tema 4 Flashcards

1
Q

What does Schedule stand for?

A

Is a timeline that outlines when specific tasks or activities will start and finish. It serves as a plan for organizing, sequencing, and allocating resources to ensure project deliverables are completed on time.

activities/tasks , durations, dependencies, milestones, resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To Create the Schedule, From Where Do We Start?

A

1.Defenir WBS
2.Identificar atividades
3. Estimar durações
4. Defenir dependencias
5. alocar recursos
6.sequenciar atividades
7.desenvolver o schedule
8.baseline o schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Differences Between Milestone Diagram and Gantt Diagram

A

Milestone Diagram: Highlights key events or achievements in the project. Focus on Milestones (no detailed tasks or durations).

Gantt:Shows the timeline, tasks, durations, and dependencies. Focus on Tasks, durations, and dependencies in detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

And between a Gantt and a Precedence Diagram?

A

Precedence Diagram: Represents tasks and their dependencies in a flowchart-like structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What kind of precedence relationship do you know?

A

Finish-to-Start (FS):
Task B cannot start until Task A finishes.

Start-to-Start (SS):
Task B cannot start until Task A has started.

Finish-to-Finish (FF):
Task B cannot finish until Task A has finished.

Start-to-Finish (SF):
Task B cannot finish until Task A has started (least common).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

when should you use gantt or precedence diagram?

A

Use a Gantt Chart when you need to track progress and communicate the timeline to stakeholders.
Use a Precedence Diagram when planning dependencies, optimizing the critical path, or ensuring logical task sequencing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What Are the Lag Times Between Tasks? (tiempo de desfase)

A

Lag time is the delay intentionally introduced between two dependent tasks. It represents a period where no activity occurs before the successor task can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Is There Any Relationship Between Work Package Duration and Its Resources?

A

Inverse Relationship: Increasing resources can reduce the duration of the work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If we accept probabilistic distribution β for task duration, how to estimate the averaged duration?

A

E(T)=(otimista +4*maior probabilidade + pessimista) /6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How much the variance would be?

A

v= ((Pessimista-otimista)/6)^2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the main hypotheses for the P.E.R.T method?

A

(Program Evaluation and Review Technique) method are:

-Task durations follow a beta distribution
-Dependencies are fixed: Tasks follow a defined sequence with clear predecessor-successor relationships.
-Critical path determines project duration: The longest path through the network determines the project completion time.
-Estimates are probabilistic: Task durations include three estimates (optimistic, most likely, pessimistic) to account for uncertainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the differences with the Critical Path Method (CPM)?

A

P.E.R.T: Based on beta distribution and expected durations.
Probabilistic (optimistic, most likely, pessimistic). Used for projects with high uncertainty.

CPM (Critical Path Method):
Based on fixed, known durations for tasks.
Deterministic (single-point estimates). Used for projects with well-defined, predictable tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the unit for monitoring and controlling the schedule in Gantt?

A

the unit in a Gantt chart is time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the major issue with the Gantt approach?

A

-does not visually emphasize task dependencies, making it harder to identify critical paths or bottlenecks.
Lack of Real-Time Adaptation:
They are static representations and require frequent manual updates.
Resource Constraints:
Gantt does not inherently account for resource availability or allocation issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the unit for monitoring and controlling the schedule in CPM?

A

The unit in CPM (Critical Path Method) is float (or slack) time, which measures the flexibility of non-critical tasks without impacting the project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the major issues with the CPM approach when monitoring?

A

Fixed Durations:
CPM assumes deterministic task durations, which may not reflect real-world uncertainties.
Resource Blindness:
It does not account for resource constraints or multitasking effects.
Focus on Critical Path Only:
CPM may overlook risks and delays in non-critical tasks, which can later impact the schedule.

17
Q

What is the unit for monitoring and controlling the schedule in CCPM?

A

Critical Chain Project Management (CCPM):

The unit is buffer consumption (e.g., project buffer, feeding buffer).
Buffers are monitored to assess whether the project is on track, with focus on buffer penetration rather than individual task durations.