Need To Knows Flashcards
Can you name different tender routes ?
If so what are the differences between them?
Single stage tender - traditional route when you have sufficient design information for the contractors to tender against.
Two stage tender - usually adopted on a D&B contract where the employer requirements are not sufficient enough for the contractor to provide a realistic price. Contractor will tender a price for the design along with a schedule of rates. Enables the client to transfer design risk to the contractor.
Negotiable tender
What is the process when Practical Completion is awarded?
- Contractor to supply building control certificate
- Insurances are transferred from the contractor to the client
- O&M manuals
- H&S files
- User manuals
What is the difference between a relevant matter & relevant event?
- Relevant event - caused by either the client or a neutral event.
Examples: variations, non-payment, instructions, strike, act of terrorism. - Relevant matter - where the client is solely responsible for the delay in a project. This may allow the contractor to claim direct liquidated damages.
Examples: delay to give possession of site, delays in instructions, payments, failure to provide materials on time.
How would you derive at an appropriate PI Insurance level for e contractor?
- Based off of the Contract sum value and any associated costs such as professional fees and the like.
How did you value the variations once you are in a contract?
- I would firstly refer to the contract rates.
- if the works are outside of the contract works, I would value the works using Spons or in house cost data.
- if I am unable to price the works, then the day work rates stated within the contract will be used.
Can you name the different types of procurement routes?
- D&B
- traditional
- managing contracting
- construction management
- measured terms
What is your organisations business plan?
- Continue to grow through new acquisitions
- continue to recruit competent staff
- identify new sectors to work in.
What is the structure of the RICS?
- Privy council (awards royal charter / grants)
- Governing council
- Management board
- regulations board
- finance committee
- world regional boards
Who is the CEO of the RICS?
Ann Gray
Who is the executive director of the RICS?
Richard Collins
What is cash flow?
The movement of money in and out of a business
How would you create a cash flow forecast?
- From the cost plan and project programme
- can be created on excel
- presented in the form of a graph, S-Curve
If a tender was received on time, but the works didn’t commence until a few months later, what would you need to check?
Check the Form of Tender for how long the price/offer is valid for. could be 60 or 90 days.
If a Contractor included a Provisional Sum against an item within the Tender, what would you do?
- Seek further information from the Contractor and ask this to be removed
- Provide commentary on this within my Tender Report
- Could possibly invalidate the submission
What are the payment timescales for the JCT D&B Contract?
- Contractor to issue valuation before the interim valuation date
- Due Date 7 days after valuation date
- Payment Notice, no later than 5 days after the due date
- Final Date for payment 14 days after Due date