Who is responsible for managing the location for shuttle apparatus to dump water?
Dump Site Unit Leader
What differentiates between a long and short driveway?
More than or less than 200’
What is unique about fill site engines with electronic governor controls regarding drafting?
Need to always draft and fill in RPM mode, pressure mode can cause damage
Personnel at the fill area need to wear appropriate PPE to include trafic vest and helmet. When would they need to wear PFDs?
If working within 10’ of an open water source
Travel lanes between the dump and fill sites must remain open and where possible wide enough for __.
tankers to pass
What is the formula for Total Tanker Flow?
Total capacity of tanker minus 20% divided by the round-trip time
Officer of the third arriving engine will __.
assume the role of the DSUL
Dry hydrants should be back flushed and tested every __.
six months
What is the recommended number of 6-inch hard sleeves on an engine where rural/suburban water supply areas exist?
Two
How many stop watches are carried in the Water Supply Officer’s bag?
Two
Low level suction strainers allow for engine company drafting down to a water level approximately __.
two inches
Low profile jet siphon strainers allow engines to get water from dump tanks without having to draft by charging which line?
1.75” hose line
Gated Wye set up for LDH have two __ line connections.
3”
What is a triamese?
Three lines into one
Where can unit officers find draft Water Usage Agreement documents for use in private bodies of water?
Water Supply for Suburban and Rural Firefighting Manual pg26
What is the minimum fire flow requirement for supply line in either a nursing or relay operation?
500 GPM
Which engine officer is tasked as the Dump Site Unit Leader (DSUL)?
Third
Which engine officer is tasked as the Fill Site Unit Leader (FSUL)?
Fifth
In a non hydrant areas fires typically occur where hydrants are in excess of how many feet from occupancy fire.
2000 ft
Relay operations generally uses three or fewer engines to supply the attack engine from the water source. This supply line should not exceed how many feet?
3000 ft
The ___ engine unit officer is initially responsible for the duties of the Water Supply Group Supervisor (WSGS) until relieved.
Third
Personnel working within how many feet of an open water source must be wearing PPE, traffic vest and PFDs?
10 ft
What consits of a tanker task force
3 tankers, 1 engine, 1 command officer
By using ____, crews can effectively extend firefighting operations by using less water
Class A or Class B foam
The first engine should lay out their LDH with what attached to it, when personnel are in a nursing operation.
A Siamese
At the fill site how many fill station should you have set up
2
How often should dry hydrants be back flushed and tested
6 months
In relay operations with 4 inch hose are feasible at distances of over____ mile
1
How often should water storage tank systems be checked
6 months
Low-level suction strainers can draft water in a dump tank down to a level of ____ inches.
2
What is the maximum GPM flow for a low level strainer
750
What type of strainer allows engine and tankers to draft from static water source
Floating dock strainer
Below what PSI does the automatic air primer begin to prime at
20 PSI
What application can you use if a LDH Siamese is not available on fill sites
Gated Wye
Who is the Dump Site Unit Leader (DSUL) in a rural water supply operation?
3rd Engine OIC
Who does the DSUL report to?
Water Supply Group Supervisor (WSGS)
Who is the FSUL Fill site unit leader?
5th Engine OIC
For a relay operation how far is the max relay distance?
3000 ft
The NOVA recommendations for tankers state that they must have a 1000 gpm pump and what size water tank?
2000 gallon
Who is the initial WSGS?
3rd Engine OIC
Typically who is responsible for setting up and maintaining the fill site?
5th Engine OIC
Who shall communicate where the fill site location will be?
1st Engine OIC
What does a tanker task force consist of?
1 Eng, 3 Tankers, 1 Command Officer
The FSUL needs to make sure there are how many lines off the Engine to facilitate rapid filling of units?
min 2
Relay operations are feasible up to what distances?
1 mile
The preferred method for continous water supply at a rural water supply operation is?
Nursing/direct fill
It is important that the DSUL knows what the low level strainer is capabile of flowing, what is the max flow for the low level stariner?
750 gpm
When using the jet siphon to transfer water from one pit to another what is the max flow of the jet siphon?
800 gpm
The jet siphon strainer utilizes an 1 3/4 hose to create the venturi affect to move water without the use of the primer, what is its max flow?
500 gpm
In a relay operations what is the max distance between each engine?
1000 ft
Rule of thumb, if the distance to the water source is greater than _____, a tanker shuttle is a better choice.
3- pumper relay
What is a non hydrant box alarm assignmnet?
5 eng, 3 tankers, 2 trucks, 1 Res, 1 ems unit, 2 BC, 1 ems super, 1 safety officer
What is the tanker flow calculation formula?
Tanker flow= capacity- 20% divided by round trip time
In northern Va a non hydranted area is an area with hydrants are more than how many feet from the occupancy on fire?
2000 ft
The movement of water at suburban and rule fires will almost always consist of one of what three types of operations?
Nursing operations, relay operations, shuttle operations
What are the four goals of rule water supply operations?
- Rapid 2. Efficient 3. Expandable 4. Uninterrupted
Where does the first tanker (Nurse Tanker) position in a rule water operation?
Position as close as possible to the attack engine and supply the attack engine with tank water for the initial fire attack.
What are the water supply group supervisors (WSGS) responsibilities?
- Provide adequate water to the incident 2. evaluate the filling in transit capacity of the operation 3. establish and coordinate the fill sites, dump sites, shuttle routes, and or relay operations in both hydrant and non-hydrant areas 5. keep command appraised of the amount of water available 6. Traffic control 7. Ensure Tankers get priority at fill sites 8. Ensure adequate resources are available 9. Establish an alternative radio channel or channels
Who establishes the water supply group supervisor (WSGS) and once established who relieves that initial unit?
The water supply group supervisor is normally established by the third arriving engine officer who will later be relieved by the second arriving command officer
What are the dump site unit leaders (DSUL) responsibilities?
- Manage all activities at the dumpsite 2. evaluate and implement travel routes for incoming tankers 3. designate a staging area for units that will be abandoned so not to impede traffic 4. evaluate and adjust water supply operation 5. keep the water supply group supervisor (WSGS) appraised of the amount of water available 6. ensure tankers get priority to the dumpsite 7. Traffic control 8. Ensure water is transferred in the safest and efficient manner 9. Calculate turnaround time and GPM per unit 10. Expanding nursing or dump site operations as needed 11. Monitor dump site operations for safety
Who is responsible for becoming the dump site unit leader (DSUL)?
The officer in charge of the third engine will become the dump site unit leader (DSUL)
What are the fill site unit leaders (FSUL) responsibilities?
- Manage all activities at the fill site 2. keep the water supply group supervisor appraised of the fill site conditions upon request 3. traffic control 4. ensure tankers get priority at fill sites 5. Ensure units are filled in the most efficient and safest manner
Who is responsible for setting up and becoming the fill site unit leader(FSUL)?
The fifth engine is responsible for setting up the fill site and the OIC will be the fill site leader
When do personnel working at the fill site need to wear a PFD?
Personnel at the fill site need to wear a PFD if working with in 10 feet of an open water source
What is considered a non-hydrant area?
Areas where the hydrants are in excess of 2000 feet from a given structure. Also in areas where infrastructure has failed or limited access highways where water supply may affect incident.
What is the maximum length of supply line laid out by relay engines
3,000 feet
What is the NOVA recommendation for a tanker’s minimum size?
1,000 GPM pump and a 2,000 gallon tank
What makes up a tanker task force?
- One engine 2. Three tankers 3. One command officer