Project Financial Control & Reporting Flashcards

1
Q

How did you establish that your cost report template was suitable?

A
  • I used my organisations in-house Cost report template
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did the cost report deal with changes?

A
  • The report had a section that listed Contract instructions and anticipated instructions, to capture all changes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you advise the Client on risk within your Cost Report ?

A
  • Identified risk items with the project team
  • Listed the items out within a Risk register
  • Valued the items on cost and programme implications
  • Built overall contingency allowance
  • Included contingency within my Cost report
  • Contingency was updated and offset throughout the project as and when the contractor priced the risk items.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tell me about a specific risk you have advised a Client on?

A
  • I advised on the potential cost and programme implications of window options to Duke Street project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How was the cost of risk reported?

A
  • Every risk was assessed and listed within a risk register
  • These risks were valued and an assessment was made against the potential cost impact.
  • Once this risk had been priced by the contractor, the risk contingency allowance was reduced/offset by the firm cost.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What did you include within your Cost Report/Financial Statement?

A
  • Executive summary
  • Contract sum
  • Contract instructions
  • anticipated variations
  • Claims
  • Cashflow forecast
  • Anticipated contract sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why might a variation arise on a project?

A
  • Change to specification/design
  • Discrepancies between contract docs
  • Potential errors in design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You mentioned you have included Provisional sums, were these defined or undefined?

A
  • These were defined provisional sums, as I had sufficient design information to allow me to make an appropriate allowance in pricing, programme and prelims.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you value the Landscaping works on the Brook?

A
  • I used the revised landscaping drawings to build my take-off
  • I used SPONS, BCIS and in-house cost data to apply current market rates to each measured item.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What did you include within your Cost Plan?

A
  • Executive Summary
  • Elemental breakdown
  • Area Schedule
  • Drawing List
  • Prov sums
  • Assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you value the Preliminaries, measured works and risk?

A
  • I used BCIS for inflation rates and location indices

- SPONS and in-house cost data to value items at current day market rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly