Construction Technology & Environmental Services (Level 3) Flashcards
How does planning permission impact on design?
- Compliance with local laws/ regulations
- Modifications to suit planning authority and public
- Constraints on land use and access
What other legislation impacts on construction?
CDM Regulations 2015
Health and Safety at Work Act 1974
Building Act 1984 – inclusive of the Building Regulations as and SI.
How does the age of the building affect construction methods?
Materials availability and quality
Building codes and regs
Structural design and techniques
Can you give me examples of 2 alternative air condition systems?
Ground source heat pumps – uses heat from the ground in cold and warm temperatures to heat/ cool the property.
Air source heat pumps - extract heat from the outdoor air and transfer it into buildings to provide heating and hot water
What do you understand by the term bus bar? Where would you expect to see such an item?
A busbar is installed within a power distribution board and is designed to connect circuit devices to isolation devices.
What are the RIBA stages?
0 – Strategic Definition
1 – Preparation and Brief
2 – Concept Design
3 – Spatial Coordination
4 – Technical Design
5 – Manufacturing and Construction
6 – Handover
7 – Use
What are the advantages of a steel framed building over a concrete frame?
Speed of construction
Higher weight to strength ratio
Sustainable
Can you give me some examples of alternative drainage systems?
SuDS - manage surface water run off in a sustainable manner slowing rate of flow and reducing flood risk
Green roofs - a roof with vegetation and media which absorbs water.
Infiltration systems - involve directing stormwater runoff to infiltration trenches, chambers, or soakaways where it can infiltrate into the ground. Infiltration systems help reduce surface runoff, recharge groundwater, and prevent flooding
Explain 3 different piling techniques.
CFA – Once the hole has been bored, concrete is pumped in, then a steel reinforcement cage is inserted.
Secant – A secant pile wall consists of overlapping (secant) piles to form structural or cutoff walls and achieve the required water tightness
Sheet - narrow sheets of material, usually designed with an angular profile and with interlocking edges
How did you analyse the difference between the road construction and truck paving to ensure a like for like comparison?
Both exercises were to be delivered by the direct delivery team we had on site. The estimate consisted of labour, plant and materials for each option. The meterage for the standard road construction and truck paving was the same. I obtained quotes for the rates of each material type. I sat with the site team and discussed durations, gang sizes and applicable plant and applied it to each of their programmes.
Did you consider how both solutions of the road construction compared on a whole life cost comparison? If so, how did you undertake the comparison?
Asphalt initial cost less than truckpave
Asphalt requires less maintenance and attention and repairs to specialist materials
Resurfacing risk of asphalt is minimal given its use (2 tankers per week).
Were there any other design solutions that you explored for the roadworks?
A concrete road, however initial costs were too high. Even given its durability. Plus the client didn’t want this option due to its aestheics
Can you provide another project example of you undertaking work in relation to this competency? Wigan
Yes, on the Wigan project we considered using a trench box method to construct a manhole, however, given the severe ground conditions this was not viable. A sheets and frame method was suggested which provides better support in poor ground conditions.
How did the concrete and GRP designs compare from a whole life cost perspective?
The construction costs for both options was significantly different for various reasons, as explained in the write up.
Due to the tanks being in the ground, there aren’t any operating or maintenance costs associated.
However, the concrete pipes had a shorter life cycle and therefore would need to be replaced earlier.
What was the effect on the programme of changing to GRP?
In total a saving of circa 10 weeks against the programme. This was due to:
o A saving on the manifold and pipework installation due to a lighter material, ease of handling and jointing methods.
o A saving on the backfilling due to not having to backfill around FRC works