Contract Administration (Level 2) Flashcards

1
Q

Who is the contract administrator under the different JCT and NEC contract forms?

A

JCT:

o Responsible for administering the contract (issuing instructions, valuing variations and
certifying payments).

o Additional responsibilities in DB over SBC relating to design coordination.

NEC:

o The Project Manager is responsible for administering the contract, issuing instructions, managing risks, assessing compensation events (variations), and certifying payments (ECC).

o Under PSC, the PM is responsible for overseeing the delivery of PS’s such as design, engineering and consultancy work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who are the parties to a JCT SBC?

A

o Employer
o Contractor
o Architect/ CA
o QS
o Principal Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who are the parties to an NEC contract?

A

o Employer
o Contractor
o Project Manager
o Construction Supervisor
o Other Consultants or Advisors (if applicable)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the general obligations of the Contractor?

A

o Performing the works in accordance with the contract.
o Provide labour, plant and materials.
o Comply with law and regs.
o Follow design requirements.
o Meet quality standards.
o Complete the works on time.
o Maintain site safety.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the general obligations of the Employer under a construction contract?

A

o Providing access to site
o Providing information
o Appointing PM
o Design requirements
o Approval and permissions
o Provide finance
o Make payments
o Notify defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does a Contract Administrator role differ from that of an Employer’s Agent?

A

o CA primary focus is administering the contract.

o EA does that too, whilst having more PM duties such as coordinating design, managing risk and ensuring compliance with statutory requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the different pricing options under a construction contract?

A

o Fixed price (lump sum).
o Cost reimbursable.
o Schedule of rates.
o Target cost.
o Guaranteed maximum price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the different certificates on a typical JCT/NEC contract?

A

o JCT Certificate of Practical Completion v NEC Completion Certificate.
o Interim payment certificates.
o Defects certificates.
o Extension of time certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What certificates have you compiled and issued?

A
  • Completion certificates.
  • Defect certificates.
  • Payment certificates.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you give an example of involvement with dispute avoidance?

A
  • Adjudication on Williamsgate with Electrical subcontractor.
  • Internal dispute resolution methods in accordance with the framework agreement, again on Williamsgate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In addition to dealing with variations and payments, can you explain how you dealt with completion/possession issues with the sub-contracts you administered?

A

o Quality of workmanship during the reedbed liner subcontract works. Leaks leading to defects leading to disputes until rectification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When does the defect correction period begin?

A

At Completion for Defects notified before Completion and when the Defect is notified for other Defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

You discuss experience with NEC3 Option B Contracts. What happens under an NEC3 Option B if something is clearly indicated on the tender drawings, but is missing from the bill of quantities?

A

Cleared up through Clause 60 by dealing with the inconsistency between the BoQ and the Works Information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly