Integration Flashcards

1
Q

Process group specific to a PM

A

Project Integration Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

18 PM Plan Components

A

Change, Configuration, Scope, Schedule, Cost, Quality, Resource, Procurement, Communications, Risk Stakeholder, Requirements, Scope Baseline, Schedule Baseline, Cost Baseline, Performance Measurement Baseline, Project Life Cycle Description, Development Approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Charter

A

Formally authorizes the project to exist, establishes PM authority, and documents high-level requirements, milestones, budget, risks, and success criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Work Authorization Systems

A

defines how project work will be authorized to ensure work is done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Issues

A

A matter in question, in dispute, or disagreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Preventative Actions

A

ensure future project work is aligned with the Project Mgmt Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Corrective Actions

A

actions taken to realign the work with the Project Mgmt Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4.1 Develop Project Charter Description, Inputs and Outputs

A

Secure authorization

BC, agreements

Project Charter; assumptions log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

4.2 Develop Project Management Plan Description, Inputs and Outputs

A

integrates all the processes in the planning phase

Charter, other process outputs

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

4.3 Direct and Manage Proj Work Description, Inputs and Outputs

A

performing the work defined, and implementing approved COs

PM plan, proj docs, change requests

Deliverables, work perf data, issue log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

4.4 Manage Proj Knowledge Description, Inputs and Outputs

A

using existtng knowledge and creating new knowledge

PM plan, proj docs, deliverables

lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

4.5 Monitor and Control Proj Work Description, Inputs and Outputs

A

reviewing and reporting progress to meet objectives

PM plan, proj docs, Work Perf reports, Agreements

work performance reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

4.6 Perf Integrated Change Control Description, Inputs and Outputs

A

review, approve, and communicate change requests

PM plan, proj docs, Work Perf reports, Change Requests

change requests, plan updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

4.7 Close Proj or Phase Description, Inputs and Outputs

A

finalize all activities

Proj Charter, PM plan, proj docs, accepted deliverables, business and procurement docs

final product transition, final report