Critical Path Method Flashcards

1
Q

Forward Pass

A

EF determined by adding the duration to the ES -1

ES of successor tasks = latest EF of predecessor tasks +1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Backward Pass

A

LS determined by subtracting the duration from the LF +1

LF of predecessor tasks = earliest LS of successor tasks -1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Float (Slack)

A

LF-EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Path

A

the longest duration path through the network diagram. Any delays along the critical path will delay the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly