Contract Practice (Level 3) Flashcards

1
Q

How do variation requests work?

A

They are used when there is a need to make changes or variations to the original scope outlined in the contract. You are to:

o Identification of the Variation

o Submission of Variation Request to Contract Administrator which includes details of the event, reasons for change, proposed modifications and associated cost and time implications.

o Evaluation and Approval

o Implementation

o Adjustment of Contract
Sum and Completion Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the JCT suite of contract options?

A

o Design and Build
o Minor Works
o Short Form
o SBC/Q

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NEC alternatives? How do the two suites differ?

A

iChemE

o Origin and scope – iChemE are typically used for process based projects assigned to address the unique technical and commercial requirements. NEC was developed by the ICE and is used across various sectors. They are easily adaptable to different project types and procurement strategies.

o Risk allocation – iChemE allocates risk in a manner than reflects the nature of the process. Risk allocation provisions address technical risks and performance guarantees. NEC has a collaborative risk management approach where the risk allocation is shared between the parties. They also have EWN’s, risk registers and CE’s to manage fairly and transparently.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does a standardised form benefit a project?

A

o Keeps contractual bias to a minimum.
o Proven caselaw
o Saves time and cost for developing a unique contract for each project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What typical amendments have you encountered? & do you agree with them?

A

o Payment terms
o Change management i.e. CE’s and periods of reply.

Payment terms are agreed on the basis of cashflow availability.
Change management is agreed based on type of work to be carried out and our liability with the client, ensuring no gaps.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What if you were asked to provide advice on amendments to the NEC Contract?

A

o Secondary clauses (X Clauses within NEC) – I can advise on

o Amendments to core clauses – seek legal advice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the parties’ responsibilities and duties under a contract?

A

o Performance of work or services in accordance with the specifications and quality standards

o Payment obligations

o Compliance with Law and Regulations

o Communication and cooperation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the significance of the Local Democracy, Economic Development and Construction Act 2009?

A
  • Adjudication can apply to written and oral contracts
  • Mandatory payment notices and other notices following
  • Strengthened the right to suspend work for non payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is adjudication recognised in standard forms of construction contracts?

A

NEC contracts have been revised to incorporate provisions related to payment, adjudication, and dispute resolution in compliance with the LDEDC Act 2009. For example, NEC contracts include mechanisms for prompt payment, issuing payment notices, and referring disputes to adjudication, as required by the Act.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

By way of examples can you tell me how the formation of a legal contract find their way into an JCT construction contract?

A

Offer and Acceptance – JCT contract documents include the contract form, tender documents, contractors’ proposals and terms and conditions of the offer.

Consideration – Agreed Contract Sum

Legal Capacity – Presumed to have the legal capacity to enter a binding agreement.

Mutual Consent – Execution of the contract documents by both parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the essential components of a valid contract?

A

Offer, Acceptance, Consideration, Legal Capacity, Legal Purpose (Non Illegal)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the principal difference between a parent company guarantee and a performance bond?

A

o PCG – If a company goes insolvent or is unable to provide the works, the parent company is obliged to complete the works.

o PB – Financial instrument provided by a third party (insurance), the guarantee the performance of a contractor under a construction contract. E.g if a product/ system is not achieving the performance requirements set out in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you name 2 types of performance bond?

A

o Bid bonds.

o Payment and performance bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Have you dealt with collateral warranties, performance bonds or PCGs on your projects? If so, can you provide details of how you did so?

A

PCG only, a contract with an MCC supplier, whom we have a framework agreement with, have a parent company. This contract was set to be over £1m therefore our company stipulates that a PCG is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Have you experience of using letters of intent?

A

No experience with letters of intent, however I am aware of the risks associated:

o Non-binding meaning there are no legally enforceable obligations

o Ambiguity and lack of clarity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How have you dealt with completion of your projects with your sub-contractors and/client?

A

Yes, I have both awarded subcontractors and been awarded by the client. Once the criteria set out in the contract is met by my company or a subcontractor, we either receive or issue a completion certificate which fully acknowledges that the work is complete and the defects liability period has begun.

Upon completion and issuance of the completion certificate, the parties may proceed to finalize the account for the works, including any adjustments for compensation events

17
Q

What is your process for formally agreeing final accounts?

A
  1. Prepare the final account – all additional costs to the tendered prices scheduled out.
  2. Linking the last formal cost report – all costs to this point should be agreed, anything new is all that requires discussion.
  3. Final account meetings – agreement on the last few items.
  4. Structuring the final account (terms)
  5. Execution and release of retention
18
Q

Have you had cause to deal with loss and expense claims on your projects?

A

No, however I have had experience dealing with compensation events under the NEC Contract.

19
Q

How do you ensure CEs under the main contract and those under sub-contracts are linked, where they need to be, ensuring MWHT isn’t left exposed?

A

I ensure that any amendments to clause’s 60 to 65 are back to back with the subcontractor’s subcontract. It is important to pass on this risk such that MWH aren’t exposed to all risks set out by the employer.

20
Q

Can you provide an example of a CE not being agreed or accepted?

