Contract Practice (Level 1/2/3) Flashcards
CE Procedure under NEC3?
Under Clause 60 of the NEC there are 19 Events which give entitlement to a CE
Once a party becomes aware of a potential compensation event, they must notify the other party as soon as possible, under Clause 61
Under Clause 62, upon notification of a compensation event, a quotation is to be submitted under Clause 62 which should include the assessment of the time and cost implications of the event
The other party should then assess the effect of the CE under Clause 63
Assessment of the CE can be make if required under Clause 64
Compensation Event is implemented under Clause 65
What are the JCT suite of contract options?
Minor Works Building
Intermediate Building
Standard JCT Building
Major Works Building
What are the NEC suite of contract options?
Option A: Priced contract with activity schedule
Option B: Priced contract with bill of quantities
Option C: Target contract with activity schedule
Option D: Target contract with bill of quantities
Option E: Cost reimbursable contract
Option F: Management contract
Option G: Term Contract
Key differences between NEC and JCT
Programme - JCT contract does not have a programme as a contractual document. NEC programme is key, it is a contractual document and to be regularly updated
Payment - JCT contract payment section is clear, is all in one section and easy to follow. Under the NEC contract it is located in three different locations and can be confusing
Contract Administrator v Project Manager - Both responsible for unbiased contract administration. Must be PM under NEC, can be anyone competent under JCT ie PM, QS, Architect
How does a standardised form of contract benefit a project?
Keeps contractual bias to a minimum
Proven caselaw
Saves time and cost for developing a unique contract for each project
What typical amendments have you encountered? & do you agree with them?
- Payment terms
- Change management i.e. CE’s and periods of reply.
Payment terms are agreed on the basis of cashflow availability.
Change management is agreed based on type of work to be carried out and our liability with the client, ensuring no gaps.
What if you were asked to provide advice?
Secondary clauses (X Clauses within NEC) – I can advise on
Amendments to core clauses (Z Clauses) – seek legal advice
What are the parties’ responsibilities and duties under a contract?
Performance of work or services in accordance with the specifications and quality standards
Payment obligations
Compliance with Law and Regulations
Communication and cooperation
What is the significance of the Local Democracy, Economic Development and Construction Act 2009?
The LDEDC 2009 Act ties in with the payment provision and adjudication procedures set out in the HGRA Act 1996. It amends and strengthens the effectiveness and enforceability of adjudication decisions.
What are the essential components of a valid contract?
Offer - Willingness to contract on specified terms
Acceptance - Act of agreeing to form a legally binding agreement
Consideration - Something of value
Legal Intention - Intention to form legally binding agreement
Capacity - Have the ability to enter the contract
By way of examples can you tell me how the essential components of a valid contract find their way into an NEC construction contract?
Offer and Acceptance – NEC contract documents include the contract form, tender documents, contractors’ proposals and terms and conditions of the offer.
Consideration – Agreed Contract Sum
Capacity – Presumed to have the legal capacity to enter a binding agreement.
Legal Intention – Execution of the contract documents by both parties
What is the principal difference between a parent company guarantee and a performance bond?
PCG – If a company goes insolvent or is unable to provide the works, the parent company is obliged to complete the works.
PB – Provided by a third party (insurance), the guarantee the performance of a contractor under a construction contract. E.g if a product/ system is not achieving the performance requirements set out in the contract.
2 types of performance bond?
On Demand - does not require proof of a breach of contract
Conditional - requires proof of liability before payment
Updates to NEC3 following Construction Act update?
Changes to Payment Provisions in Option Y(UK)2
Changes to adjudication provisions in W2
Key changes from NEC3 to NEC4?
Two new contracts:
- BBO Contract
- ALC Contract
Risk Register > EWN Register
Employer > Client
Works Info > Scope
AFP must be submitted for a payment, rather than a PM obliged to make an assessment
New W3 Dispute Clause
What is NEC4?
New Edition of NEC released in 2017
NEC3 Dispute Resolution?
Two Tier Approach:
- Adjudication (W1, when HGCRA doesn’t apply or W2 when HGCRA applies)
- Arbitration or Litigation