Quantification & Costing of construction works Flashcards
Talk me through when you’ve selected appropriate pricing documents.
Essex Lodge - The design provided a good level of detail, therefore, I advised to utilise a BoQ, which allowed accurate quantification regarding progress of works executed.
Tell me about when you’ve negotiated a contract sum.
Project London - I examined the contractors tender submission and agreed that the rates matched those of a concurrent running project. The remaining items were reviewed and compared against rates from other projects and negotiated to arrive at a reasonable contract sum.
Tell me about when you’ve negotiated and/or agreed the valuation of
construction works?
Essex Lodgde -
* Planning - prior to start I revisit the contract conditions and determine the clients specific payment requirements and issue the team a valuation schedule
* Pre Valuation - Upon receipt I’ll complete an initial desk check of the contractors application
* Valuation - I’ll visit site and make fair assessment of the works through inspection.
* Valuation documentation - I’ll complete final desk check of the valuation. If I have made any adjustments or there are any errors I’ll rectify and send revised valuation back to the contractor to agree on changes made.
* On agreement I will prepare and complete valuation documentation and issue to CA/EA/PM
What does valuation documentation include?
Contract dependant -
* JCT; Interim Payment Certificate/Notice
* NEC; Interim Payment Assessment
* Statement of retention
* Sectional/Practical/Partial Possession Certificate
What are the pitfalls of BoQ?
- Errors within the document, the client bears the risk
- Lengthy production process
- High production costs
What are some other advantages of BoQ?
- Clear & extensive statement of works to be executed
- Provides consistent basis for tender evaluation
- Provides stong basis for post contract management
- Provides a schedule of rates
Could you have considered any alternative pricing documents?
Schedule of works
What are the disadvantages of a schedule of works?
- It can be difficult to properly assess tender returns if you wish to understand why there are large price variances on certain items between suppliers
- Agreeing variations can be problematic
What are the advantages of a schedule of works?
- Transfers the risk of errors in quantifying over to the contractor
What is a PTE?
Pre-Tender Estimate
* Final cost check before tender bids
Have you prepared a Pre Tender Estimate (PTE)?
- London - I produced a pricing schedule for tender issue, I then priced the activities within the document myself and compared it against the contractors bid
In your PTE what are 2 risks you advised your Client of?
- Contingency
- Inflation
- Exclusions
What is the purpose of cost management?
- Control cost
- Resource planning
- Cost estimation
- Budgeting
You mention advising on appropriate methods of measurement, who did you give this advice to?
- The contractor quantified a variation in a different method to the NRM2, this produced higher costs.
Was the contractor on your project in London, bound to match rates on like-for-like activities if the project is under a separate contract?
No, technically as it is a separate project they were welcome to apply new. However, the contractor was engaged on the promise that rates would be adhered to on any like-for-like activities.