Quantification and costing of Construction works Flashcards

1
Q

What are the key differences between SMM7 and NRM2?

A
  • NRM2 now provides further elemental breakdowns within work section
  • many small items are now deemed included
  • Clearer definitions of prime costs and prov sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is your understanding of a Prime cost?

A
  • Is the cost of an item that has either not been selected or the price was unknown as the time the contract was entered into.
  • the client would therefore pay the difference in price.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would you advise your client if an error was found within your Cost Plan?

A
  • If the error was identified before a contract had been entered into, then a discussion between client and contractor could be held to agree to amend.
  • If a Contract has been signed, then both parties would have to stand by the rate/qty. Only through agreement by both parties could the error be changed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Where would you find the defined GIA & GEA

A
  • The code of measuring practice notes, published by the RICS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly