Quantification & Costing of construction works Flashcards

1
Q

Talk me through when you’ve selected appropriate pricing documents.

A

Essex Lodge - The design provided a good level of detail, therefore, I advised to utilise a BoQ, which allowed accurate quantification regarding progress of works executed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tell me about when you’ve negotiated a contract sum.

A

Project London - I examined the contractors tender submission and agreed that the rates matched those of a concurrent running project. The remaining items were reviewed and compared against rates from other projects and negotiated to arrive at a reasonable contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tell me about when you’ve negotiated and/or agreed the valuation of
construction works?

A

Essex Lodgde -
* Planning - prior to start I revisit the contract conditions and determine the clients specific payment requirements and issue the team a valuation schedule
* Pre Valuation - Upon receipt I’ll complete an initial desk check of the contractors application
* Valuation - I’ll visit site and make fair assessment of the works through inspection.
* Valuation documentation - I’ll complete final desk check of the valuation. If I have made any adjustments or there are any errors I’ll rectify and send revised valuation back to the contractor to agree on changes made.
* On agreement I will prepare and complete valuation documentation and issue to CA/EA/PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does valuation documentation include?

A

Contract dependant -
* JCT; Interim Payment Certificate/Notice
* NEC; Interim Payment Assessment
* Statement of retention
* Sectional/Practical/Partial Possession Certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the pitfalls of BoQ?

A
  • Errors within the document, the client bears the risk
  • Lengthy production process
  • High production costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some other advantages of BoQ?

A
  • Clear & extensive statement of works to be executed
  • Provides consistent basis for tender evaluation
  • Provides stong basis for post contract management
  • Provides a schedule of rates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Could you have considered any alternative pricing documents?

A

Schedule of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the disadvantages of a schedule of works?

A
  • It can be difficult to properly assess tender returns if you wish to understand why there are large price variances on certain items between suppliers
  • Agreeing variations can be problematic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the advantages of a schedule of works?

A
  • Transfers the risk of errors in quantifying over to the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a PTE?

A

Pre-Tender Estimate
* Final cost check before tender bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Have you prepared a Pre Tender Estimate (PTE)?

A
  • London - I produced a pricing schedule for tender issue, I then priced the activities within the document myself and compared it against the contractors bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In your PTE what are 2 risks you advised your Client of?

A
  • Contingency
  • Inflation
  • Exclusions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of cost management?

A
  • Control cost
  • Resource planning
  • Cost estimation
  • Budgeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You mention advising on appropriate methods of measurement, who did you give this advice to?

A
  • The contractor quantified a variation in a different method to the NRM2, this produced higher costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Was the contractor on your project in London, bound to match rates on like-for-like activities if the project is under a separate contract?

A

No, technically as it is a separate project they were welcome to apply new. However, the contractor was engaged on the promise that rates would be adhered to on any like-for-like activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did you advise your client on the final account?

A

I advised my client that my last formal cost report gives an indication of the estimated final account and therefore, the client can express their overall position.
I also advised on items outside of the contractors account, such as;
* Professional fees
* Loose furniture
* Audio Visual
* Escorting
* Other employer direct costs

17
Q

You mention assessing final accounts, how do you prepare?

A

When preparing for a final account I;
* Review the account
* Compile supporting documentation
* Ensure non-measured sums are omitted or adjusted via instruction
* Capture all contract instructions and variations
* Discuss items the client is willing to concede on and which they are not

18
Q

How are your final account meetings structured?

A
  • In a informal or formal environment.
  • Each party will review one anothers supporting documentation and review their postion before negotiating and finding common ground.
  • No set rules regarding structure
19
Q

What process do you follow when agreeing a final account?

A
  • Make an assessment
  • Discuss outstanding variations with client and understand their commercial position
  • Compile supporting documentation
  • Email the contractor after agreement confirming final agreed figure
  • Issue statement of final account to the contractor for signature
20
Q

What does a statement of final account include?

A

It is not an official document, but it would typically include;
* Adjustment of provisional sums, quantities and prime costs
* Contract instructions
* Loss and expense
* Fluctuations
* Variations

21
Q

What are the differences between NRM1, 2 & 3

A

NRM 1 – provides guidance on the quantification of building works for preparing cost estimates and cost plans.

NRM 2 - NRM 2 provides standard detailed rules for the measurement and description of building works, in order to prepare bills of quantities (BQs) and quantified schedules of works.

NRM 3 - NRM 3 provides essential guidance on the quantification and description of maintenance works

22
Q

How do you value for preliminaries?

A
  • Preliminaries are usually a mixture of fixed charge and time-related charge item,
  • Time-related charges can be quantified and costed per week.
  • Fixed charges will require quotations specifying total cost for a period.
23
Q

How did you advise your client on change?

A

It depends on the form of contract, but typically;
* Where changes to the works character or condition occur, this constitutes change.

24
Q

What are appropriate methods of measurement?

A
  • Standard set of measurement rules, such as NRM2
25
Q

You mention producing a BoQ for your £3m scheme in London, including the groundworks. In your experience name some line items captured in your measurement of the groundworks?

A
  • Site clearance
  • Site Preparation
  • Excavation
  • Disposal
  • Imported Filling
26
Q

In your experience name some line items captured in your measurement of the internal works?

A
  • Finshes to floors/walls/ceilings
27
Q

In your experience name some line items captured in your measurement of the External works?

A
  • Kerbs
  • Planting trees
  • Surface application
  • Turfing
28
Q

In your experience name some line items captured in your measurement of the internal doors?

A
  • Door set
  • Roller shutters
  • Ironmongery
29
Q

Why did you use NRM 2? What is the difference between NRM 2 and NRM 1? Why didn’t you use IPMS?

A

As I was preparing a BoQ, I utilised the NRM2 as that is its purpose. NRM 2 provided standard rules for the measurement and description of building works, in order to prepare bills of quantities (BQs) and quantified schedules of works.

whereas;
NRM 1 – provides guidance on the quantification of building works for preparing cost estimates and cost plans.

  • The revised NRM suite of documents are linked to the IPMS and incorporates the same principles
30
Q

What is the ICMS?

A
  • International Cost Management Standards
  • A global high-level principle-based cost classification system
31
Q

What is the purpose of RICS cost prediction?

A
  • Sets out principles of global cost estimating/planning
32
Q

What does IPMS stand for?

A
  • Internation Property Measurement Standards