Unit 1 is at 100% power with all systems in a normal lineup.
PNA-D25 develops a ground and de-energizes.
What is the status of the RTCBs?
A. All four are closed.
B. RTCB ‘A’ is open, the others are closed.
C. RTCB ‘A’ and ‘C’ are open, the others are closed.
D. All four are open.
C
Unit 1 is at 100% power with all systems in a normal lineup.
PKC-M43 develops a ground and de-energizes.
What is the status of the RTCBs?
A. All four are closed.
B. RTCB ‘C’ is open, the others are closed.
C. RTCB ‘A’ and ‘C’ are open, the others are closed.
D. All four are open.
C
Unit 3 is at 100% power with all systems in a normal lineup.
PKC-M43 develops a ground and de-energizes.
What is the status of the RTCBs?
A. All four are closed.
B. RTCB ‘C’ is open, the others are closed.
C. RTCB ‘A’ and ‘C’ are open, the others are closed.
D. All four are open.
B
Unit 2 is at 100% power with all systems in a normal lineup.
RCB-PT-199B, SPS Pressurizer Pressure Transmitter, fails high.
What is the status of the RTCBs?
A. All four are closed.
B. RTCB ‘B’ is open, the others are closed.
C. RTCB ‘B’ and ‘D’ are open, the others are closed.
D. All four are open.
B
Unit 2 is at 100% power with all systems in a normal lineup.
RCB-PT-101B, Narrow Range Pressurizer Pressure Transmitter, fails high.
What is the status of the RTCBs?
A. All four are closed.
B. RTCB ‘B’ is open, the others are closed.
C. RTCB ‘B’ and ‘D’ are open, the others are closed.
D. All four are open.
A
Unit 3 is at 100% power with all systems in a normal lineup.
RCB-PT-101B, Narrow Range Pressurizer Pressure Transmitter, fails high.
What actions are required (if any) per Tech Specs?
A. No actions are required, as reactor trip coincidence is still available.
B. Immediately bypass Hi Pzr Press on Channel B.
C. Bypass Hi Pzr Press on Channel B within one hour.
D. Bypass Hi Pzr Press, Hi LPD, and Lo DNBR on Channel B within one hour.
D
Unit 1 is at 100% power with all systems in a normal lineup. RCC-PT-101C, Narrow Range Pressurizer Pressure Transmitter, fails low. Consider the following Tech Specs: 1. LCO 3.3.1 condition A 2. LCO 3.3.1 condition C 3. LCO 3.3.5 condition A 4. LCO 3.3.5 condition C Which action statement(s) currently apply? A. 1 only B. 1 and 2 only C. 1 and 3 only D. 1, 2, 3, and 4
A
Unit 1 is at 100% power with all systems in a normal lineup. RCC-PT-102C, Wide Range Pressurizer Pressure Transmitter, fails high. Consider the following Tech Specs: 1. LCO 3.3.1 condition A 2. LCO 3.3.1 condition C 3. LCO 3.3.5 condition A 4. LCO 3.3.5 condition C Which action statement(s) currently apply? A. 1 and 2 only B. 1 and 3 only C. 1, 3, and 4 only D. 1, 2, 3, and 4
C
Unit 2 is at 100% power with all systems in a normal lineup.
RCD-PT-102D. Wide Range Pressurizer Pressure Transmitter, fails low.
The CO bypasses Lo Pzr Press on PPS ‘D’.
Subsequently, RCA-PT-102A, Wide Range Pressurizer Pressure Transmitter, fails low.
Based on these conditions, SIAS has ___(1)___, and the Reactor Trip First Hit light for Lo Pzr Press is ___(2)___.
A. (1) actuated, (2) on
B. (1) actuated, (2) off
C. (1) not actuated, (2) on
D. (1) not actuated, (2) off
C
Unit 1 is at 100% power with all systems in a normal lineup.
RCD-PT-102D. Wide Range Pressurizer Pressure Transmitter, fails low.
The CO bypasses Lo Pzr Press on PPS ‘D’.
Subsequently, RCA-PT-102A, Wide Range Pressurizer Pressure Transmitter, fails high.
The CO presses the BYPASS switch for Lo Pzr Press on PPS ‘A’.
Based on these conditions, PPS ‘A’ Lo Pzr Press is ___(1)___, and PPS ‘D’ Lo Pzr Press is ___(2)___.
A. (1) bypassed, (2) bypassed
B. (1) bypassed, (2) not bypassed
C. (1) not bypassed, (2) bypassed
D. (1) not bypassed, (2) not bypassed
B
Unit 3 is at 100% power with all systems in a normal lineup.
RCB-PT-102B. Wide Range Pressurizer Pressure Transmitter, fails low.
The CO bypasses Lo Pzr Press on PPS ‘B’.
Subsequently, RCA-PT-102C, Wide Range Pressurizer Pressure Transmitter, fails high.
The CO presses the BYPASS switch for Lo Pzr Press on PPS ‘C’.
Based on these conditions, PPS ‘B’ Lo Pzr Press is ___(1)___, and PPS ‘C’ Lo Pzr Press is ___(2)___.
A. (1) bypassed, (2) bypassed
B. (1) bypassed, (2) not bypassed
C. (1) not bypassed, (2) bypassed
D. (1) not bypassed, (2) not bypassed
B
Unit 2 is at 100% power with all systems in a normal lineup.
A steam break causes containment pressure to rise to 5 psig.
Which actuations were generated by PPS directly from containment pressure?
Reactor Trip, SIAS, CIAS, MSIS
Unit 3 is at 100% power with all systems in a normal lineup.
A main steam line break occurs in the MSSS upstream of MSIV 181.
The RO notes the following parameters:
SG #1 level 50% WR and stable (and was never lower)
SG #2 level 26% WR and lowering.
SG #1 pressure 700 psia and lowering.
SG #2 pressure 300 psia and lowering.
As SG #2 level continues to lower, AFAS-2 ___(1)___, and SG #2 auxiliary feed pump discharge valves will ___(2)___.
A. (1) will actuate, (2) open
B. (1) will actuate, (2) stay closed
C. (1) will not actuate, (2) open
D. (1) will not actuate, (2) stay closed
D
Unit 2 is at 100% power with all systems in a normal lineup.
After replacing a light bulb in the ‘A’ Aux Relay Cabinet, the CO inadvertently depresses the TRIP pushbutton for Leg 1-3 of SIAS.
What is the expected plant response?
A. No actuations will occur. The leg trip will reset as soon as the button is released.
B. No actuations will occur, The leg trip will reset as soon as the Leg 1-3 RESET pushbutton is depressed.
C. SIAS ‘A’ components driven by Leg 1-3 will actuate. The leg trip will reset as soon as the button is released.
D. SIAS ‘A’ components driven by Leg 1.3 will actuate. The leg trip will reset as soon as the Leg 1-3 RESET pushbutton is depressed.
A
Unit 3 is at 100% power with all systems in a normal lineup.
The power supply fuse blows for ‘A’ SIAS Leg 1-3, causing a Leg 1-3 SIAS A alarm on B05. What is the expected plant response?
A. No actuations will occur. The leg trip will reset as soon as the fuse is replaced.
B. No actuations will occur, The leg trip will reset as soon as the Leg 1-3 RESET pushbutton is depressed.
C. SIAS ‘A’ components driven by Leg 1-3 will actuate. The leg trip will reset as soon as the fuse is replaced.
D. SIAS ‘A’ components driven by Leg 1.3 will actuate. The leg trip will reset as soon as the Leg 1-3 RESET pushbutton is depressed.
C