Miscellaneous Flashcards

1
Q

How was the L&E claim ‘factored into’ the final account sum? (BM)

A

EoT approved: 5-week extension.
Prolongation basis of claim.
Time related preliminary item rates used.
Weekly cost derived: £1.8k.
Total: Circa £9.5k.
Apply Hudson formula OH% of 5% to the total of the additional prelim costs.
No other request for claims were made however they could have applied for others as well ie. Cost of claim; loss of profit, thickening preliminaries, etc.

Although stating to the contractor and the client that actual costs can be used to determine costs, they both agreed to accept this figure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did you think they could be omitted/changed - what did you base this on? (BM)

A

Reported costs and proposed a meeting.
Agreed to align works with budget.
Marked pricing document with urgency levels.
Created cost matrix with alternatives and potential costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What items did you advise you felt could be omitted or alternative solutions used? (BM)

A

Back of house area redecorations rather than replacement; kitchenette areas was upgraded not replaced; side windows were renovated rather than replaced; UFH cleaned and flushed rather than replaced (Survey Report £25k full replace); omissions also made; replacement of all external paving;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was this ‘new information’ in the addendum concerning M&E? (BM)

A

New M&E surveys conducted.
Focus on AHU.
Refurbishment increased costs by £50k (£65K refurbish AHU instead of the earlier £18k replacement of Hunidifier and controls)
Earlier plan: £18k for humidifier replacement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Company Business Plan?

A

5 years
Invest in employees and working environments; promote happy and productive working environments; invest in technology; improve diversity; provide best service to clients; diversify clients and sectors.
SWOT - S:Offer many services ;W:Narrow range of clients ;O-New Technology; Sustainability;T- Economy/Global Situation
Increase employees by a third (600-900)
Increase turnover and profit. (£93m-£130m)
Profit (£17m-£30m)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the benefits of partnering?

A

The overall construction and design programme is shortened because there is a prior understanding of
the Client and their requirements from previous projects.
o The potential for conflict is reduced.
o Communication is improved.
o Pooling of resources and ideas should result in innovative solutions.
o Improved client satisfaction is gained.
o RECOGNITION OF PROTECTION OF PROFIT MARGIN FOR CONTRACTORS AND SUPPLIERS.
o A team environment is formed that encourages innovation and technical development.
o Improved buildability with early involvement of contractors.
o Better predictability of time and cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key differences between NEC and JCT?

A

The NEC is concise and written in plain English.
* There are a number of optional clauses reducing the need to amend contracts compared to the JCT.
* The Project Manager is presented with options to deal with problems as soon as they become apparent.
* Provision of early warning procedure and risk register encourage a proactive approach to the
management of the project whereas JCT is more reactive.
* Compensation events deal with issues affecting both time and money under NEC whereas under JCT,
variations deals with money and loss and expenses deal with time.
* Changes are based on quotations prior to commitment whenever possible under a rolling final account
under NEC whereas under JCT agreement of costs can be left to the very end of the project.
* Cost of compensation events are calculated using schedules of actual costs rather than bill rates under
JCT.
* There is no QS or Employers Agent mentioned in NEC only a Project Manager who takes on both
roles.
* The Programme is a contract document under NEC with 25% of money being deducted on interim
payments if the contractor does not submit an accepted programme at contract stage.
* The NEC has no provision for nomination of sub-contractors but preferred sub-contractors can be
listed within the Works Information.
* The Defects correction period has different periods specified depending on the impact of the defect
under NEC where the contractor must “make good” in these time periods. This approach is much
better at dealing with defects when compared to JCT.
* Short periods of reply are adopted under NEC which incentivise the parties to respond to each other
however is reality the NEC maybe considered as very administration heavy.
* Retention and delay damages are optional clauses under NEC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Client Drivers - value for money?

A

Most benefits derived from cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What were these minor roof repair works? (BM)
The values?

