Critical Path Method Flashcards
1
Q
Forward Pass
A
EF determined by adding the duration to the ES -1
ES of successor tasks = latest EF of predecessor tasks +1
2
Q
Backward Pass
A
LS determined by subtracting the duration from the LF +1
LF of predecessor tasks = earliest LS of successor tasks -1
3
Q
Float (Slack)
A
LF-EF
4
Q
Critical Path
A
the longest duration path through the network diagram. Any delays along the critical path will delay the project.