Schedule Flashcards

1
Q

Project Schedule Network Diagram

A

a graphical depiction of the relationships among project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4 Types of Dependencies

A

Mandatory (hard logic, Discretionary (soft logic), External, and Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Logical Relationships

A

dependencies between 2 activities where one must be finished or started before another task can start or end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Lead

A

starting an activity prior to completion of preceding activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lag

A

delaying the start of an activity after the completion of a preceding activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bottom-Up Estimating

A

Breaking a project or activity down into smaller components, then rolling up costs or durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Analogous Estimating

A

Use a previous project as a starting point/reference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Parametric Estimating

A

Use a statistical relationship to calculate cost or duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Three-point Estimating

A

weighted average to increase estimation accuracy; optimistic, pessimistic, most likely
Examples: PERT& Triangular Distribution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PERT Formula

A

(Optimistic + 4xMost Likely + Pessimistic)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Triangular Distribution

A

(Optimistic + Most Likely + Pessimistic)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Total Float vs Free Float

A

Total Float - the amount of time an activity can be delayed without delaying the project completion date

Free Float - the amount of time an activity can be delayed without delaying the earliest following (successor) activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path Method

A

calculating the shortest path for the project, float for each activity, and possible start and finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Crashing vs Fast-tracking

A

Crashing - add extra resources, higher costs

Fast-Tracking - doing activities in parallel, increases risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Resource Leveling vs Resource Smoothing

A

Resource Leveling - adjust the resource schedule when resources have been over allocated; let the schedule slip to level out resources; Histogram

Resource Smoothing - adjust activities to keep resources from exceeding limits; completion date not delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

6.1 Plan Schedule Mgmt Description, Inputs, and Outputs

A

estab the plan to create and manage the schedule

charter, PM Plan: scope mgmt plan, development approach

Schedule mgmt plan

17
Q

6.2 Define Activities Description, Inputs, and Outputs

A

identify specific actions required to produce deliverables

PM plan: schedule mgmt plan, scope baseline

Activity list, activity attributes, milestone list

18
Q

6.3 Sequence Activities Description, Inputs, and Outputs

A

identify relationships between project activities

PM plan: sched mgmt plan, scope baseline, activity attributes, activity list, assumption log, milestone list

project schedule network diagram

19
Q

6.4 Estimate Activity Description, Inputs, and Outputs

A

work periods needed to complete each activity

PM plan: scope mgmt plan, scope baseline, project docs

Duration estimates, basis of estimates

20
Q

6.5 Develop Schedule Description, Inputs, and Outputs

A

create project schedule for proejct execution

PM plan: sched mgmt plan, scope baseline, proj documents

schedule baseline, project schedule, schedule data

21
Q

6.6 Control Schedule Description, Inputs, and Outputs

A

monitor to update progress progress and manage changes to schedule baseline

PM Plan, Proj docs, work perf data

Work performance information, schedule forecasts