Common Confusions Flashcards

1
Q

Risk Audits vs Risk Review Meetings

A

Audits (macro) are more associated with the Risk Mgmt Plan

Risk Review Meetings (micro) are more focused on the Risk Register and Risk Report - Responses to individual risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Charter vs Project Scope Statement

A

Charter formally authorizes the project to exist. It outlines the project objectives but not the project deliverables

Scope statement would describe the actual deliverables; it outlines what we will deliver to meet the objectives in the charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sign-off on the Project Charter vs sign-off on the Project Mgmt Plan

A

Charter sign-off by the initiator or sponsor

Proj Mgmt Plan sign-off by whole project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Scope vs Product Scope

A

Project Scope defines the way in which the deliverables will be created - how we will deliver the product

Product Scope - deliverables being created, design specifications/features; defined in Prodduct Requirements - features and functions being delivered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Work Performance Data vs Work Performance Information

A

Work Perf Data - output of Direct and Manage Project Work; shows where we are at a given area and what has been accomplished; data rolls up into Work Perf Information

Work Perf Information - variances and analysis; provided to stakeholders to demonstrate project performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work Package vs Activity List

A

Work Package - created first in the Define Activities process - lowest level project work is broken down

Activity List created after the Work Package during the Create WBS process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Analogous vs Parametric Estimating

A

Analogous looks at past project activity to create an estimate. least reliable estimate

Parametric scales the figures taken from historical project information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Total Float vs Free Float vs Project Float

A

Total float is the difference between a Late Finish and an Early Finish. If Late Finish and Early Finish are the same, there is 0 float.

Free float is the amount of time that an activity can be delayed without delaying the start of the earliest successor activity

Project Float is the amount of time the project completion date could be delayed without impacting an imposed deadline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost of Conformance vs Non-Conformance

A

Conformance - all costs incurred to prevent defects in the deliverables

Non-conformance - arises when a defect has already occurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost of Conformance: Prevention Costs vs Appraisal Costs

A

Prevention - spent on front end to help prevent defects from arising

Appraisal - costs incurred to uncover defects; testing and inspection costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost of Non-Conformance: Internal vs External Failure Costs

A

Internal - defect discovered while still in your possession

External - defect discovered by customer; warranty repairs, lawsuits, and lost business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Contingency Reserves vs Management Reserves

A

Contingency - buffers that PMs add to their project cost baseline; known unknowns

Management - set by senior management and not part of cost baseline; unknown unknowns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Control Quality vs Manage Quality

A

Control Quality ensures the correctness of deliverables; deliverables meet the requirements

Manage Quality looks at processes and methodologies we employ in the Quality Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Communication Methods vs Communication Technology

A

Methods - Interactive, push, and pull

Technology - email, phone, fax

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Risk Management Plan vs Risk Register vs Risk Report

A

Risk Management Plan - The ways in which we will manage risk and who has responsibility; contains the Risk Breakdown Structure

Risk Register contains each risk facing the project and our planned response; updated many times

Risk Report contains information about overall project risk, and summary information on individual project risk; an executive summary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Qualitative Risk Analysis vs Quantitative Risk Analysis

A

Qualitative - ranking of the risks according to their priority - risk register

Quantitative - numerical assessment of the risk impact - impact to dollars, schedule, etc.

17
Q

Corrective Actions vs Preventive Actions

A

Corrective - ensures failures do not happen again

Preventive - avoid failures in the first place

18
Q

Quality Audit vs Inspection

A

Quality Audit - technique of manage quality; looks at processes

Inspection - tool of control quality; looks at deliverables

19
Q

Requirements vs Constraints

A

Requirements - features and functionality that a deliverable must include

Constraints - anything that limits a project teams options; time, budget, scope, resources, laws and regulations

20
Q

EAC vs BAC

A

EAC - the total amount of what we project we will actually spend

BAC - the total amount we planned to spend