Some Numbers, PROC Flashcards

1
Q

s

What is due date of contractor invoice if LG rep must first approve?

A

s

25 business days from date invoice is stamped received.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

s

What is due date of contractor invoice if LG rep need not first approve?

A

s

20 BUSINESS days from date invoice stamped received.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
#s
-----------
What kind of invoices get pre-approved or need approval?
-----------
Due date?
-----------
Int rate & when applied?
A
#s
-----------
Construction.
-----------
Pre-approved = 20 BUSINESS days.
Need approval = 25 BUSINESS days.
-----------
2% upon due date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

s

What is significance of LG’s receipt of overdue notice?

A
#s
-----------
After 4 business days of delivering an overdue notice, if LG does not reject the invoice it is deemed undisputed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

s

What is LG required to do if it disputes the invoice or the overdue notice?
———–
If Vendor acts in response, what is LG’s timeline?

A

s

w/i 20 business days of receipt, provide written rejection, specifying deficiency & stating action to rectify.
————
If Vendor submits corrected, 10 bus days to pay or reject.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
#s
-----------
If LG sent contractor a written rejection of an invoice & contractor revises the invoice, what now must LG do?
A
#s
-----------
Pay or notice rejection:
a) w/i 10 business days of receipt or
b) 1st business day after LG's next meeting.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
#s
-----------
How long does a contractor have to pay its subs after receiving LG payment?
A

s

10 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
#s
-----------
How long does subcontractor have to pay the sub-subcontractors after receiving contractor's payment?
A

s

7 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

s

What are penalties for LG’s late payment of its invoices?

A

s

CONST. NEW 2021 [used to be 1%,]

2% per month (more if agreed to in K) from due date [20 bus pre-app, 25 bus need app).
———–
NON-CONST.
1% per mo. 30 days aft due date of 45 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

s

What procedure must LG initiate if there is a payment dispute?

What’s the tight turn around?

A

s

• w/i 45 days proper invoice was received,
commence its established dispute resolution procedure.
• w/i 60 days proper invoice was received, have final decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

s

Re: construction
Threshold amt requiring LG to announce for pro services?

A
#s
-----------
Exceeds $325k const, $35k study.
-----------
~i thought $300k, construction?~
~look for keyword 'pro servs'~
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

s

Re: planning or study activity
Threshold amt requiring LG to announce for pro services?

A

s

Exceeds $35k.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

s

What work is covered by 255.20?

A
#s
-----------
Public Construct
Inc. bridges, roads, streets, hiways, RRs 
• 	May req qualf
• 	DQ if 10% behind
• 	Prequl by DOT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
#s
-----------
What is dollar threshold for Construction?
A

s

Over $300k*
* Includes labor, equip + materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
#s
-----------
What is dollar threshold for Electrical?
A

s

Over $75k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
#s
-----------
What is dollar threshold for Roads?
A

s

Over $250k

17
Q

s

GET CLARIFICATION.
There are different thresholds for 255.20 & 287.055, so how can 255.20 require comply w/ 287.055?

A
#s
-----------
255.20
Constr.   over $300k*   *Includes labor, equip + mats
Roads.    over $250k
Elect.      over $75k.

CCNA
Constr. over $325k
Study/Plan over $35k

18
Q

s

What are 2 exemptions under 255.20?

A

s

  1. County roads, FS 336
  2. No req to comp award anything if $300k or less
19
Q
#s
-----------
What's the pre-requisite to Self Hire exception to new const of pub facilities, 255.20?
A

s

  1. Pub mtg w/ 21 days notice
  2. Hear from Ktor who wd have gotten the job
  3. Consid econ dev, tax revs, wh/ ktor offers hlth ins.
  4. Dets in best interest to use Staff
20
Q

s

How much overhead paid on Self-Hire?

A

s

Get 20% admin

21
Q

s

What are 3 performance mandates on a Self-Hire under 255.20?
———–
What does #3 require be included & what does it require LG to do? How frequently?

A
#s
-----------
1)  Use lic ktor if over $300k
---
2)  Inspected just like private proj.
---
3)  Prep report of projects for Auditor General w/:
(a) estimated costs & 
(b)  actual costs.  
---
Review publicly EACH YEAR.
22
Q

s

When are preferences prohibited under 255.20?

A

ANY State funding prohibits:
1) Local preference in construction
2) Wages, benes, source or amt of staffing pref in utility const.
———–
Remember - Fed has no retainage [& State has none under $200k]

23
Q

s

What amt can set aside for optional MBE preference?

A
#s
-----------
May set up to 10% aside
\+
Encourage 20% bond writing
Equal protection suit @ 30%
24
Q

s

FS 255.20 threshold for when to competitively bid?

A
#s
-----------
$300k constr.
$250k roads.
$75k elec.
25
#s ----------- LGs are encouraged to competitively bid what amount for MBEs?
#s ----------- $100k.
26
#s ----------- When must road contractor be qualified?
#s - ---------- 1. If over $250k 2. Ktor must be certified or qualified 3. To construct or improve bridges, roads, streets, highways, or railroads, and services incidental thereto.
27
#s ----------- When is road contractor not eligible to be qualified?
#s ----------- If behind by 10% at the time of advertising the work.
28
#s ----------- What 6 items are exempt from bidding?
``` i want Exempt from eng lit 300 b/c POE SuCs --- in an Emergency, SOS a COP ----------- 1. Change Orders 2. Emergency 3. Sole Source 4. Professional services 5. Under $300k per 255.20 6. If built into City/County Ordinance or Sp Dist resolution as permitted under 255.20. ```
29
``` #s ----------- For how long are sealed bids exempt from public records disclosure? ```
``` #s ----------- Earlier of: (1) Notice of intended decision or (2) 30 days following opening. ```
30
``` #s ----------- If LG reissues solicitation, how long do the sealed bids remain exempt from public records laws? ```
``` #s ----------- Until notice: (1) Intended decision or (2) Withdrawal of solicitation, BUT no longer than 12 months after initial notice of rejection. ```
31
``` #s ----------- What could change between now & the CCLG exam regarding trade secrets & public records? ```
#s ----------- The confidential & exempt status of computer data, programs & their documents in the hands of LG. Why? FS 815.04(3) is scheduled to sunset on 10/2/21.
32
255.20 [public works/roads] ----------- How much overhead is included in calculating the threshold for mandatory construction bidding?
255.20 [public works/roads] ----------- $300k incl: 1) Overhead @ 20% 2) Labor 3) Materials.
33
255.20 [public works/roads] ----------- What is dollar threshold for at which must competitively award for Construction?
255.20 [public works/roads] ----------- Over $300k* * Includes labor, equip + materials + overhead @ 20%
34
State the difference in dollar thresholds between public works [255.20] & CCNA [287.055]
Pub Works 255.20 $300k incl: 1) Ovrhd @ 20%, 2) Labor, 3) Materials. CCNA 287.055 $325k for construction $35k for study/design fee.
35
CCNA ----------- When does 255.20 (construction of public works) require compliance with CCNA?
CCNA ----------- When awarded based on negotiations.
36
255.20 [public works/roads] ----------- What is dollar threshold for at which must competitively award for Electrical?
255.20 [public works/roads] ----------- Over $75k
37
CONTINUING K ----------- What is the threshold dollar amount for a continuing contract under CCNA?
CONTINUING K ----------- $4M for construction. $500k for planning/study
38
CCNA ----------- Who does CCNA apply to?
CCNA ----------- An instrumentality of LG. HFA, a county civic facilities authority;. a hospital taxing district; a multi-county airport authority; & a county housing authority.