A

Clerestory window repairs
Additional lead repairs and replacement
Installation of additional hoppers
Replacement of weatherboarding
Upgrading rainwater goods with 5ln guttering and downpipes

£30k total

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What sort of strategies for managing these risk were proposed? (HCW)

A

Engagement initiatives: team meetings, events, drop-ins, associations
Resident profiling: assess needs, preferences, vulnerabilities
Communication plans: tailored for each project stage
Customer care: training, conduct standards
Complaints management: surveys, prompt resolution, improvement strategies
Dedicated contact point: for resident communication and issue tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was discussed at the ‘pre-start meeting’?

A

Introduction and attendance
Health and safety briefing
Review of project scope, schedule, and milestones
Site rules and access arrangements
Construction methods and sequencing
Coordination of subcontractors and suppliers
Quality control and inspection procedures
Communication protocols and reporting mechanisms
Environmental considerations and waste management
Any specific project risks or issues to address before starting work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why might there be ‘loss and expense claims from the original contractor’?

A

Disruption and Delay: The omission may disrupt the contractor’s planned sequence of work, leading to delays in completing the remaining scope of works.
Resource Reallocation: The contractor may have allocated resources and manpower based on the original contract scope, and the omission requires reallocating resources or remobilizing, incurring additional costs.
Reduced Efficiency: Working on a reduced scope of works may decrease productivity and efficiency, leading to increased labor and overhead costs.
Extended Duration: The contract duration may be extended due to the omission, resulting in prolonged site overheads and additional supervision costs.
Contractual Entitlement: The JCT Intermediate Contract provides for the contractor to claim for loss and expense resulting from variations, including omissions, subject to meeting notification and substantiation requirements.
Overall, the contractor may argue that the omission of a significant portion of the works has impacted their ability to perform efficiently and has resulted in additional costs, entitling them to claim for loss and expense under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What ‘times of the year’ does it sit?

A

The frequency of procurement cabinet meetings can vary depending on factors such as the volume of procurement activities, the urgency of procurement needs, and the administrative schedule of the authority. Typically, these meetings might occur on a regular basis, such as monthly or quarterly, to ensure effective oversight and decision-making in the procurement process

[There is also usually a requirement to book a slot to be seen by the committee in advance and these bookings may already be taken]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why was ‘cost’ the main driver, then time, and then quality, exactly?

A

Firstly, as a publicly funded project, cost efficiency is essential to ensure optimal use of taxpayers’ money and to meet budget constraints set by the council.

Secondly, programme duration is critical to minimize disruptions to residents’ lives and to ensure that essential services are maintained throughout the refurbishment process.

Finally, while quality is important for ensuring the longevity and functionality of the facility, compromises in quality may be acceptable if they do not compromise safety or essential services, allowing the project to be completed within budget and on schedule.

Prioritizing these factors allows the council to achieve its objectives of delivering necessary upgrades to the facility while efficiently managing resources and minimizing inconvenience to residents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a ‘control methodology’?

A

Systematic approach to manage changes to the contract scope, ensuring adherence to budgetary constraints and timely completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does ‘effectively manage and plan the developing scope’ mean?

A

Systematically analyzing, organizing, and adjusting project requirements as they evolve, ensuring alignment with project objectives, resources, and constraints while minimizing disruptions to progress and budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why was it made? (EoT; BM)

A

Bullet-pointed reasons for delays.
10 causes submitted with explanations and durations.
Primarily late confirmation on CDP items - ie blinds spec, CAT ladder locations, south elevation and internal changes following RIW waterproofing solution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What was the rate of ‘Liquidated Damages’? How did the Client calculate this figure?

A

LADs £1,663.39/week

Client used a standard formula designed for their projects based on contract sum and associated Finance and Professional Costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Examples of your implementing rules of conduct eg acting with integrity?

