Prince 15 Flashcards
What is the purpose of the Directing a Project process?
Enable project board to be accountable and overall control.
Where is the following documented: How and how often should the PM communicate with the project board?
Communcation Strategy Document.
Who is responsible for ensuring continued business justification?
Project board.
What is the purpose of the Control a Stage process?
Project manager to assign and monitor work, deal with issues, report progress to Project Broad and take corrective action to stay within tolerances.
Which Prince2 process describes the day to day work of the Project Manager during a stage.
Control Stage process.
Which report does the Project Manager usually use to report to the project board during a stage?
The highlight report.
There are 8 activities within the Controlling a Stage process. Which 3 groups are they divided into?
Work Packages
Monitoring and Report
Issues
What are the 2 monitoring and report activities in the Control a Stage process?
- Compare stage progress to stage plan
- Create highlight reports for project board
What are the 3 issues activities in the Control a Stage Process?
- Capture and size potential impact of issues and risks.
- Take corrective action
- Escalate.
Which 3 registers should be updated during the Control a Stage Process?
Issue register
Risk register
Quality register