Contract Practice Flashcards
Level 3 - Sectional completion
LED project - Tell me about when you provided reasoned advice on any specific matters of a contract and why?
- Advised on dividing contract in sections
- Enabled the client to plan their operations as sections are clearly identified with start/completion dates and rate of LDS.
- Meet client requirements
- Allowed client to vacate areas at agreed times rather than vacate entire space
Level 3 - Sectional completion
What were the benefits of dividing the contract into sections, as apposed to doing it any other way?
- Both parties understand their liability/obligation
- Allows the employer to plan/programme their operation (decant/vacate)
- Pre-agreed and written in the contract, scope & extent clearly identified
*
Level 3 - Contract selection
Why did you advise on a JCT IC 2016?
Why were other forms or suites discarded?
- Simple nature
- Contained appropriate provisions such as; Sectional completion to meet client requirements
- Minor Works doesn’t allow for sections
- Standard Building Contract for larger more detailed projects
Level 3 - LDs
On your LED lighting project, how did you advise your Client on the Liquidated Damages provision in the contract?
- Genuine pre-estimate of likely loss
- Reasonableness of LD’s
- Method of calculation
- How the LDs are specified in the contract (days/weeks)
- Obligation under contract - how LDs become payable
- Risks involved in under/over valuing or leaving blank
- Termination
Level 1 - LDs
What are the risks of unreasonable LD amounts?
- Construed as a penalty
- Unenforceable
- Employer will have to claim unliquidated damages
- Will have to prove actual loss, remoteness, causation, reasonable steps to mitigate loss
Level 1 - LDs
What are the risks of under/over valuing or leaving LD’s blank?
- Employer cant change or increase under valued LDs if sums doesn’t cover their loss.
- Employer cannot levy damages against contractor if damages are stated as ‘Zero’
- Unreasonable sums are construed as a penalty and left to claim unliquidated damages
- Leaving the provision blank assumes unliquidated damages.
Level 1 - LDs
What are the Pro’s and Con’s of Unliquidated Damages?
Pro’s
* Employer could be compensated for sums not previous considered or forseeable
Con’s
* Employer has to prove actual loss, remoteness and loss mitigation
* Hard to prove
* Contractor doesn’t know their liability and cannot budget for risk of delay or adjust tender accordingly.
Level 2 - LDs
On your LED project, what considerations were mad in calculating the LD’s?
- Loss of rent
- Level of occupancy
- Storage costs
- Fee’s
- Financing costs
- Accommodation costs
Level 1 - LDs
What are the advantages of LD’s?
- Pre-defined sum
- Recoverable without proof of loss
- Contractor knows the limit of their liability
- Allows contractor to budget risk of delay and adjust tender
- Confirms remedy to the Employer
Level 3 - Completion
On your LED Lighting scheme, how did you advise your client before including Sectional Completion provisions in the contract?
- Provisions required for sectional completion to apply
- Risks associated with incomplete information
- Consequences of sectional completion
- EOT provisions
Level 1 - Completion
What are the advantages of sectional completion?
- Gives you a clear cut off point
- Allows parts of the business to remain operational
- Minimises disruption to client operations
- Removes need for entire vacation
- Parties understand their liability for each section
Level 1 - Completion
What are the consequences of completion?
- End of liability for LD’s.
- The client takes control of the building and should transfer and maintain building insurance.
- Risk of loss and damage passes to the client, which terminates any further requirement for the contractor to insure the works.
- Beginning of rectification period
- Half retention releases
- Preparation of final account
- Assessmennt of EOT claims
Level 1 - Design potions
What is CDP?
- Contractos design portion
- Contractor designs and builds discrete parts of the works
Level 1 - Design portions
What is required from the contractor for their CDP?
- Collateral Warranty
- Take out and maintain Professional Indemnity Insurance
- Contract sum analysis
Level 1
Post completion, can the contractor still be liable for damages?
- If the client suffered loss or damage as a result of the contractors defective work