Project Finance (Level 1/2/3) Flashcards
Different techniques of cost control / reporting?
Cost Control:
- Budgeting and Cost Management
- Short Interval Control
- Risk and Change Management
Reporting:
- CVR’s
- FTC’s
- Cashflow
What is the difference between cost control and cost reporting?
Cost control
Monitoring, managing, and regulating project costs to ensure that they remain within budgeted limits and align with project objectives.
Cost reporting
Communication of project cost-related information to relevant stakeholders in a clear, accurate, and timely manner.
As a QS what should you be doing for your client?
- Cost planning and budgeting
- Value engineering
- Procurement advice
- Tender documentation and contract administration
- Cost control and reporting
- Claims management
How would the number of changes affect the frequency of reporting?
If there was frequent changes then you could look to introduce more frequent reporting, bi-weekly
How do you compile a risk register?
Identify project risks
Categorise the risks
Assess impact and likelihood
Assign risk owner
Develop mitigation strategies
Monitor and review
Key Components of a CVR?
Executive Summary
CTD Analysis
EVA Analysis
FTC
Risk & Opportunity
Approved CE’s / Pending CE’s
Purpose / Benefit of a CVR?
Manage Financial position of the project
Inform Senior Management on the Financial position of the project
Allow Senior Management to advise on any risk reduction matters to improve/mitigate financial position
How to create a cashflow?
I would use the construction programme and tender breakdown to populate the cashflow
It would be split into cost headings: Staff, Plant, Materials, Subcontracts, Design, Labour
I would forecast the costs for the construction activity inline with the programme
This would determine my outgoings
Then our contracts are Option C or E, therefore cost, plus fee back the period prior
Benefit of a cashflow?
Allows the business / client to understand the financial requirements over the project duration
Allows for budgeting, can understand time when there will be surplus cash and areas of cash shortfalls
Enables companies to grow more predictably
What does CEMAR stand for?
Contract Event Management and Reporting
Difference between contingency and risk?
Contingency covers costs that are unknown unknowns
Risk covers known unknowns
What is a provisional sum?
Figure that covers works where the exact scope and requirements are undefined
Analysis period of Whole life cost?
UU have an Asset life table within the EWI, therefore it is in accordance with this:
M&E Plant - 23 years
Civil Structures - 60 years
Prime Cost v Provisional Sum?
Prime Cost - Allowance made for supplying an item, doesn’t include related works
Provisional Sum - Allowance made for an item of work that cannot be priced at contract award as the extent is undefined
Flying Start Project - How do you compile the forecast cost to complete? How do you assure yourself that it is correct?
- Ensure CTD data is true and accurate
- Forecast remaining costs inline with programme
- Ensure risks are accounted for