s
CP’s Capital Improvement Element covers how many years?
s
5 years
s
CP covers how many years?
s
20 years
s
STATE COORDINATED REVIEW
9 step CP amendment method/timeline.
s
PROPOSAL STAGE.
1. Agency or citizen intiative, LPA preps amndmt
2. Transmittal hearing.
3. 10 days transmit to SPA & any requesting agencies.
4. 5 days for SPA to notify LG if deficient.
ADOPTION STAGE
5. SPA, if reviews, has 30 days to issue ORC.
6. LG has 180 days to hold Adoption Hearing.
7. 10 days re-transmit to DEO (may issue sanctions if LG ignored its ORC).
8. 5 days for DEO to notify LG if deficient.
9. 31 days after DEO notified LG complete = effective.
#s ----------- How often required to review CP? How long to pass any required updates?
s
Every 7 years.
1 year.
s
How many acres in Sector Plan
s
5,000
s
What is acreage cut-off for small scale CP amendment?
s
50 acres [100 acres rural]
s
For 50+ acres, what is the required timing for PHs to amend CP?
7 ———- 5 ———- 10
———-
TOTAL of 2 ads for 2 PHs (1 ad each), 1 PH held after 5 p.m. (unless maj + 1)
———–
TRANSMITTAL HEARING
Weekday @ least 7 days after date of 1st ad.
ADOPTION HEARING
Weekday @ least 10 days after 1st hearing + 5 days after 2nd ad.
#s ----------- What notice is required for small scale CP amendment or zoning map change?
s
LG mails notice to Owners @ least 30 days before hearing.
What notice is required for non-land use ordinances?
1 ad 10 days before hearing.
s
Small Scale amendment method/timeline.
s
- Agency or citizen initiative, LPA preps amndmt
- Submit to DEO, which does not review.
- Adoption hearing.
- LG does not re-transmit to DEO unless challenged.
- 31st day = effective.
- 30 days for affected person to file DOAH.
- 30-60 days, DOAH hearing.
s
Limits of 163.01 Creation + Powers of New Entity (Amended 2021)
s
Limits:
1. Consent of existing needed to serve in same area.
2. No ED over existing W or WW
3. If acquire by ED, 10 yrs must elapse before get title.
4. Any limits set forth in Interlocal.
s
Newly Incorp Muni - CP deadlines (Amended 2021)
s
1 year. Create local planning agency.
3 yrs. Adopt CP.
s
DOT’s acq, lease, disposal of Real Prop + Pers Prop via 337.25 & LG’s rt of first refusal
(FS 337.25 Amended 2021)
#s ----------- LG does not have rt of first refusal.
DOT must give prior O rt of 1st refusal (b/4 giving to LG) via certified mail or hand deliver, effective upon receipt.
A. 30 days to exercise.
B. 90 days to close
s
Limit on DOT rt of 1st refusal to prior O
s
Not req’d for property acquired more than 10 yrs before date of disposal.
#s ----------- What does FLUEDRA (FS 70.51) provide?
s
If O believes unfairly burdened, has 30 days to request.
LG has 10 days to give to special master.
#s ----------- How many days does FLUEDRA claimant have to assert?
s
O has 30 days to request relief.
s
How many days for LG to act on O’s FLUEDRA request?
s
LG has 10 days to assign to special magistrate
LG must notify contiguous Os & any witnesses from PH.
#s ----------- How many days do FLUEDRA interested persons have to act?
s
21 days to request to participate.
#s ----------- How many days does FLUEDRA special magistrate have to hold hearing?
s
45 days for a hearing.
40 day advance notice given. WEIRD #