A

W&B Wigan (Restricted working access over MH01)

  • Unable to progress with works due to tracking over existing chmaber
  • Temporary works solution required to enable tracking
  • Use of grab wagon over standard equipment

Rejection for
- Chamber always been shown in contract drawings
- Subby required to produce temporary works
- Health and safety risk in accordance with mentioned specs in contract

21
Q

How do you ensure compliance with the contract and legislation for payments?
The contract

A

The contract sets out the requirements that of the relevant legislation for payments:

o Payment notices in accordance with the statutory requirements of Section 110 of the Construction Act.

o Issuance of a payment certificate in accordance with section 111 of the Construction Act. This also refers to issuing payless notices if you intend to pay less than the notified sum.

o Dispute resolution process - Section 108 of the Construction Act provides for statutory adjudication to resolve payment disputes quickly and cost-effectively.

22
Q

Have you issued a Payless Notice? Explain how and why you would use it.

A

Yes, on the Forton project a civil subcontractor had applied for various accepted CE’s, of which the quotations were not yet agreed. However, as a gesture of good will, and that the work was complete, I certified their applied amounts in full (on account) until we had agreed a price.

Subsequently, we had agreed a value for each of the CE’s. I revised the payment certificate and issued them a payless notice within the time frames set out in the subcontract.

23
Q

How was your advice received by MWHT and the sub-contractor for the welfare building package amendments?

A

I held a meeting with the subcontractor to discuss the proposed amendments, which concluded in agreement on most.

Then, I set up another meeting with senior management advising them on the position of the project, the contract and potential implications of said changes.

24
Q

How did you persuade senior management to depart from the standard risk position for the welfare building package?

A

I explained the nature of the works required by the contract and advised that, despite the amendments differing from the standard risk position, our exposure is minimal subject to the contract being drafted correctly.

24
Q

Can you give examples of the risks you cite that led to the sub-contractor suggesting an Option E sub-contract on Williamsgate?

A

o Unfinished design – there were small elements of work with unfinished design which would have to be captured at a later date.

o Potential interface with other subcontractors on site – it was a large site with multiple subcontractors on it. They were concerned that this would cause them delays. However, we stipulated that if their programme is correct and the contract is written accordingly, this can be captured by the compensation events listed in an Option A subcontract.

24
Q

How did you advise the sub-contract to be amended such that it would deal with these risks?

A

o I advised that we include the current information relating to the works into the subcontract and to add wording into the works information addressing that further design work is required in this area which will be subsequently instructed by the contractor.

o For the interface concerns, we advised them to draft their programme carefully with what areas they needed access too and when. If we delayed them access to this area, it would be captured under Clause 60.1 (3).

24
Q

In addition to considering the cost of providing temporary power, did you advise of any other implication to the project in terms of cost and programme?

A

Yes, we advised on the costs to install and deinstall the temporary power facilities as well as a proposed assumption that if the electrical supplier is further delayed, we are to receive another compensation event. The PM accepted both.

25
Q

What certificates are issued on both JCT and NEC Contracts?

A

JCT:

  • Practical Completion
  • Sectional Completion
  • Non-Completion (Contractor fails to complete and LD’s begin)
  • Defects Certificate
  • Final Certificate (Final account)
  • Interim Certificate of Completion of Making Good Defects (Defect rectification before Final Certificate)

NEC:
* Payment Certificate
* Completion
* Sectional Completion
* Defects

26
Q

Compare the difference of a CA to a PM.

A

**CA responsibilities: **

Role is** administering the contract **on behalf of the Employer

  • Issuing instructions and certificates
  • Managing variations and changes to the works
  • Administering payments
  • Handling contractual correspondence

They could also have a **dual role **such as the consultant, employers agent, PM.

PM responsibilities:

Role is managing the overall project delivery, including administering the contract and overseeing construction activities.
* Administers the contract in accordance with NEC procedures
* Issues **instructions
and deals with
CE’s and EWN’s**
* Ensures compliance with **project objectives, timelines and quality standards **

PM holds more authority than CA

27
Q

Role of a CA, EA & QS under JCT?

A

CA handles contractual matters, issues instructions and certificates, manages variations, and oversees compliance with contract terms.

EA manages and coordinates the project on behalf of the employer, including liaising with the design team, contractors, and other stakeholders.

QS** prepares cost estimates, manages budgets**, evaluates tenders, and administers financial aspects of the project.

28
Q

What are the different payment provisions between NEC and JCT?

A

JCT - Contractor does valuation
NEC - PM makes assessment

JCT has the dates for various notices in accordance with HGRA but NEC only has it as an option under YUK2

29
Q

What is the difference in a JCT and NEC contract?

A
30
Q

How is novation different to assignment?

A

2 different methods of transferring contractual rights and obligations.

Novation is substituting one party with another. Complete transfer of both rights and obligations. CLEAN BREAK.

Assignments is the transfer of contractual rights to a new party. The original party remains liable for their obligations under the contract.

31
Q

What is a collateral warranty and when may one be used?

A

They create contractual relationships between the main parties of a contract and a third party.

One may be used when investors are involved.

32
Q

What is the Housing Grants Construction and Regeneration Act?

A

Significant piece of legislation in the United Kingdom designed to regulate payment practices and dispute resolution in the construction industry.

33
Q

Do you know of any construction works the HGCR excludes?

A

Assembly, installation, and demolition of plant or machinery on water treatment works sites.

34
Q

Under the HGCRA, what are the payment timeframes?

A

21 day payment cycle (NEC)

Assessment Date (7 calendar days before Due Date)
Payment Notice due (5 days after Due Date)
Final Date for Payment (9 days after the Payment Notice)
Payless Notice (7 days before Final Date for Payment)

35
Q

What is the period for reply for CE’s under NEC?

A

61.4 states two weeks from Notification
62.3 states 1 week to submit a quotation, 4 weeks to assess it.