Cost management Flashcards
Cost management process
Plan cost management (Planning)
Estimate costs (Planning)
Determine budget (Planning)
Control costs (Monitoring & Controlling)
Plan cost management (Planning) 1st
-How the project costs will be managed
Output: Cost management plan
Plan cost management (Planning) 1st
Cost management plan
-Units of measure
-用幾多小數點位
-Budget variance 幾多你就會take action
- Rules of performance measurement
-Reporting formats
Estimate costs (Planning) 2nd
-Develop 大概你需要既資料係呢個project 上
-估計要幾多成本去完成project
Input:
Scope baseline
Project schedule ( Type, quantity, and amount of time that the team and physical resources will be active on the project)
HR plan
Risk register (risk of the project)
project management costs
Estimate costs (Planning) 2nd
Tools and techniques
-One point estimate
-Analogous estimate
-Parametric estimate
-Three point estimate
-Bottom up estimate
Est. rolled up to control account , then into overall project estimate
Estimate costs (Planning) 2nd
Accuracy of estimate
- 一開始一定唔準, 之後先會準
-Estimate must be in a range
- Rough order of Magnitude (ROM) estimate
開始先用, -25 to 75% from actual - Budget estimate
Planning 先用, -10% to 25 % from actual - Definitive estimate
最後先用, -10 to 10 , or -5 to 5
Determine budget (Planning) 3rd
-加曬所有estimated cost of individual activities 去做個cost baseline
-Determines the cost baseline
-Project estimate 要加risk management ==> 姐係reserve
Contingency reserve / Management reserves
Tools:
Financing
Output:
Cost baseline
Project function requirement
Determine budget (Planning) 3rd
Cost baseline
Funds authorized for PM to manage and control
包括Contingency reserve
Cost baseline + Management reserve = Cost budget
Control costs (Monitoring & Controlling) 4th
-Monitoring status and update the project cost
-Managing changes to the cost baseline
-Recognize variance from plan
Control costs (Monitoring & Controlling) 4th
Earned value management (EVM) - Variances
-Measure project performance against scope, schedule and cost baseline
Planned value (PV) - Estimate the work planned
Earned value (EV) - Estimate the work actually accomplished
Actual cost (AC) - Actual cost incurred
Schedule variance (SV) SV=EV-PV
SV <0 Behind schedule
SV= 0 on track
SV>0 ahead schedule
Cost variance (CV) CV=EV-AC
CV <0 Over budget
CV= 0 on track
CV>0 under budget
Schedule performance index (SPI) - Measure of schedule efficiency
SPI<1 Behind schedule
SPI= 1 on track
SPI>1 ahead schedule
Cost performance index (CPI) - Measure of cost efficiency
CPI <1 Over budget
CPI= 1 on track
CPI>1 under budget
CPI=EV/AC ( Est. work actually done / actual cost)
Control costs (Monitoring & Controlling) 4th
Earned value management (EVM) - Forecasting
Budget at completion (BAC) - sum of all budgets established for the work to be performed
Estimate at completion (EAC) - expected total cost of completing all work