Schedule management Flashcards

1
Q

Schedule management process

A

Plan schedule management (Planning)
Define activities (Planning)
Sequence activities (Planning)
Estimate activity durations (Planning)
Develop schedule (Planning)
Control schedule ( Monitoring & controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan schedule management (Planning) 1st

A

-提供guidance & direction for project schedule 點管理
-建立policies, procedures, documentation for planning, developing, managing, control the project schedule

Output: Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan schedule management (Planning) 1st
Schedule management plan

A

-用咩Scheduling methodology & Software
-建立schedule baseline
-辨認 Performance measure ,
-有分差點managed
-辨認 schedule change control procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define activities (Planning) 2nd

A

-辨認同記錄specific action to be performed to produce the project deliverable
-Breakdown activities 然後做個work package ( 叫做Activities)
- Define activities with your team

Output:
Activity list ( project activities)
Activity attributes ( WBS ID, predecessors…. )
Milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Sequence activities (Planning) 3rd

A

-identifying & documenting relationships among
之中 the project activities
-會用network diagram, 同show critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sequence activities (Planning) 3rd
Precedence Diagramming method (PDM) - network diagram

A
  1. Finish to start (FS)
  2. Start to start (SS)
  3. Finish to finish (FF)
  4. Start to finish (SF)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sequence activities (Planning) 3rd
Lead time / Lag time

A

Lead - 超前, 唔等A 做完就偷步做B

Lags - 延後, 做完A, 等3日先做B, 但project 無delay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate activity durations (Planning) 4th

A

Estimating the number of work periods needed to complete individual activities with estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate activity durations (Planning) 4th
Techniques

A
  1. One point estimate
    準確時間表唔係必須, 可用呢個方法, 但唔準確, D 人會加好多PAD
    one estimate per activity
  2. Analogous Estimating (Top-down)
    之前有smiliar project,可根據之前去做估算, 但你自己未做過
  3. Parametric Estimating
    Base on historical record,你之前有做過
  4. Heuristics
    Rule of thumb 80/20 rule
    80% of quality problems are caused by 20% of the potential
    sources of problems
  5. Three point estimate (PERT analysis)
    O+M+P/3 or O+4M+O/3
  6. Reserve analysis
    Connected to risk management
    Contingency reserve = 已知risk
    Management reserves = unseen risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Develop schedule (Planning) 5th

A
  • You will have final project schedule - etc start & end date duration resources
  • Generate schedule model with planned dates

Output:
Project schedule
Schedule baseline

  1. Network diagram - Showing interdependencies of activities
  2. Milestone chart - For reporting to management
  3. Bar chart - Track progress and repot to team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Develop schedule (Planning) 5th
Critical path method

A

-你有critical path , 就會知project duration
- Longest duration path
-無float
-有多條critical path = high risk
-有負數neg path = schedule is behind than the planned,

Total Float - delayed without delaying the end date
Free float - delayed without delaying the early start date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Develop schedule (Planning) 5th
Schedule compression

A

-Compress the schedule without changing project scope

Fast tracking : 同時進行D activities
Crashing : cost vs schedule tradeoffs, 加資源
Resource leveling: produce a resource limited schedule 將同事分工得好D, 但對整體無做快到,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Control schedule ( Monitoring & controlling) 6th

A
  • Monitoring the status of project activities to update project progress and manage change to the schedule baseline to achieve the plan

Output:
Update lesson learn register
Work performance information
Change request
Project management plan (update)
Project document (update)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Agile
Metric度量 - quick method using relative size to estimate the user stories

A

Story points

-A story point is s an arbitrary隨意的 measure typically used by agile teams.
-It is used to measure the effort required to implement a user story.
- tells the team how difficult the story is. The level of difficulty could be related to complexity, the number of unknowns o the effort required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sequence activities (Planning) 3rd
Type of dependencies

A
  1. Mandatory dependency (hard logic)
  2. Discretionary dependency ( preferred , 先做A, 再做B)
  3. External dependency
  4. Internal dependency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly