Contract Administration Flashcards

1
Q

What were the effects of issuing a non-completion certificate ?

A
  • EOT request
  • Additional prelims weekly costs
  • Client to claim damages
  • Revised programme date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Did you issue any other contractual notices/certificates ?

A
  • A payment certificate
  • Non-completion certificate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What should be provided by the contractor on Practical Completion of a project?

A

Contractor should provide:
- Building control sign off
- O&M manuals
- Warranties
- User guides
- H&S file

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you require in order to issue a Practical Completion certificate ?

A
  • Building control sign off
  • F10 certificates
  • Building warranties
  • O&M manuals
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tell me about the insurance provisions within the JCT Contract?

A

JCT payment schedule within contract

Option A: new built works insured by the employer

Option B: New build works insured my the contractor

Option C: refurbishment works insured by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did the Contractor inform you of the delay?

And what did you issue in response ?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens on completion of a project?

A
  • Issue of the PC certificate
  • Release half the retention
  • Ends contractors liability of LADs
  • Initiates start of defect period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens when a contractor issues a change request?

A
  • Client evaluates if the change is acceptable
  • Issue of an instruction to the contractor or consultant
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you fund a change within a project?

A
  • If available, the change can be funded using the project contingency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the process of the change procedure?

A
  • Reasons for the change
  • Who is requesting it
  • Consequences of change T/C/Q
  • Risks
  • Instruction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How can you minimise change on a project?

A
  • Site investigations
  • identifying risks early on
  • ensuring the design is comprehensive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you monitor progress on site?

A
  • regular progress meetings, contractor progress report
  • regular site visits, check the progress on site.
  • check works against the programme
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were your roles/duties as Contract Administrator?

A
  • Issuing instructions
  • Chairing meetings/ providing minuets
  • Reviewing claims
  • Change control
  • Administering the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an Employers Agent?

A
  • They administer the contract under the D&B contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the role of the QS under the JCT form of contract?

A
  • Qs is named under Article 4 of the JCT form
  • Carry out valuations
  • Value variations
  • Ascertain Loss & Expense
  • Cost Planning
  • Cost reporting
  • Agreeing Final accounts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the role of the Client under the JCT?

A
  • Ensure Contractor and Designer carry out duties under the CDM regulations 2015.
  • Give possession of the site
  • Pay for works
  • Not to interfere with CA/QS (Consultants)
17
Q

What is the Contractors role under the JCT?

A
  • Carry out and complete works
  • Comply with instructions
  • Insure the works
  • Carry out duties as Principle Contractor listed within the Contract.
18
Q

What is the difference between the CA and EA role?

A
  • EA acts in the best interests of the client
  • CA must act impartially when administering the contract
19
Q

What are the time periods when granting an EOT?

A
  • CA has 12 weeks to review and respond to the EOT claim
  • if there is less than 12 weeks before PC, then the CA should consider reviewing before this time frame.