A

Rule 1: Final Accounting - including any ‘missed’ costs.
Rule 2: Only providing advice where I am competent - eg recommending possible work options but not specifying any works.
Rule 3: Understanding what is required of me and providing my full attention together with QA procedures eg Recommendations for Payment.
Rule 4: Respecting all people I encounter within my role paying proper consideration and unbiased actions eg undertaking negotiations.
Rule 5: Identifying and calling out any improper actions eg unsafe practices on site, asking to stop, and reporting to person in charge.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the definition of Bribery?

A

Inducement for an action which is illegal, unethical, or a breach of trust.
Something in return for an advantage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How did you present advice in your case study? (really high level)

A

-I summarized the problem and key issues
-Proposed options and the reasons for them
-Ran through the positives and negatives
-Offered the best solution based on which best addressed the client’s goals and priorities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are ‘Reckoning Days’ and what do they allow for?

A

The days identified in the contract for matters such as issuing notices, issuing certificates, etc
Allow for bank holidays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the ICMS? (really high level)

A

international Cost Management Standards

International measure on lifecycle costing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Case Study - ‘managing residents’ - what does this involve? (really high level)

A

-Protecting the works site ie hoarding, barriers, signs
-General updating of residents of works being undertaken and progress
-Procedures in place to register resident concerns/complaints handling eg contact details, liaison officer, catchup meetings,
-Accommodating resident needs during the works eg providing use of facilities as much as possible (laundry - evenings)

25
Q

What is a Relevant Matter? (get in key phrase ‘materially affects progress’)

A

Items listed in the contract which ‘materially affect progress’ of the works and allow the contractor to claim for loss and expense.

26
Q

Cost submissions by ‘quotations’ - how could you be certain value for money was obtained? (consider number; formality, acquaintance, doctoring)

A

Risk:
-contractor could go to ‘own’ subcontractors where have ‘relationship’
-contractor go to ‘anyone’ with high quote
-contractor ‘doctor’ quote

Precautions:
-recommend subcontractors/suppliers
-have an ‘approved’ subcontractor/supplier list
-check that quotations correlate with ‘cost data’, VfM checks on current market
-Quotation/invoice documentation contains all details including name of project/property/works to be undertaken/specifications/terms and conditions
-Quotations/invoice documentation forwarded on direct from the subcontractor/supplier, avoiding any ‘doctoring’.

27
Q

BM: What were the CDP items?

A

Vent grilles to plant rooms
Lead sheet flashings
Modifications to services
Blinds specification/mechanism of operation
Access ladder to roof (CAT ladder)
Mansafe system
..

28
Q

What is Ridge’s Business Plan?

A

Ref other Flashcard Decks. Is one somewhere on Ridge’s Plan eg turnover/profit from £90M to £130M;….

29
Q

What is the difference between sarnafil roofing and bauder roofing

A

Sarnafil roofing uses single-ply PVC membranes for durability and weather resistance, ideal for flat roofs. Bauder roofing offers various systems, including bituminous membranes, single-ply membranes, and green roof solutions, focusing on comprehensive waterproofing and insulation options for different roof types.

30
Q

BM: How did you advise the savings on the alternative waterproofing proposal? Did you also consider the programme implications? (general note: consider the cost implications/value for money for all construction items/variations/proposals)

A

Refer to other Decks.

However:
-identified alternative approach possible (experience with RIW before, aware of basement tanking internal or external)
-Identified all works that could be omitted from the original proposal together with the associated costs.
-Identified probably works required (refer to actual works required), and budgeted cost and potential changes to programme and duration.
-calculated total change in costs ie original omitted v new works and L&E/duration.
-Advised savings. (which was circa £10k??)

31
Q

How do you stay up to date? (articles - modus now online read, ridge updates, CDP, registered with CDP providers, training needs, performance reviews, client feedback)

A

Populate this:

Modus (now online)
Building Magazine
Updates from company on intranet and notifications
CPD Providers
Reviews with senior managers
Career Planning (currently APC attainment)
…..
..

