Referral Report Flashcards
Definition of disallowed costs
11.2 (25) Disallowed Cost is cost which the Project Manager decides
* Cost not justified by records
* Cost that should not have been paid to a Subcontractor
* Failure to follow a procurement procedure
* Failure to give an Early Warning
* Failure to correct defects after Completion
* Resources not used to Provide the Works
Ensuring cost certainty under an Option C contract
Transparent Defined Cost
Risk Sharing and Collaborative
Regular cost reporting
Effective use of EWN System
Guaranteed Maximum Price
How is risk apportioned under an NEC Option C contract?
Target Cost means any savings and overspends are shared between both parties
As such, it is in the best interest of both parties to work collaboratively to manage risk
Risk can be managed contractually through:
Cost
- Upper and Lower Limits
Time
- Bonus for Early Completion
- Delay Damages for late completion
Quality is Contractor risk, as have to comply with UU Specs. However Contractor gets paid for rectifying defects prior to completion. Not after.
Not specifically NEC Option C, however Employer risks are stated within Clause 80 and CD1, Contractor all other risks are carried by Contractor
What actions would be carried out if there was the suspicion of the Subcontractor being at risk of insolvency?
As it’s only suspicion, I would run a D&B report on the Subcontractor and hold discussions with Client
Key elements of a business plan?
A Business Plan is a formal document containing the goals of a business, the methods for attaining those goals, and the time-frame for the achievement of the goals
It should include:
- Executive Summary
- Business Strategy
- Business Plan
- Marketing and Competitor Analysis
- Organogram
- Financial Summary
Which piece of legalisation does the Data Protection Act 2018 incorporate into UK law?
General Data Protection Regulations
Regulations/Legislation that sets out how companies need to manage data they hold?
General Data Protection Regulations
Legislation that supports GDPR?
Data Protection Act 2018
Advice which would be provided to the client on MEICA budget sheet/cost report
Risks - Inflation, change in laws/regs
Any omissions from tender - Overall packages or within each package
Opportunities - Discount/buying gain due to purchase across the framework
Design Changes - Result of this on each package
How was the MEICA budget sheet presented to the Client?
IT was an excel document, which consisted of:
- Summary Page - Every Package on and the delta between tender and latest estimate
- Then each tab consisted of a different package, which detailed the risks, omissions, opportunities & design changes
- Option E with Client, therefore enables them to review and query anything, suggest mitigation strategies
Modern methods of construction?
Pre-cast panels
DfMA Solutions
Modular construction
3D Printing Construction
In the water industry - OSEC
How was the advice presented to the Client?
I produced a presentation, which was structed in a clear and organised manner:
- Overview of the
- Information on each methodology
- Comparison of both on:
Cost
Programme
H&S
Sustainability
Quality
- Conclusion incl my recommendation
Advice you would give to someone who was rejecting Early Warnings
Early Warnings are used as a risk management tool and not part of the change management process
Things to consider when advising that the ground conditions risk should not be passed on to the subcontractors
Cost - Inflated prices to deal with the unknown
Programme - Extended programme due to the unknown
Improper management of the risk - can lead to further delays, H&S problems
Quality - lack of experience in managing the risk, could lead to poor techniques
Tender Recommendation Report Example?
Oswestry WTW - Clean Water Pipework
Introduction of package
- Required within the EWI to provide new pipework from 1st Stage RGF to the 2nd Stage RGF and ISPS
Procurement Strategy
- Competitively tendered to ensure the best value
- Single Stage Selective Tendering
- Bidder list, ADP approved, UU approved Cl 26, Internal Supplier 360 Scoring
Tendering Summary
- Date received, all compliant
- Comment on mid-tender meetings
Commercial Compliance
- All agreed to Z Clauses
- Some contractors wanted amended X Clauses (X18 to be included)
- All agreed to Payment Terms
- All held sufficient Insurances
Technical Compliance
- Ensured I included Design/Engineers Comments
- All complied with Specs
- FAT/Quality procedures
Programme Compliance
- All provided tender programmes
- Some couldn’t meet the Cl32 dates
- All provided organograms and resource charts
H&S Records
- No RIDDOR’s
D&B
- Two Contractors were showing moderate or high risk of failure
Recommendation based on the above
Cost v Budget
Risk & Opportunities
- Tight programme, working around others, ensure no delays to access
+ Subby’s could work weekend/nights to reduce programme risk