Cost Flashcards
Variance Analysis
measure the difference between planned and actual costs
Contingency vs Management Reserves
Contingency - amounts set aside by PM to cover known risks and are included in baseline
Management - management sets aside to cover unknown risks and not included in the baseline
Payback Period
amount of time needed to recoup the project’s investment
Benefit Cost Ratio
compares financial yield to the cost of doing the project
7.1 Plan Cost Mgmt Description, Inputs and Outputs
how costs will be estimated, managed, and controlled
charter, PM Plan: Sched mgmt plan, risk mgmt plan
Cost Mgmt Plan
7.2 Estimate Costs Description, Inputs and Outputs
approximation of the cost of resources
PM plan: cost mgmt plan, Qual mgmt plan, scope baseline
cost estimates, basis of estimates
7.3 Determine Budget Description, Inputs and Outputs
establish authorized cost budget
PM plan: cost mgmt plan, resource mgmt plan, scope baseline, basis of estimates, cost estimates
cost baseline, project funding requirements
7.4 Control Costs Description, Inputs and Outputs
monitor and update budget, manage changes to cost baseline
PM Plan, proj docs, proj funding req’ts, work perf data
Work performance information, cost forecasts