Quantification & Costing (Level 1/2/3) Flashcards

1
Q

Why do quantities need to be measured in a uniform way?

A

Consistency
Comparability
Accuracy
Compliance with regulatory requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the different method of measurement?

A

Standard Method of Measurement (SMM)
New Rules of Measurement (NRM)
Building Information Modelling (BIM)
Civil Engineering Standard Method of Measurement (CESMM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can tell me what is your understanding of RICS code of Measuring Practice?

A

Provides guidance and standards for the measurement of buildings and land, ensuring consistency, accuracy, and transparency in measurement practices within the property and construction industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When would the RICS code of Measuring Practice be used in your day-to-day employment?

A

When quantifying materials for new orders on construction projects, for example measuring the amount of fill required for trenches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

GEA, GIA and NIA how are they each measured?

A

GEA (Gross External Area) - area of a building measured externally at each floor level
GIA (Gross Internal Area) - area of a building measured to the internal face of the perimeter walls at each floor level
NIA (Net Internal Area) - usable area within a building measured to the internal face of the perimeter walls at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which method of measurement would you consider is the most appropriate for measuring civil engineering works?

A

CESMM (Civil Engineering Standard Method of Measurement)

CESMM provides detailed rules and guidelines for measurement of civil engineering projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why was NRM introduced?

A

Replaced SMM7 and introduced to provide a common and consistent basis for the production of cost plans to ensure greater confidence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

RICS Measurement Documents?

A

NRM 1 - Order of cost estimating and planning
NRM 2 - Detailed measurement for building works
NRM3 - Life Cycle Costing
ICMS - Sets out the measurement hierarchy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do British Standards affect the measurement of construction works?

A

They provide standardisation of:
- Measurement methods
- Measurement units, terminology
- Quality assurance/ compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do the Building Regulations affect the measurement of construction works?

A

Building regulations affect measurement of construction works in several ways:
- Space requirements
- Accessibility and inclusivity
- Structural stability
- Fire safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is your understanding of the shorter schedule of cost components?

A

It is a shorter version of the Schedule of Cost Components (SCC) which is used in options A and B and only to assess compensation events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you cost works?

A

When required to cost works, whether that’s a CE or for the FTC, I use a variety of methods:
- CESMM
- Historic Prices
- Subcontract Prices
- In house cost databases
- Price books (CECA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Prupose of a BoQ?

A

Provides an accurate picture of the scope of works
Provides a common/consistent ground for pricing
Enables easy/accurate tender comparison
Enables contract works to be valued and interim payments to be made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Example of a BoQ I have prepared?

A

Oswestry WTW - Surfacing package
I met with design team to ensure all information was available
Worked with the engineers to understand required quantities
Produced a BoQ based off Design and Required quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Value Engineering?
What is Value Management?

A

VE - Identifying areas where cost savings can be made, without compromising on the overall quality
VM - Similar to VE, however in the pre-construction therefore aims at reducing the need for VE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is classed as Prelims?

A

Site Set Up
Management & Supervision
Insurances
Task Lighting
Protection & Temporary Barriers

17
Q

How did you determine appropriate daywork rates for inclusion in the sub-contracts you have procured?

A

When procuring Subcontractor packages, I ask them to complete Contract Data Pt 2 and provide a Schedule of rates. I check each rate is inline with the industry benchmarks

18
Q

Oswestry WTW Project - What method of measurement did you use in compiling the bill of quantities?

A

I used CESMM, and accounted for:
- Subbase
- Base Course
- Binder Course
- Surface Course
- Wearing Course

19
Q

Oswestry WTW Project - Why did you use a bill of quantities (Option B)?

A

Quantities were hard to define
Allowed for greater flexibility
Enabled less risk to be built into the price
Agreed set of rates, less chance of disputes
Satisfied both parties

20
Q

Oswestry WTW Project - How did you deal with the sub-contractor prelims in the pricing document?

A

The Subcontractor provided a weekly prelim rate, which was paid in accordance with their programme

21
Q

Can you provide an example of costing of works using quotations or day works?

A

I have costed a CE to the client which included a Subcontractor quotation and the relevant subcontractor fee percentage

22
Q

Oswestry Project - Can you give an example of disallowed cost that you have agreed with the Employer?

A

Within our Contracts, there is amendments to the standard NEC3 which states the following are Disallowed Costs:
- Admin Personnel (HR, Directors, Accounts, etc)
- Hand tools (Drills/Saws/etc)

23
Q

Oswestry Project - Can you give an example of disallowed cost that you have not agreed with the Employer and how you resolved the difference?

A

Yes, one example was:
Under the NEC, a Cost can be disallowed because the Contractor did not follow a procurement procedure.
We are required to submit the name of each proposed Subcontractor to the Client for acceptance under Clause 26.
The Client disallowed costs of a subcontractor one month, stating the name had not been submitted for acceptance.
However, this was a misunderstanding, as I didn’t have CEMAR access to begin with, the name was submitted via email to the Employer, accepted, but not followed up on CEMAR.
I resolved it, by providing the evidence and uploading it to CEMAR. The cost was then allowed

24
Q

Flying Start Project - What did you do if the sub-contractor was not available for the site walk?

A

Each month I provided a number of days and times, therefore it was very rare for a subcontractor not to be available for a site walk.
On the rare occasion they weren’t, I ensured I took photo evidence to support my assessment

25
Q

How does the sub-contracts being lump sum minimise any confusion and disputes relating to what was due for payment?

A

Because an activity can only be paid once complete, there is no mechanism for part payment under the NEC. As such, following a site visit, we can discuss the works in conjunction with the activity schedule and agree what items have been completed.

26
Q

Can you provide an example of selecting appropriate pricing documents?

A

Oswestry - Surfacing - BOQ over Activity Schedule:
- Quantities were hard to define
- Allowed for greater flexibility
- Enabled less risk to be built into the price
- Agreed set of rates, less chance of disputes
- Satisfied both parties

27
Q

What is IPMS?

A

International Property Measurement Standards
Sets outdefinitions of measurement and the principles of what should or shouldn’t be included within a measure
Most recent publish 2023