Procurement and Tendering (Level 3) Flashcards
How do you develop an effective procurement strategy?
- Define Project Requirements
- Conduct Market Analysis
- Risk Assessment
- Select Procurement Method
Are there other options beyond traditional and D&B? When would you use one over another?
Other options include:
o Management Contracting
o Framework Agreements
You would management contracting over D&B for high complexity projects and a contractor/ subcontractor expertise is required. They can provide valuable input during the design development phase.
When would you advise the use of two-stage tendering? & what are the benefits?
Advise it on high value, complex projects with uncertain requirements.
o Early contractor involvement
o Risk mitigation – contractor capabilities.
o Cost certainty
o Time efficiency – shortlisting preferred contractors early and focus on detailed negotiations.
How do you identify a client’s approach to time, cost and quality?
o Initial consultation
o Develop a project brief.
o Identify a client’s priorities.
o Review historical data from previous clients.
o Risk assessment and management.
o Communication and engagement.
How does management contracting differ from construction management?
Management contracting is when the client appoints a contractor to manage the construction works on their behalf, including letting of packages etc.
Construction management is when the client hires a CM to provide project management services and acts as an advisor to the client, but does not construct the works
In what situation would construction management be appropriate?
Complex projects which require expertise in project management.
Design-bid-build procurement routes where they provide an extra layer of project oversight and coordination.
What is your understanding of PFI as a form of procurement?
PFI means Private Finance Initiative.
In a PFI arrangement, a private sector consortium typically designs, builds, finances, and operates a public infrastructure project over a long-term concession period.
What are the factors that would be considered in deciding the most appropriate procurement route for a project?
The route needs to align with the project’s objectives, constraints and characteristics:
o Project complexity
o Tine constraints
o Budget and cost considerations
o Risk allocation and management.
What sources of guidance do you use when you are procuring and tendering contracts or packages of work?
The RICS has guidance on tendering strategies, it outlines the different routes of procurement, issuing tenders, conducting interviews and scoring them.
Also standard forms of contract and government procurement guidelines.
How do you determine which pricing document to use with a sub-contract?
o Project complexity
o Contractual framework
o Risk allocation.
o Payment mechanisms
How did you choose the tenderer for the civil package on Forton?
Through CBA analysis once all tenders had been received. Once the scope was fully aligned, checks were made from an operational, technical and commercial perspective.
Can you explain why you would use either a D&B or management contracting route?
D&B:
o Client deals with a single entity
o Overlapping design and construction phase
o Cost certainty
Management Contracting:
o Early contractor involvement
o Flexibility to manage change.
o Expertise within the Contractor and Subcontractor
Why use an NEC Option A sub-contract?
o Fixed price approach
o Risk allocation on the subcontractor.
o Incentives them to get paid by completing activities
What alternatives could you use to an NEC Option A and when would you use each of them?
o Option B – if the work was well defined and quantifiable.
o Option C – Project scope is not fully defined and they each have the incentive to save money.
o Option E – Project involves research or development where the scope is highly uncertain.
Outline the contents of the invitation to tender for the package
o General enquiry document (brief work description, drawings, key dates, specifications etc.)
o Works information
o Form of contract