Commercial Management (of Construction Works) Flashcards

1
Q

What is your understanding of the components that make the cost of the project to a contractor?

A

Under the NEC contract, the Schedule of Cost Components lists out all of the costs in which the contractor will be paid for on the project. This includes People, Equipment, Plant, Materials, Subcontractors etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the key components of a CVR report in respect to cost/value to date?

A

Analysis of the cost to date vs forecast in previous months across the various headers listed in the Schedule of Cost Components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key components of a CVR report in respect to cost/value to complete?

A

Aligning the latest programme to the forecast to complete in the CVR report ensures its updated with the latest and most accurate data. Ensuring that each of the activities are picked up and allowances have accurate figures against them. It is also important to ensure the risk register is up to date with costs attributable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do you understand by the term liability? & how does it differ from cost?

A

Liabilities are the debts a business owes and expenses are the costs a business incurs to generate revenue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What would you consider before constructing a cashflow forecast?

A

Consider the income and outgoings during your cashflow forecast period and sum the running cashflow amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is wasteage calculated?

A

Concrete wastage (%) = [(Volume of concrete actually used - Volume of concrete as per design) / Volume of concrete as per design] x 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What insurances are required under a contract? How are they included in a tender?

A

Professional indemnity
Contractors all risk
Employers’ liability
Public liability
Products liability

When sending out tender enquiries, the above insurances are listed in section 8 of Contract Data Part One

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What current challenges is covid and/or Brexit brining to Commercial Management

A

Suppliers are struggling with increased costs, labour and supply shortages following departure from the EU.
COVID challenges have minimised since the rapid decrease in cases, however at the time it caused increases in time and cost due to the restrictions put in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you explain how you compile the cashflow forecast for subcontractors

A

Table out the forecasted costs for the project in line with each of the cost components and mark that as ‘outgoings’. For the income, table out the predicted payments we are to receive from the client. This generates the running cashflow amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you populate the risk and opportunity register?

A

Each month myself, the contractors PM and the risk coordinator will review the risk register addressing if a risk or opportunity has passed or present. An impact, mitigation and scoring is applied to each risk which also contributes to the value of the risk or opportunity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you deal with anticipated variations, those that haven’t reached a CE status or are disputed as a CE by the PM?

A

If a CE has been notified and it is disputed by the PM, I will request their position on the matter and respond accordingly. If a meeting is required, then I will call a meeting with the relevant members required to resolve the situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you explain more about how you incorporate the latest programme into the CVR?

A

Within the CVR document is a formulated programme tab which you can insert an excel version of the Clause 32 which becomes usable data. The cost component tabs can be linked by activity ID reference which attributes a start and finish date to a cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you provide an example of value engineering you have undertaken on your projects?

A

I carried out a value engineering exercise on the ducting contained within an existing subcontract package. After review of the drawings, I proposed a simpler duct run which discounted various manholes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you do with the cost data generated by your projects? Is it kept centrally for future use?

A

Yes, the cost data is filed centrally for the different departments to access. For example, the estimating department can reconcile live costs for materials, subcontract packages, labour rates etc for use on future bids.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What other methods of compiling a cashflow forecast have you used?

A

I have carried out weekly cashflow forecasts for subcontractor payments only whereby I create a list of all subcontractors and our liabilities with them and compare it to the dates we are to be paid from the client where we have applied for said payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On Forton, how did the 4-month delay happen, was it a domestic issue or did the client have any culpability?

A

The four month delay/ extension was due to a number of factors:
o Weather delays
o Slow production and inefficient labour
o Poor forecasting from the site manager

16
Q

What were the financial implications of the labour and plant increase on Forton and what impact did your intervention have?

A

The financial implications resulted in a circa £200k increase to labour and plant. This reduced our risk allowance considerably and had a negative effect on the pain and margin. My intervention to draft a detailed programme and track on a weekly basis held the site team accountable and gave clearer direction as to what work is required to be complete day by day. It resulted in no further increases.

17
Q

What lessons did you learn from this and how differently would you advise your senior management in the future?

A

Begin to plan earlier with the site team.
Have them bought into a programme that’s been agreed.
With knowing the details earlier, I would advise senior management that there is an exercise to be carried out which will result in an increase. By doing this earlier, it negates the larger impact of the shock and allows the project team to plan accordingly.

18
Q

Can you provide another project example where you have advised at a senior role regarding project cashflows?

A

Cashflow become an issue across the framework, as suggested by senior management. I advised that it will be a good idea to have each project’s QS table out the cash that their project is due to pay over the forthcoming weeks. This was implemented on a weekly basis and allowed the finance team to understand how much cash we required.

19
Q

Can you outline what’s included in the Commercial Management of Construction RICS Guidance Note?

A
  1. Value Engineering
  2. What is a commercial manager (managing relationships and maximising business profitability)
  3. Cost and cashflow analysis