Contract Administration Flashcards

1
Q

Talk me through procedure you’ve followed for making payment in a contract.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

On project London, you mention the contractor wanted to remove the damages. In practice how did you advise your client on the risks?

A
  • Provision must state NIL or ‘n/a’ within the particulars
  • Amending the contract to remove the provision entirely
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

If the damages provision was left blank, how would that impact the contract?

A
  • The contract assumes unliquidated damages apply
  • Unliquidated damages are damages payable for breach, but the amount is not pre-agreed
  • Compensation is at large
  • The amount of compensation is to be determined after the breach occurs by a court
  • Employer will have to prove actual loss incurred
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the pitfalls of unliquidated damages?

A
  • It can be harder to prove losses incurred
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages of unliquidated damages?

A
  • it allows for recovery of losses which may have been impossible to foresee
  • or to estimate with any certainty before the breach.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the advantages of liquidated damages?

A
  • Do not require proof of loss after the event/ or prove actua; damage
  • simply deducted by the employer under contractual mechanisms in the contract
  • agreed in advanced and stated in the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In your role as project QS how did you contribute to an assessment of an extension of time claim?

A
  • Refer to the contract and tender documents to see if genuine change occurred
  • Ascertain the direct loss and/or expense
  • Feed these responses back to the CA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

As a QS what responsibilities do you have as a QS which relates to the completion of a project?

A
  • Settling the final account
  • Releasing half retention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of retention?

A
  • Provides the client with some security that the contractor will return to correct any defects during the retification period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is retention taken incrementally?

A
  • Not taken in a lump sum at the beginning of the project as it may impact contractors cash flow,
  • also if the contract sum is adjusted retention is over/ under-valued
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Level 1 - Final account

What are the time-bars under the JCT to settle the project final account?

A
  • Depends on standard form
  • Traditional - not later than 3-months after information supplied by the contractor (which should not arrive any later than 6-months after issue of practical completion certificate.)
  • D&B - not later than 2-months after information supplied by the contractor (which should not arrive any later than 3-months after issue of practical completion certificate.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What provision does the CA refer to - to form their opinion on EOT?

A
  • Relevant Events
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What mechanisms within the JCT is used for assessing any costs relating to the contractors EOT claim

A
  • Relevant Matters
  • Loss & expense
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

As CA what methods are there to assess delay?

A
  • Overview of the facts (cause and extent of delay)
  • Planned v actual progess (as built)
  • Critical path analyses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the process of an EOT claim?

A
  • The Contractor will notify the CA of delay
  • CA can then request further information from the contractor
  • CA should refer to the relevant events to ensure the claim is eligible
  • In principle the CA assess whether or not the delay has had an effect on contractual completion date and what that effect is.
  • Response is due as reasonably practicable, but within 12-weeks of receipt of ‘required particulars’ (request information)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Level 1 - Loss and Expense

What are the timescales for ascertaining Loss and Expense?

A
  • 28 days from receipt of initial assessment
  • 14 days of any update
17
Q

What are the timescales for ascertaining Loss and Expense at final account?

A
  • no later than 3-months after receiving information from contractor
  • Contractor has 6-months to provide assessment
  • If the 6-month period expires, the CA must notify the contractor they have 1-month to provide the information
  • If the contractor fails, the CA shall make assessment on the information in their possession
18
Q

What are the timescales for issuing final certificate?

A
  • Within 28 days of expiry of the rectification period
19
Q

Level 1 - EOT

How long do you have to ascertain a EOT claim?

A
  • Within 12-weeks of receiving particulars
  • Within 12-weeks of PC