Project Financial Control & Reporting Flashcards
How did you establish that your cost report template was suitable?
- I used my organisations in-house Cost report template
How did the cost report deal with changes?
- The report had a section that listed Contract instructions and anticipated instructions, to capture all changes.
How did you advise the Client on risk within your Cost Report ?
- Identified risk items with the project team
- Listed the items out within a Risk register
- Valued the items on cost and programme implications
- Built overall contingency allowance
- Included contingency within my Cost report
- Contingency was updated and offset throughout the project as and when the contractor priced the risk items.
Tell me about a specific risk you have advised a Client on?
- I advised on the potential cost and programme implications of window options to Duke Street project.
How was the cost of risk reported?
- Every risk was assessed and listed within a risk register
- These risks were valued and an assessment was made against the potential cost impact.
- Once this risk had been priced by the contractor, the risk contingency allowance was reduced/offset by the firm cost.
What did you include within your Cost Report/Financial Statement?
- Executive summary
- Contract sum
- Contract instructions
- anticipated variations
- Claims
- Cashflow forecast
- Anticipated contract sum
Why might a variation arise on a project?
- Change to specification/design
- Discrepancies between contract docs
- Potential errors in design
You mentioned you have included Provisional sums, were these defined or undefined?
- These were defined provisional sums, as I had sufficient design information to allow me to make an appropriate allowance in pricing, programme and prelims.
How did you value the Landscaping works on the Brook?
- I used the revised landscaping drawings to build my take-off
- I used SPONS, BCIS and in-house cost data to apply current market rates to each measured item.
What did you include within your Cost Plan?
- Executive Summary
- Elemental breakdown
- Area Schedule
- Drawing List
- Prov sums
- Assumptions
How did you value the Preliminaries, measured works and risk?
- I used BCIS for inflation rates and location indices
- SPONS and in-house cost data to value items at current day market rates