Alex Spring 10.05.24 Flashcards

1
Q

What is a risk?

A

SH: something which may occur that will have a negative impact on the project’s/client’s goal.

SH: In terms of Risk Register? - the probability of the risk identified occuring ie therefore ‘risk analysis’ where probability of something occuring is analysed?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an ‘incident’?

A

Something which has occured??
SH: with an associated impact ie cost and time implications? Contingency spent?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you ‘score’ risk? (heat charting)

A

SH: not EMV (Estimated Monetary Value), but, grading of potential impact ie big or small (priority of needing to deal with)? So, Cost (1-5) x Probability (1-5) = High (25); Low (2)?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you ‘quantify’ risk? (the probability)

A

SH: Identification of likelihood of occuring / identify probability of occuring? therefore probability analysis?

or,
Quantify = cost x probability (EMV)?
Qualify = cost severity x probability?

Ref flashcard below.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you apportion/deal with risk? (eg reduce, transfer, etc)

A

Refer to other flashcards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is risk ‘quantified’ and ‘qualified’? (quantified - cost x probability ie EMV; qualified - heat chart ie impact severity)

A

As flashcard above?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What types of structural frames are there?
What costs are associated with these?
What are the advantages/disadvantages of each?

A

Types and Adv/Disadv - As other flashcards.

Costs - ????????

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the difference between the JCT and NEC?

A

As other flashcards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Relevant Event? (entitled to EoT; no one at fault)

A

As other flashcards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Relevant Matter? (entitled to EoT and L&E; cost claim justified)

A

As other flashcards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Differences between JCT Minor and JCT Intermediate?

A

As other flashcard (somewhere - Guidebook?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Difference between a CA and and EA?

A

As other flashcard (Guidebook?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

JCT Practice Note - Pricing Options? (A-BoQ/SoW; B-Formatted and prepared by contractor in submision)

A

Check this:

Pricing Option A - BoQ/SoW prepared by client
Pricing Option B - Formatted and prepared by contractor on submission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is LAD?
How assess LAD on your project (high level)

A

Liquidated Ascertained Damages.
Figure in contract particulars identifying imposition of costs on the contractor if fail to reach completion date.
Based on realistic costs
Calculated by Client
Assess - to check if reasonable - review ‘heads of claim’ costs client used - heads of claim applicable? costs realistic?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the process for imposing LADs on the contractor?

A

1 - Client notify contractor intend to impose LADs and validity of doing this.
2 - Client issue a Pay Less Notice (at least 5 days before final date for payment), identifying reasons and calculation of cost imposition.
3 - Issue payment, subtracting LAD costs notified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly