exceptions, so use exceptions to alert above layer
Who can each management layer delegate to?
- Corporate or Programme Management can delegate to the Project Board
- Project Board can delegate to the Project Manager
- Project Manager can delegate to the Team Manager
Who sets the Project Tolerance?
Project Tolerances are set by Corporate or Programme Management. These are set at the beginning of the project and can be updated for each stage.
What happens if a stage Tolerance is forecast to be exceeded?
Stage Tolerances are set by the Project Board and managed by the PM.
Should they be forecast to be exceeded then an exception report should be created and the project board notified immediately.
Who sets the Stage Tolerance?
Stage Tolerances are set by the Project Board. These are set at the beginning of the project and can be updated for each stage.
What happens if a Work Package Tolerance is forecast to be exceeded?
The Work Package tolerances are set by the Project Manager.
If the event a work package tolerance is set to be exceeded, the deviation should be referred to the project manager for a decision on corrective action.
This is considered an issue.
Who sets the Work Package Tolerances?
The Work Package tolerances are set by the Project Manager when assigning a work package to a Team Manager.
What happens when one of the project tolerances is forecast to be exceeded?
They must alert the Project Board immediately. The Project Board may decide to wait a week or a few days to see if the situation changes, or request an Exception Report or even request an Exception Plan.
They should seek advice from Programme / corporate management.
What are the 3 controls that a project board use to control a project?
These controls are Authorizations, Progress Updates and Exceptions & Changes.
- The Project Board first authorizes the Initiation Stage, secondly they authorize the Project and then authorize each stage and lastly they authorize Project Closure.
- Progress Updates. They receive Highlight Reports and End Stage Report from the Project Manager.
- Exceptions and Changes: The Project Manager advises the Project Board about any exceptions during a stage. All change requests will go through the Change Management Procedure as described in the Configuration Management document.
How does a project board use Exceptions and changes to control a project?
Exceptions and Changes: The Project Manager advises the Project Board about any exceptions during a stage and the project board undertakes exception assessments.
How does a project board use Authorisations as control?
The project board use authorisations to control the project by:
- Authorising the Initiation stage
- Authorising the project
- Authorising each stage
- Authorising project closure
How does a project board use progress updates to control a project?
Oversight. They recieve Highlight Reports and End Stage Reports from the Project Manager
What control tasks can the Project Board can do at the end of each stage?
The Project Board can do the following at the end of each stage:
- They review the End Stage report and Review plan for next stage
- They can continually check the check the viability of the project
- They can authorize the next stage to start
- Then can check project progress against the baselined project plan
What are the 3 controls a Project Manager uses to control the project?
These controls are Authorizations, Progress Updates and Exceptions & Changes. These are same names as the 3 Project Controls as the Project Board.
- Authorizations: The Project Manager authorizes work packages to the Team Manager during the CS process.
- Progress Updates: This includes Check Point reports that are provided by the Team Manager or Team Members.
- Exceptions and changes: They use the project registers and logs to review progress and identify issues that may need to be resolved.