What is the purpose of the Managing Product Delivery process?
A
Manage and control work between project manager and team manager.
2
Q
Who creates checkpoints reports and why?
A
Created by team manager to keep the project manager informed on the progress on the work package.
3
Q
What are the 4 activities in the stage boundary process?
A
Planning next stage
Update project plan
Update business case
Report stage end or produce exception plan
4
Q
What is the purpose of project closure?
A
Provide a fixed point to check that the project has reached its objectives and that the products have been accepted.