32
Q

RICS Rules of Conduct - which rule is most important to you?

A

Rule nr 1 - acting with honesty and integrity. and complying with professional standards Without this all other rules become meaningless.

33
Q

Corruption - what procedures should be implemented for countering bribery and money laundering?

A

Ref other flashcards.

As Guidance Note/Professional Statement - Countering Bribery, Corruption, Money Laundering….

Guidebook:
Proportionate measures
Top Level Commitment
Risk Assessments
Due Diligence
Communication
Monitoring

34
Q

Tip: Ethics - know ‘gift’ scenarios.

A

Key:
-Proportionality
-Timing
JB: normal course of business?

35
Q

BM: What is a Chiller?

A

Ref Guidebook Flash Cards

A component of an …. AC System.
Powered by area which has own gas generators
Cools water in pipes which circulates within air ducts cooling the nearby air.

36
Q

RICS guidance on Bribery?

A

Guidance Note/Practice Note: Bribery, Corruption, Money Laundering….

37
Q

Of the RICS, who:
-the President?
-the President Elect?
- the Vice President?
-the CEO?

A

Refer to other flashcards.
Tina Paillet
Justin Sullivan
Nicholas McClean
Justin Young

38
Q

What RICS Committees are there?

A

Note: Hot Topic 2024 - Governance and Management Structure undergoing reform.

Privy Council
Royal Charter
Governing Council (Bye Laws)
Management Committee; Regulation and Standards Committee; Auditing Board;
New Committes - as above?, plus?:
- Diversity and Inclusion?; Sustainability?; Young persons?;

39
Q

Difference between a cost plan at stage 2 and stage 4?

A

Stage 1 Cost Plan:
Initial estimate during Preparation and Brief.
Rough order of magnitude costs based on project outline.

The Order of Cost Estimate is typically produced during Stage 1: Preparation and Brief of the RIBA Plan of Work. This initial estimate provides a rough cost projection based on the project’s early scope and objectives, setting the foundation for more detailed cost planning in subsequent stages.

Clarification:
-Order of Cost Estimate: Produced during Stage 1, it provides an initial, high-level cost projection based on early project information and assumptions.
-RIBA Stage 0 (Strategic Definition): At this stage, the Order of Cost Estimate provides an initial, high-level cost projection based on very early project information, helping to establish feasibility and budget considerations before detailed planning begins in Stage 1.
-Cost Plan: Developed in more detail during subsequent stages (Stages 2 to 4), it involves detailed breakdowns and more accurate estimates as the project design and specifications become more defined.

Stage 2 Cost Plan:
Concept Design phase.
Preliminary cost estimates based on overall scope and early design.

Stage 3 Cost Plan:
Developed Design phase.
More detailed costs, including specific elements and materials.

Stage 4 Cost Plan:
Technical Design phase.
Highly detailed and accurate, based on finalized design, item costs, and quantities.

40
Q

JCT Practice Note - Pricing Options? (A-BoQ/SoW; B-Formatted and prepared by contractor in submision)

A

Check this:

Pricing Option A - BoQ/SoW prepared by client
Pricing Option B - Formatted and prepared by contractor on submission

41
Q

What is the process for imposing LADs on the contractor?

A

1 - Client notify contractor intend to impose LADs and validity of doing this.
2 - Client issue a Pay Less Notice (at least 5 days before final date for payment), identifying reasons and calculation of cost imposition.
3 - Issue payment, subtracting LAD costs notified.

42
Q

SH: What laws relate to construction generally?

