Contract Administration (Level 1/2) Flashcards
Who is the contract administrator under the different JCT and NEC contract forms?
JCT
- Contract Administrator
- Can be any professional competent, QS, Architect, PM
NEC
- Must be the PM
Who are the parties to an NEC contract?
Clause 11.2(11) The Parties are the Employer and the Contractor
What are the general obligations of the Employer under a construction contract?
Provide the contractor with the facilities to complete the works in accordance with the contract and programme
What are the general obligations of the Contractor?
Complete the specific work, in accordance with the agreed terms and specifications as well as the conditions required by the contract and statutory requirements
What is the role of an NEC PM and the NEC Supervisor?
Project Manager - Full authority to make decisions, duty to be impartial
Supervisor - To check the works are carried out as prescribed within the contract
What are the different pricing options under a NEC contract?
Option A - Priced Contract with Activity Schedule
Option B - Priced Contract with BoQ
Option C - Target Contract with Activity Schedule
Option D - Target Contract with BoQ
Option E - Cost Reimbursable
Option F - Management Contract
Option G - Term Contract
Which NEC forms are remeasurable and which are reimbursable?
Remeasurable
Option B
Reimbursable
Option E
What are the different certificates on a typical NEC contract?
Completion/Sectional Completion Certificate
Defects Certificate
Payment Certificate
Termination Certificate
Flying Start Project - What was involved when you certified Completion on the scheme?
Completion is granted when the Subcontractor has
- Done all the work which the SWI states he is to do by the Subcontract Completion Date and
- Corrected notified Defects which would have prevented the Employer or the Contractor from using the subcontract works or Others from doing their work
I then issued a Completion Certificate
Can you describe a project example of your involvement with dispute avoidance?
On Verulam Rd, I was involved in Negotiation, a form of ADR. The pre cast concrete supplier had raised CE’s totalling £300k. The CE’s were not moving forward and neither party could come to an agreement at project level, therefore we agreed for both our legal representatives to meet and review each CE and agree a FA Settlement. I was tasked with making notes and meeting minutes documenting the agreements, then by following up with the Final Account Statement.
Difference between Novation & Assignment?
Novation - Mechanism which allows a party to transfer all of its contractual obligations to another party
Assignment - The same process, however contractual burdens cannot be transferred, only benefits
Items to include on an AFP
Option C or E with Client, therefore CTD plus costs that will of been paid by the due date, plus the fee, minus disallowed, minus retention, minus previous payments
Difference between JCT & NEC?
NEC can be used for building & civil engineering projects, whereas JCT is only for building
NEC can be adopted to bespoke contracts due to the options available, whereas JCT has a standard set of clauses
What is fustration?
When an event beyond control of both parties makes it impossible or illegal to fulfil their contractual duties
The contract will automatically discharge
Difference between Under Hand & Deed?
Limitation Period:
Underhand - 6 Years
Deed - 12 Years