What’s the Moscow abbrivation?
Must have, should have, could have, won’t have for now.
Tell me, why must we have this feature?
It is essential for the viability of the project and its absence would affect project objectives. The end product will not work without.
Tell me, why is this feature a should have?
Its absense would weaken the business case, but the project will still meet its objectives.
Tell me, why is this feature a could have or nice to have?
It’s useful, but its absense will not weaken the business case.
What are the 3 types of issues that may have to be escalated?
Request for change (suggestion not earlier agreed on)
Off-spec (agreed on, but not forecasted to be provided).