A

Certainly, here are the headings for the laws and regulations in the UK related to construction work:

Health and Safety at Work Act 1974
Construction (Design and Management) Regulations 2015 (CDM 2015)
Building Regulations 2010
Control of Asbestos Regulations 2012
Construction Products Regulation 2011
Planning Act 2008
Equality Act 2010
Environmental Protection Act 1990
Party Wall etc. Act 1996
Landlord and Tenant Act 1985
Workplace (Health, Safety and Welfare) Regulations 1992
Control of Noise at Work Regulations 2005
Control of Substances Hazardous to Health Regulations 2002 (COSHH)
Manual Handling Operations Regulations 1992
Electricity at Work Regulations 1989
Provision and Use of Work Equipment Regulations 1998 (PUWER)
Personal Protective Equipment at Work Regulations 1992
Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013 (RIDDOR)
Fire Safety Order 2005
Clean Air Act 1993

43
Q

What is a Conflict of Interest? (‘impacts ability to act impartially)

A

Can be a very very simple statement:
Something which impacts ability to act impartially.

44
Q

Handling Client’s Money? (ledger; permission before transacting; % interest belongs to client - agree how to be used; obtain insurance from RICs - Money Protection Scheme)

A

As other Flashcards, but also ensure mention:

Ledger
Permission for transactions
% interest - what do with it (belongs to client)
Obtain RICS insurance (Money Protection Scheme)

45
Q

Did you compile the risk register?

A

(Be careful with this, you wouldn’t compile this from scratch)

46
Q

Option 2
How CDM would be managed with two contractors? How two contractors on site be managed generally?

A

(along lines of overlap but separate)

47
Q

Option 3
How go about a negotiation?

A

-Identify the issue
-Research and source relevant information
-Assess the appropriate action and in discussion with client/project partners if necessary
-Identify other parties possible positions and how these will be dealt with
-Identify ‘red lines’ and areas of compromise
-Conduct the negotiation in a calm environment, allowing everyone their say, respecting the other party, and endeavouring to reach an amicable agreement in the best interests of the all parties and the project.

48
Q

Do the RICS need to get involved in complaints?

A

The RICS will only become involved if the firm fails to respond to a complaint or prevents the client from gaining access to an independent redress mechanism

49
Q

A client phones you up and says he is dissatisfied with your cost report. He is very unhappy about it and refuses to accept it. What action would you take?

A
  1. Communicate to understand the reason for the complaint
  2. Attempt to resolve the issue through negotiation
  3. Refer client to firm’s CHP if no resolution can be found
  4. Respond to the complaint in a timely manner
  5. Keep a log of the complaint

(Good, just be more succinct - try to resolve, rectify any mistake as you stated. Don’t forget to mention Complaints Handling procedure)

50
Q

What must a firm have in place in relation to money laudnering and terrorist financing?

A

Policy for

51
Q

Wcan you give an example of some of the RICS Committees?

A
52
Q

Can you give an exmaple of some of the changes within the industry at the moment - curent event / news?

A
53
Q

What is Corporate Social Responsibility?

A

(strategies encourage the company to make a positive impact on society and the environment)

54
Q

What types of Statements should a company have on file?

A

(Slavery and Human Trafficking Statement, Equality and inclusion etc)

55
Q

How does your firm comply with the Modern Slavery Act 2015?

A

(Group procurement policy defining minimum standards when procuring goods or services
Whistleblowing policy
Training and awareness
Corporate responsibility policy)

56
Q

What is unconcious bias?

A

(Learned stereotypes that are automatic, unintentional, deeply ingrained, universal, and able to influence behavior)

57
Q

What FOUR points must be contained within a companies Health & Safety policy?

A

(1. A policy setting out the organisations commitment to Health and Safety
2. Details of the organisation’s Health and Safety structure, with roles and responsibilities for organising Health and Safety
3. A risk assessment setting the risk within the workplace and the preventative measures in place
4. Details of the planning, implementation of the Health and Safety Policy and control measures)

58
Q

What was the Hackitt Review?

A

(Led by Dame Judith Hackitt, reported in May 2018
Independent Review of Building Regulation and Fire Safety, called “Building a Safer Future”
Made over 50 recommendations for changes to ensure a more robust regulatory system)