7 : Plans Flashcards
There is a good deal of information in this theme and the questions are a good way to help you remember this. Like other themes, don’t worry about getting the answers exactly correct.
What is the purpose of the plans theme?
Effective project management relys on plans. Without a plan, there can be no control.
What is included in a Prince2 plan? (6 things)
A Prince2 Plan includes:
- What has to be produced (the scope)
- What has to be done to produce the products
- What has to be done to ensure the products are of suffcient quality
- When the products will be prodced
- How progress will be monitored
- What has to be done to control risks
Is a gantt chart a plan?
No.
A plan is a document that describes how, when and by whom a specific target or set of targets is to be achieved. You many think the target is just to create the project product but there will also be targets for time, cost, quality and benefits. So a plan is more than a Gantt chart.
What is Planning?
Planning is the act or the process of making and maintaining the plan.
You can also say creating and maintaining the plan. The Project Plan is created at the start of the project and is regularly updated during the project to show what has been done to date. The Stage Plans are created before the stage and updated to show what has been done during the stage.
What are the 3 levels of plan?
The three levels of plans are
- the Project Plan,
- Stage Plan and
- Team Plans.
There can also be an exception plan and a Benefits Review Plan.
Should all plans be created at the start of a project?
No.
It is impossible to plan an entire project from the start unless it’s a very small project and it has a lot in common with a very small project that has been done before. It is only possible to accurately plan a short time in advance, e.g.: 0 to 8 weeks. This is known as the planning horizon. So PRINCE2 recommends having different levels of plan, which are linked, to the management levels in a project organization.
What is developed and maintained in the Plans theme?
The Plans theme provides a framework to design, develop and maintain the project plans such as the Project, Stage & Team plans.
What is the backbone of the project?
The project plan is the backbone of the project.
It is created at the start of the project and continually updated during the project to show what has been done and what still needs to be done. It can be compared with the original document to see how well the project is progressing.
What are the six project variables?
Planning helps to manage the six project variables, which are Time, Cost, Quality, Scope, Benefits and Risk.
What are the 3 levels of management in a project team.
The three management levels are:
- Directing (Project plan)
- Managing (Stage plan)
- Delivering (Team plan)
What are all the plans in a Prince2 project?
Name the type of plan in each of the management levels of Directing, Managing and Delivering and mention when this plan is created.
- Project plan (Directing level)
- Stage plan (Managing level)
- Team plan (Delivery level)
- Benefits Review Plan (covers activities during and after the project)
- Exception plan
What is a project plan?
A high level plan showing the major products of the project, when they will be delivered and at what cost, and what resources are involved.
It provides the project costs for the business case and identifies the major control points.
An initial project plan is presented as part of the projec tinitiation document or PID. This is revised as information on actual progress appears. It is a major control document for the project board to measure actual progress against expectations.
Which plan is mainly used by the Project Board?
The Project Plan is a high level plan and mainly used by the Project Board to measure progress.
Are delivery stage and management stage the same?
No. They can align but they aren’t the same.
Management stages don’t overlap and are sequential.
Delivery stages can overlap and are related to the types of activities being undertaken at that point.
What do the Project Board use to check how the project is progressing?
The Project Plan is always baselined at the start of the project, so the Project Board can compare this baselined plan to the current Project Plan at the end of each stage to see how the project is going compared to the original plan.
When is the Project plan created?
During the Initiating a project process.
An initial project plan is presented as part of the project initiation doc or PID (which is revised as information becomes available).
How does the Stage Plan differ from the Project Plan?
The Stage Plan is just for one Stage and it’s a lot more detailed that the Project Plan. The Stage Plan is used by the Project Manager on a day-to-day basis.
What is a stage plan?
A detailed plan used as a basis for project management control throughout a management stage. It enables day-to-day management of the project.
It doesn’t include plans for anything outside of the management stage.
Each management stage has a stage plan.
When is a stage plan finalised?
Towards the end of the previous stage so it includes the latest information.
What is a Team Plan?
A team plan covers the work of the team for a stage or work package.
Team Plans and Team Managers are optional depending on the project’s size, complexity and the number of resources involved in creating the products. The Team Managers may create their Team Plans in parallel with the Project Manager when they create the Stage Plan.
When are team plans created?
During the Managing product delivery process.
Who creates the Team Plans?
The team plans are created by the Team Manager to plan the execution of one or more Work Packages.
Team Plans and Team Managers are optional depending on the project’s size, complexity and the number of resources involved in creating the products. The Team Managers may create their Team Plans in parallel with the Project Manager when they create the Stage Plan.
What should be considered when defining stages?
- How far ahead it is sensible to plan
- Where the key decision points are needed
- The amount of risk in the project
- How confident the project board and the PM are in proceeding
How can a Project Manager be involved in the development of a Team Plan?
A project manager can ask to review the Team Plan and it is up to the Team Manager to decide to allow this.
What is an exception plan?
The Exception Plan is used to recover from the effect of tolerance deviation and if approved replaces the current plan? In other words it picks up from where the current plan had stopped.
It covers the period from the identification of exception, to the end of the stage or project (depending on which plan it is replacing).
How do exception plans relate to work packages?
They don’t. Exception plans operate at the stage plan level / management level. If a Team Manager forecasts that the work package will exceed tolerances they will raise an issue to the Project Manager. The Project Manager can take corrective action by updating the Work Package or creating a new Work Package to complete the work.
There is no Exception Plan at the delivery management level.
What technique does Prince2 use to identify and analyze the plan’s products?
Prince2 uses Project Based Planning.
What are the four steps in product based planning?
The four steps in Project Based Planning are:
- Write the Project Product Description: The description of the main product
- Create the product breakdown structure: List all products than need to be created
- Write the Product Descriptions: Can be done for each product
- Create the product flow diagram: Show product flow and inter-dependencies
What are the benefits of a Product Based Planning approach? (7 things)
Here are some of the benefits of Product Based Planning:
- Clearly identifies and documents the plan’s products and interdependencies between them.
- Clearly shows what the project involves and avoids setting the wrong expectations.
- Involves users in supplying product requirements, thus increasing their support.
- Improves communication as both diagrams, the product breakdown structure and product flow diagram provide a simple overview of showing what needs to be done and make it much easier to get feedback.
- Makes it easier to clarify what is in and out of scope and therefore later to avoid scope creep.
- Easier to gain a clear agreement on what needs to be produced.
- Helps manage risk.
Who writes the Project Product Description?
The Senior User is responsible for specifying the project product, but in practice the Project Manager may do most of the work as they will be used to do this and consult with the Senior User and Executive. The Project Product Description should be as detailed and complete as possible.