Reactor, MFP, and Turbine Trips Flashcards
List the Rx Trips
- SR High Flux
- IR High Flux
- PR High Flux, Low Setpoint
- PR High Flux, High Setpoint
- PR High Rate
- OTΔT
- OPΔT
- PZR High #
- PZR Low #
- PZR Level High
- RCS Loss of Flow
- RCP Busses UV
- RCP Busses UF
- RCP Breaker Position
- SGWL Lo-Lo
- SGWL Lo with Feed Flow < Steam Flow
- SI
- Turbine Trip
List the “At Power” Rx Trips
- PZR Low #
- PZR Level High
- RCS Loss of Flow
- RCP Busses UV
- RCP Busses UF
- RCP Breaker Position
SR High Flux Trip Coincidence, Setpoint, and Interlock
- 1/2 SR NI
- 9 x 10^4 CPS
- P-6
IR High Flux Trip Coincidence, Setpoint, and Interlock
- 1/2 IR NI
- Current equivalent of 22.5% RTP (20)% RTP
- P-10
PR High Flux Trip (Low) Coincidence, Setpoint, and Interlock
- 2/4 PR NI
- 20% RTP
- P-10
PR High Flux Trip (High) Coincidence, Setpoint, and Interlock
- 2/4 PR NI
- 107% RTP
- No Interlock
PR High Positive Rate Trip Coincidence, Setpoint, and Interlock
- 2/4 PR NI
- 4.5% rise in 2 seconds
- No Interlock
OTΔT Trip Coincidence, Setpoint, and Interlock
- 2/4
- Variable Setpoint
- No Interlock
OPΔT Trip Coincidence, Setpoint, and Interlock
- 2/4
- Variable Setpoint
- No Interlock
PZR High # Trip Coincidence, Setpoint, and Interlock
- 2/4 # detectors
- 2385 #
- No Interlock
PZR Low # Trip Coincidence, Setpoint, and Interlock
-2/4 detectors
- 1950#
- P-7 Interlock
RCS Loss of Flow Coincidence, Setpoint, and Interlock
- 2/3 detectors on 1/4 loops (2/3 detectors on 2/4 loops)
- 91% (91%)
- > P-8 (< P-8, but > P-7)
PZR High Water Level Coincidence, Setpoint, and Interlock
- 2/3 detectors
- 92%
- P-7 Interlock
RCP Busses UV Trip Coincidence, Setpoint, and Interlock
- 1/2 on 2/4 busses
- 88 V
- P-7 Interlock
RCP Busses UF Trip Coincidence, Setpoint, and Interlock
- 1/2 on 2/4 busses
- 58.2 Hz
- P-7 Interlock
RCP Breaker Position Trip Coincidence, Setpoint, and Interlock
- 2/4
- Open Aux Switch
- P-7
SGWL Lo-Lo Trip Coincidence, Setpoint, and Interlock
- 2/3 detectors on 1/4 SG’s
- 5 (22)%
- No Interlock
SGWL Low with Feed Flow < Steam Flow Trip Coincidence, Setpoint, and Interlock
- 1/3 level detectors on 1/4 SG’s AND 1/2 flow detectors on same SG
- 15 (26)% AND 0.71E6 (1.47E6) lbm/hr
- No Interlock
Turbine Trip Coincidence, Setpoint, and Interlock
- 2/3 pressure detectors OR 4/4 Stop Valves
- Auto stop oil pressure < 800# OR stop valves < 1%
- P-8 Interlock
List the MFP Trips
- Manual
- Rx Trip
- SI
- Hi-Hi SGWL
- IOPS
- Thrust Bearing Wear
- Low Lube Oil Pressure
- Low Suction Pressure
- Low Condenser Vacuum
- Low Trip Header Pressure
List Main Turbine Trips
Hardwired
- ATWS
- SI
- SGWL Hi-Hi
- Manual
- Overall Differential Trip
- IOPS
- Stator Water Cooling Loss
- Thrust Bearing Wear
- Unit Differential Wear
- Rx Trip
PLC
- Low Lube Oil Pressure
- Low Vacuum
- Low Control Oil Pressure
- Low Trip Header Pressure
- Loss of both DC power supplies
- Overspeed